Wymard v. Deeds
Wymard v. Deeds
Opinion of the Court
Opinion by
The plaintiff was subcontractor under defendants for the stone work and, under a separate agreement, for the concrete and granolithic work of a public school building which the defendants had contracted, under an agreement with the public school authorities, to erect. After the plaintiff had completed his contract, as he alleged, he brought suit to recover a balance alleged to be due under his several agreements with the defendants.
Defendants, in their affidavit, set out two grounds of defense, arising under the contract for the stone work, alleging that the plaintiff had failed to perform his contract in all of its
The plaintiff resisted these reductions, first, because they were not proper under the facts, as they were shown in relation to his contract. Second, that, being in the nature of a set-off, they could not be given in evidence, because that, under Rule 8 of the courts of Allegheny county, the notice required under section 3 thereof had not been given to the plaintiff, and third, that, under the stipulation in the agreement between plaintiff and defendants, relating to arbitration, the plaintiff was not bound thereby, because (a) the clause “any other matter should arise, relating to this contract wherein first and second parties cannot agree ” did not include work omitted to be done, and (5) that the reference to the architects, Messrs. E. J. Car-lisle & Company, who were made sole arbitrators, whose decision was to be final, did not specify individual arbitrators and was, therefore, uncertain and void. These contentions, on the one side and on the other, make up the subject in controversy, although the assignments of error number eleven.
The court below ruled that the claim for damages, by reason of delay, was liquidated and was the subject of set-off; that, no notice of it having been given under the rule, it could not be given in evidence, and that the plaintiff was thereby entitled to recover to that extent, but that the amount claimed for work omitted to be done under the direction of the architect was not set off, and that it was the legitimate subject of defense. A verdict was rendered for $229, upon which judgment was entered. Plaintiff alone appealed. We are not, there
The testimony was very clear that the plaintiff was notified not to deliver stone for the footings, as they are called, which we take it to be the foundation under the ground, and that no stone of that kind had been delivered or was upon the ground, when the contract was completed, nor was there stone used in the erection of other portions of the wall above the surface on the ground, after the work was done. The architect testified to the amount of the stone work rendered unnecessary by reason of the foundation being found sooner than anticipated, and provided in the specifications and the value thereof, under the contract. This was clearly not set-off. It was incumbent upon the plaintiff to show that he fulfilled his contract in every respect, in order to enable him to recover, and it was entirely legitimate for the defendant to show that the contract had not been fulfilled. In general “ set-off takes place only in actions and contracts for the payment of money, as assumpsit, debt and covenant, and where the claim set off grows out of a transaction independent of the contract sued on: ” 2 Bouvier’s Law Diet. 988. In Pennsylvania, however, set-off is the subject of statutory regulation, and is as follows : “ If two or more dealing together be indebted to each other upon bonds, bills, bargain, premises, accounts or the like, and one of them commence an action in any court of this province, if the defendant cannot gainsay the debt, bargain or assumption upon which he is sued, it shall be lawful for such defendant to plead payment of all or part of the debt or sum demanded and give any bond, bill, receipt, account or bargain in evidence,” etc. 1 Sm. L. 49, sec. 1. The general rule is herein clearly indicated. The defendants here by their defense endeavored to gainsay the bargain or assumption upon which the plaintiff sought to recover. The court below was, therefore, clearly right, at least to the extent of holding that the portion of the claim relating to work not done was a legitimate defense of which notice, other than that contained in the affidavit of defense, was not required.
Andrew McMasters was shown to have been a member of the firm of E. J. Carlisle & Company. He was the architect in charge of the work, recognized as such by plaintiff and defendants, and was shown to have made the calculation of the materials and work omitted to be furnished and done, and was sufficiently indicated in the agreement as arbitrator, being included in the firm of E. J. Carlisle & Company, although his individual name was not mentioned. This question does not seem to have been raised specifically in the court below and the ninth assignment of error, which relates thereto, is not in accordance with our rule, as it does not show where or how or when or in what manner the court held: “ That E. J. Carlisle & Company, were specific persons, so as to make a reference to them as arbitrators valid and binding on the plaintiff who did not know who composed the firm of E. J. Carlisle & Company.” This
Considering the whole case, the appellant certainly has nothing of which to complain.
Judgment affirmed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.