Harrisburg v. Mish
Harrisburg v. Mish
Opinion of the Court
Opinion by
By an ordinance of councils approved December 2, 1893, it was ordered that Cameron street between certain points be graded; that a contract to do the work and furnish the materials be awarded to the lowest responsible bidder; that the cost of the work be assessed upon the abutting properties in proportion to the number of feet each property fronts on said street; and that at the expiration of thirty days after the completion, approval and acceptance of the work, the proper officers “ make and issue to the contractor improvement bonds in the usual and proper form, with coupons attached, for the amount of the assessments outstanding, which bonds shall rest alone upon and be payable out of said assessments, and from no other fund.”
In the contract subsequently awarded, the city agreed to pay the contractor “ the sum of $6,972.50, the assessments levied upon the properties,” as follows: “ So much of the said assessments as may have been paid into the city treasury, in cash, and for the balance of the said $6,972.50 due him will assign and transfer or mark to his use, so much of said unpaid assessments as is equivalent to the amount due him, and the city of Harrisburg shall not be further liable to said contractor, James Nalen whether said assessments are collectible or not. Or if the ordinance authorizing said work so specifies and directs, and the. contractor shall prefer, he shall be paid from time to time in cash such sums as shall be estimated for by the commissioner of highways upon his warrant duly countersigned by the city controller, out of the assessments paid into the city treasury, and from no other fund.” Then follows a provision for the issuing of bonds in the exact words of the ordinance, which we have quoted, and then this clause: “ They shall be issued in denominations of $100, be numbered seriatim, bear interest at the rate of five per centum per annum payable semiannually out of assessments, .... and shall be called in and
A scire facias was issued upon the municipal claim filed against the defendant’s property, and upon the trial of the issue the contract, the assessment and the claim were offered in evidence and objected to upon the ground that the contract lacked the controller’s certificate. At the conclusion of the evidence the objection was renewed in the following point: “ The alleged contract between the city of Harrisburg and its contractor under which the improvement of the roadway called Cameron street was made, the cost of which was, in part, assessed upon the property of the defendant, involved an appropriation of money and, on its face, designated the items of appropriation on which it was founded. The supposed contract was not certified by the city controller of the city of Harrisburg, as required by section 5, article 9 of the act of assembly, approved May 23, A. D. 1889, P. L. 277, and therefore never took effect as a contract and no lien, assessment or other charge can be made upon or against defendant’s property by reason of anything done under said supposed contract, and there can be no recovery against defendant in this case.” The court was also requested to charge that upon all the evidence there could be no recovery against the defendant. A verdict was rendered for the plaintiff subject to the decision of the court upon the reserved questions raised by these two points, and subsequently the defendant’s motion for judgment non obstante veredicto was overruled and judgment entered for the plaintiff.
Section 5 of article 9 of the Act of May 23,1889, P. L. 277, 303 provides as follows: “ Every contract involving an appropriation of money shall designate the item of appropriation on which it is founded, and the estimated amount of the expenditure thereunder shall be charged against such item and so certified by the controller on the contract before it shall take effect as a contract, and the payments required by such contract shall be made from the fund appropriated therefor. ... It shall be the duty of the controller to certify contracts for • the payment of which sufficient appropriations have been made.” It will be well to notice in this connection that section 7 of article 4 of the same act provides that, “ no money shall be paid
The question whether or not such a contract as this “ involves ” or is “founded ” on an “appropriation of money” within the meaning of section 5 of article 9 of the act of 1889 arose, and was fully argued by counsel in Harrisburg v. Shepler, 7 Pa. Superior Ct. 491, and we decided the case upon the assumption, but not without consideration of the question, that the section applies to such a contract. The judgment was affirmed by the Supreme Court on appeal, reported in 190 Pa. 374. Not to claim for that case greater authority as a binding and conclusive adjudication of the question than it is entitled to, it is proper to say — and this is shown by the reports of the case— that the judgment must necessarily have been the same, even if it had been held that the section does not apply to a contract to which the liability of a city is restricted to the amount of the assessments actually collected and paid into the city treasury. We have, therefore, considered it, as if it were still an open question, but without reaching a different conclusion from that plainly intimated in the former case. What we have to sajr upon the subject is but a repetition, with slight changes, of what was said in that case. Construing the ordinance and the contract together, it is seen that three things were contemplated : first, an engagement by the city to pay the cost of the improvement out of a fund to be raised by the city by assessments on abutting properties according to the “ front-foot ” rule; second, an appropriation to the payment of the cost of the improvement of the fund of money that would thus be raised by local and special taxation; third, an exemption from liability beyond the amount actually collected by the city from this source. The scheme did not contemplate a discharge of the city from liability by merely assigning to the contractor the claims against abutters, unless the contractor so elected, which he appears not to have done. In other words, the contractor was not bound to take the claims in full payment of the contract
It follows, that, without the certificate of the controller, there could be no recovery against the property owners. This was clearly and unequivocally decided in Erie City v. Moody, 176 Pa. 478, and there was nothing said or decided in Harrisburg v. Shepler in conflict with that ruling. In the former case the controller’s certificate was indorsed on the contract but was incomplete. It was argued that as the company had paved the street, and the city with knowledge of all the facts had accepted the pavement, approved of the assessments made for the cost thereof, paid for the street intersections and in every manner recognized the validity of the contract, the property owner could not go behind their acts and set up a technical defense that the parties to the contract had waived. The court refused to adopt this view, and held that there could be no recovery.
The judgment is reversed, and judgment is now entered for the defendant upon the reserved points non obstante veredicto.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.