Perna v. McFadden
Perna v. McFadden
Opinion of the Court
Opinion by
Plaintiff claimed a balance of §1,098.86 from defendant, upon a contract for excavation and stone work of certain houses in the city of Philadelphia, under an agreement in writing, a copy of which is attached to the statement. A paragraph of said •contract which relates to liquidated damages is as follows:
“ The said party of second part further promises, and agrees to push the work vigorously and to keep pace with the other work, to the satisfaction of the party of the first part, and agrees to pay the sum of one dollar per house for each day’s delay as liquidated damages until such delay shall cease, and directs the same shall be deducted from any cash payment that shall be due, will be due, or is to become due by virtue of this contract. And should such delay continue for more than five days, then the said party of the first part to have the right to assume charge of and sublet or relet all or any part of the above work or furnish the material and labor and set other men to do the work, and charge the cost thereof against any balance that may be due, will be due, or is to become due by virtue of this contract, for the work done, or to be done, or material furnished, or to be furnished, as above stated.”
The affidavit of defense filed by the defendant expressly denies the accuracy of the measurement of both excavation and stone work for which the plaintiff claims, and further claims, as a set-off, items of lumber, steel bars, and removing rubbish and
“ That the contract sets forth on its face that the work was to be completed in two weeks from tbe date of signing of contract. That as the contract was signed on May 2, 1906, the work therein provided for should have been completed on May 16, 1906, but in point of fact and according to the statement filed it was not completed until June 25, 1906, which was forty days after the date agreed upon. And it was further provided in said agreement that said Perna should be liable to a penalty of $1.00 per day for each house for each day’s delay, as liquidated damages, so that this deponent is entitled to retain out of any money due, or to become due, the said plaintiff, the sum of $480, for his delay in completing the work, the said amount being $1.00 per day per house for twelve houses and for forty days.
“ Defendant further says that by the delay caused as aforesaid by the failure of the plaintiff to complete the work within the time agreed upon, this deponent was put to great additional' loss and expense, as all other work had to wait until the cellars and foundations were completed by the plaintiff, and during all that time the amount of interest chax-ged against this, deponent and paid by him (the interest on $84,000 for 40 days, making $560) could have been avoided, had the plaintiff 'completed his contract within the time specified therein.”
The court below adjudged the affidavit of defense sufficient as to the items first above mentioned, aggregating $366.59, axxd entered judgment for $732.27. The affidavit was deemed insufficient as to the items last mentioned, naxnely, for delay in the completion of bouses under the coxrtract, and interest on $84,000 for forty days.
As to the last item, it is very clear that, if the penalty provided in the contract is liquidated damages, as therein set forth, none other would be recoverable under the agreement. The question, therefore, is as to the sufficiency of the affidavit of. defense in regard to this penalty. The claim is for $12.00 per day for forty days. The agreement, however, provides for the
Judgment affirmed, without prejudice to the right of the plaintiff to proceed for the balance of his claim, as to which the affidavit of defense was regarded as sufficient.