Manerud v. City of Eugene
Manerud v. City of Eugene
Opinion of the Court
delivered the opinion of the court.
There are fifty-one assignments of error noted in the abstract. It is impossible within the limits of an ordinary opinion and, considering the nature of some of them, unprofitable, to examine all these alleged errors. The essence of plaintiffs’ grievance, as stated, is that the city *205 entirely failed to comply with part of its contract and was dilatory in what it did perform. Without going into the elaborate detail which would be necessary in a minute consideration of the plaintiff’s numerous objections, we must content ourselves with some general observations upon the construction proper to be given to the contract involved.
“The contractor shall not be entitled to damages on account of delay, but if such delay be occasioned by the city the contractor shall be entitled to an extension of time in which to complete the work, to be determined by the engineer.”
“The city of Eugene shall have the right to make any changes in the plans, grades or lines that it may deem necessary, after the contract is awarded. If the changes diminish or add to the quantity of work to be done under the contract, the contractor shall be paid at the contract price for only the actual amount of work done, as herein specified.”
This furnishes the rule for compensation of the plaintiffs for increased work done on account of the alleged changes. True enough, it is said in the complaint that the defendant and its engineers frequently changed the lines and grades of the canal, thereby causing great loss of time and extra work, and required plaintiffs to increase the height of the embankment after the same had been completed according to contract. But whether that resulted in ten yards of excavation or fifty yards increased fill on the embankments is not stated. Such data as this are necessary in order for the court to determine the amount of compensation which should have been awarded to the plaintiff on account of extra work, if any was *206 required by reason of the changes made by the direction, of the defendant’s engineer.
“The contract prices shall include all labor and expense necessary to complete the work according to the plans and specifications on file in the office of the city recorder of the city of Eugene, and to maintain it in good condition until accepted by the engineer.
Owing to the fact that the plans are not set out in the bill of exceptions, we are unable to construe them, and, if we were thus equipped, it is a sufficient answer to the contention of plaintiffs in this respect that if the delineations were not wrought out in detail enough to meet their approval they ought not to have engaged on such drawings to build the canal. According to their contract, these plans and specifications were on file in the office of the city recorder, a matter of public record which they could consult before undertaking the work. Then was the time to object to the sketches and require them to be worked out in greater detail. It is too late, after having signed the contract, to urge that objection.
*207
The record discloses no statement in the pleadings, nor, so far- as the bill of exceptions shows, any evidence of knowledge on the part of the defendant of the alleged custom or any statement that it is of such general notoriety as would authorize us to indulge the presumption that the defendant was aware of or contracted with reference to it.
There were sundry instructions given by the court, of which the plaintiffs complain, all relating to what would amount to an abandonment of the work by the plaintiffs or what would excuse them from the imputation of such fault. These become unimportant in view of the fact that the jury found the issue on that subject in favor of the plaintiffs and rendered a verdict against the defendant.
There are many other unimportant assignments of error, such as asking leading questions and receiving answers thereto, all of which are largely within the discretion of the court, apparently not abused in this instance. They are not sufficient, however, in our judgment to affect the result, and hence the judgment must be affirmed. Affirmed.
Reference
- Full Case Name
- Manerud v. City of Eugene.
- Cited By
- 8 cases
- Status
- Published