Court of Appeals of Oregon, 2023

Kizer Excavating v. Stout Building Contractors

Kizer Excavating v. Stout Building Contractors
Court of Appeals of Oregon · Decided May 3, 2023 · Egan
325 Or. App. 642; 529 P.3d 1024

Kizer Excavating v. Stout Building Contractors

Opinion

On appellant’s petition for reconsideration filed February 28, respondent’s response filed March 8, opinion filed February 15, 324 Or App 211, 525 P3d 883 (2023); reconsideration allowed, opinion modified and adhered to as modified May 3, 2023

KIZER EXCAVATING CO., an Oregon corporation, Plaintiff-Appellant Cross-Respondent, v. STOUT BUILDING CONTRACTORS, LLC, a Utah limited liability company, Defendant-Respondent Cross-Appellant.

Clackamas County Circuit Court 20CV17226; A177168 529 P3d 1024 Plaintiff Kizer Excavating Co. seeks reconsideration of the Court of Appeals opinion holding that the trial court erred in determining that plaintiff could recover damages on its quantum meruit claim, and holding that defendant Stout Building Contractors, LLC, the general contractor, is entitled to judgment and attorney fees on plaintiff’s breach of contract claim. Kizer Excavating v. Stout Building Contractors, 324 Or 211, 525 P3d 833 (2023). Held: The Court of Appeals allowed reconsideration to correct a misstatement at 324 Or App at 219 n 2, that plaintiff did not dispute that defendant’s challenge in its first assignment of error on cross-appeal was preserved. Plaintiff did, in fact, argue that the argument made in the first assignment of error was not preserved. As the court had pre- viously noted at 324 Or App at 219 n 2, given the way the case was tried, the argument made in the first assignment of error was preserved. But the court corrected the footnote to delete the statement that plaintiff did not dispute that defendant’s challenge was preserved.

Reconsideration allowed; opinion modified and adhered to as modified.

Susie L. Norby, Judge.

Paul B. Barton, Alexander Graven, and Olsen Barton LLC, for petition.

Holly E. Pettit, Peter J. Viteznik, and Kilmer, Voorhees & Laurick, PC, for response.

Before Egan, Presiding Judge, and Kamins, Judge, and Hadlock, Judge pro tempore.

Cite as 325 Or App 642 (2023) 643 EGAN, P. J.

Reconsideration allowed; opinion modified and adhered to as modified.

644 Kizer Excavating v. Stout Building Contractors EGAN, P. J.

Plaintiff Kizer Excavating Co., an excavation sub- contractor on a commercial construction project in Dallas, Oregon, seeks reconsideration of our opinion holding that the trial court erred in determining that plaintiff could recover damages on its quantum meruit claim, and holding that defendant Stout Building Contractors, LLC, the gen- eral contractor, is entitled to judgment and attorney fees on plaintiff’s breach of contract claim. Kizer Excavating v. Stout Building Contractors, 324 Or 211, 525 P3d 883 (2023).

We write to allow reconsideration to correct our misstate- ment at 324 Or App at 219 n 2, that plaintiff did not dispute that defendant’s challenge in its first assignment of error on cross-appeal was preserved. Plaintiff did, in fact, argue that the argument made in the first assignment of error was not preserved. As we previously noted at 324 Or App at 219 n 2, given the way the case was tried, we conclude that the argu- ment made in the first assignment of error was preserved.

As corrected, the footnote now reads: “We view defendant’s argument as the equivalent of a con- tention that the court mis-instructed itself on the law in concluding that the denial of the change order rendered the additional excavation extracontractual. Given the manner in which the case was litigated, we conclude that defen- dant’s challenge is preserved.”

Reconsideration allowed; opinion modified and adhered to as modified.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.