Allen v. Swarthmore Borough
Allen v. Swarthmore Borough
Opinion of the Court
Opinion by
The permit under which plaintiff connected his premises with public sewer was in the form adopted by the sewer committee ; it was signed by the highway and sewer inspector, he being the proper officer, as shown by the form adopted by the committee, as well as by the fact that the book containing the permit blanks drawn in this form, was delivered to him by his predecessor pursuant to the written order of the sewer committee; and the plaintiff paid the proper permit fee to the inspector, who paid it to the borough treasurer. The language of the ordinance is, that the permit shall be “ signed by the borough engineer or the duly authorized agent of the sewer committee,” which was done, and “ shall be issued by the secretary of the council under the regulations of this ordinance, in the form adopted by the sewer committee.” It is objected that the permit was not issued by the secretary. The undisputed facts are, that the book containing permit blanks was originally held by the secretary, but subsequently delivered by him into the custody of the sewer inspector, where, since that time, a period of several years, it has remained with the express approval of the sewer committee. Granting that the issuing of blank permits to the inspector, to be signed and issued by him as they were applied for, was an irregular mode of performing the purely ministerial duty devolving upon the secretary, it was not such an irregularity as could be taken advantage of by the borough after it had received the plaintiff’s money for the permit, and he, in good faith, had made the connection at the very place designated by the inspector, had completed his drain, and the sewer inspector had inspected and approved the work.
The permit was to make connection with the public sewer “ from his premises located on the easterly side of Haverford avenue.” It is objected that the premises from which the plaintiff constructed his- branch sewer or drain are not the
The manifest purpose of the permit was to enable the plaintiff to construct and maintain a drain from his building to the public sewer, and he made the connection at the place pointed out by the proper officer, which, by the way, was the only place where it was feasible to make it. The .facts that this point of connection was not immediately opposite his twenty feet frontage on Haverford avenue, and that he conducted his drain
A discussion of the liability of plaintiff’s property to assessment by the front foot rule seems out of place. Such liability, whatever it may be, is imposed by another ordinance than that under which permits to connect with the sewer are issued, and is, or was, enforceable in the mode therein prescribed. Neither ordinance makes the discharge of this liability a condition precedent to the issuing of a permit or to the execution of the privilege granted. The plaintiff paid all that the ordinance required him to pay for the permit, and upon no principle can he be required to pay more in order to entitle himself to the aid of a court of equity to prevent the defendants from wrongfully destroying the drain that was lawfully made pursuant thereto.
There can, ordinarily, be no judicial restraint or interference with the bona fide exercise by a borough council of powers, legislative or discretionary in their nature, which do not violate private rights ; nor is anything of that kind involved in this decree. Its purpose and effect are simply to prevent the execution of an invalid resolution of council which, in addition to directing the borough solicitor to proceed to collect penalties as provided by ordinance fifty-six, also requires the sewer inspector to break the connection of the plaintiff’s branch sewer or drain with the public sewer, — an act which would be contrary to law, prejudicial to the interests of the plaintiff, and 'for which the remedy at law would be inadequate. We have no doubt of the right of the plaintiff to maintain his sewer, or of the jurisdiction of a court of equity to restrain the borough and its officers from interfering with it in the manner proposed.
' The decree is affirmed, the costs of suit, including this appeal, to be paid by the borough of Swarthmore.