Urban Plumbing & Heating Co. v. Erwin
Urban Plumbing & Heating Co. v. Erwin
Opinion of the Court
Plaintiffs, who are contractors, retained defendant, a lawyer, to represent them in a claim against the federal government arising out of a modification of a heating plant on an Air Force base. After much litigation, total recovery amounted to $129,161.17, which included $90,139.17 in excess of the contract price for additional work, and $39,022 “retainage,” a percentage of the contract price retained during construction to protect the government against certain contingencies.
Plaintiffs brought a declaratory judgment proceeding to determine the amount of defendant’s fee. Defendant, also, requested a determination of his fee and asked the court to foreclose a lien upon plaintiffs’ bank account for whatever amount it found to be due defendant.
Plaintiffs claimed there was to be a 40 per cent fee on all sums recovered over the contract price and no fee on the “retainage.” Defendant claimed there was to be a 50 percent fee on all sums recovered over the contract price and a 20 per cent fee on the “retain-age.” The trial court found that the fee, by agreement, was 40 per cent on the amount recovered in excess of the contract price and 20 per cent on the “retainage.” Defendant appeals, contending now that he is entitled to 40 per cent on the “retainage” instead of 20 per cent as he originally pleaded.
. Upon appeal, there is no contention, as there was at trial, that a declaratory judgment proceeding is an improper proceeding by which to litigate the present issue. • .
Defendant first asserts that at the commencement of trial the parties stipulated the court could find that
Defendant next argues that because plaintiffs testified there was to be a 40 per cent fee on the total recovery (at variance with their contention) and because they denied there was any agreement for a fee of 20 per cent on the $39,022 “retainage,” plaintiffs are responsible for a fee of 40 per cent on the “retain-age.” Assuming that plaintiffs’ testimony is capable of such a construction, defendant ignores his pleading and testimony to the effect that he agreed to accept a 20 per cent fee on the “retainage” and that it was paid. Defendant argues that plaintiffs either waived the benefit of the agreement for the reduction of the fee on the “retainage” or are estopped to assert it. The logic of defendant’s argument escapes us. We know of no application of the laws of estoppel or of waiver which justifies th.e result for which defendant contends.
Defendant’s argument..seems to be that plaintiffs
Defendant also argues there was no consideration for his agreement to reduce his fee on the “retain-age.” However, he testified that his fee was requested and received by him in advance of the time it normally would have been due.
After the issuance of the court’s memorandum opinion, plaintiffs paid sufficient money into court to pay defendant’s judgment with the exception of a small amount for costs and interest. Because of such payment, defendant has indicated that unless his judgment is increased upon appeal, he is not particularly concerned about his second assignment of error which relates to the court’s ruling that he had no lien on plaintiffs’ bank account.
The judgment of the trial court is affirmed.
Reference
- Full Case Name
- URBAN PLUMBING & HEATING CO. v. ERWIN
- Status
- Published