Seligman v. Beecher
Seligman v. Beecher
Opinion of the Court
Opinion by
According to the testimony of both parties, the plaintiff agreed to deliver, and the defendant agreed to take and pay for, 240 carloads of prop timber during the year 1905, in quantities of twenty carloads a month at $4.70 per ton for one kind, and $4.85 per ton for another kind. In this action of assumpsit the plaintiff sued to recover the contract price for a certain number of carloads, and the defendant pleaded as a set-off damages in consequence of the plaintiff’s failure to deliver (1) a certain number of carloads for which he, the defendant, had given orders; (2) a certain number for which orders had not. been given at the time the plaintiff brought suit. In the contract as thus far stated the place of delivery was not expressly determined. Therefore, it is contended by appellant’s counsel upon the authority of Barr v. Myers, 3 W. & S. 295, it was incumbent on the plaintiff to tender the whole number of props within the time specified. It appears, however, by the course of dealing, by the plaintiff’s testimony which was not contradicted, and by defendant’s averment in his claim of set-off, that the timber was to be shipped upon orders, given by the defendant to the plaintiff, to the places designated in the orders. This being so, the deféndant was to become the actor in the transaction; therefore, so far as the number of carloads for which he did not give orders during the year is concerned, it was, prima facie, not necessary for the plaintiff, in order to save himself from default, to tender them at defendant’s residence or place of business. If, however, while still under obligation to fill the orders, up to the number of 240 carloads, which the defendant might give, the plaintiff expressly refused to go on with the contract, the defendant was not under obligation to go through the idle form of -giving orders in order to hold the plaintiff for a breach of his contract to. deliver 240 carloads during the year. So also, if without valid
But as to the orders that were given by the defendant, accepted by the plaintiff and not filled, a different question is presented. According to the plaintiff’s testimony, the defendant ordered from time to time during the year, 154 carloads, and canceled orders for twenty-one carloads, thus leaving orders for 133 carloads to be accounted for, of which forty-three were unfilled. Two of the reasons given for not filling these orders and for delay in filling others were inability to get cars and unfavorable weather conditions; but, as pointed out by the learned judge below, it was shown by the plaintiff's own record, to which he testified, that when he was complaining that he could not get cars he was shipping a great many cars to other people, and that the same was true in the months
We are constrained also to the conclusion that the instructions complained of in the third assignment are open to criticism upon the ground that they seem, or might be so taken by the jury, to give them too wide a latitude in determining the questions for decision, particularly the question of damages. Of course, as the counsel for appellee well says, it was for the jury to determine what estimate of damages should be adopted by them; but the conclusion of these instructions with the remark “you can adopt such estimate of damages as you think proper,” unaccompanied by a clear statement of the legal measure of damages that should guide them in determining what estimate it was proper for them to adopt, had a tendency to mislead.
The complaint that the court submitted to the jury to determine whether there was a contract to deliver 240 carloads during the year in quantities of twenty carloads a month; is not well founded. There was no dispute as to these matters, as the appellant’s counsel well says, but viewing the charge as a whole, in the light of the testimony and the manner in which the case was tried, we are convinced that the jury could not have understood that either the existence or these terms of the contract were in dispute and that the determination of the question was submitted to' them. There is part of one sentence of the charge quoted in the first assignment that,
The second and third assignments of error are sustained, the judgment is reversed and a venire facias de novo awarded.
Reference
- Cited By
- 3 cases
- Status
- Published
- Syllabus
- Contract — Sale—Monthly deliveries — Failure to fill orders — Failure to give orders — Delay in filling orders — Damages. Where a contract is to deliver 240 carloads of timber during a year in quantities of twenty carloads a month to be shipped upon orders given by the purchaser to the seller, to places designated in the orders, the purchaser is the actor in the transaction, and if he fails to give orders for a number of carloads, it is, prima facie, not necessary for the seller in order to save himself from default, to tender such carloads at the purchaser’s residence or place of business. If, however, the seller expressly refuses to fill orders, which under the contract he was bound to fill, the purchaser is not under obligation to go through the idle form of giving orders in order to hold the seller for a breach of his contract to deliver 240 carloads during the year. If without valid excuse and in spite of the purchaser's repeated remonstrances, the seller fails to fill orders that are given, this might, under some circumstances, justify the purchaser in withholding further orders, and still hold the plaintiff for a breach of the contract; but in determining whether'the seller will be liable on that ground, it is necessary to consider what the purchaser’s conduct had been in giving and canceling orders. If in that particular there has been lax performance on his part, either in giving the full number of monthly orders, or in canceling without proper grounds, orders already given, he is not in a position to say that the seller’s delay in filling, or even failure to fill, some of the orders that he gave was a breach of the contract, which, without more entitled him to damages for the nondelivery of the carloads for which he gave no orders. If the evidence relating to the purchaser’s conduct is conflicting, the case is for the jury. Where a contract is to deliver a certain number of carloads of lumber during a year on monthly deliveries, the seller cannot justify his failure to fill orders because of inability to get cars, and because of unfavorable weather conditions, where the evidence shows that at the time he was complaining that he could not get cars, he was shipping a great many cars to other people, and that the same was true in the months in which he claims he was prevented from filling the orders by bad weather. Where a contract is to deliver a certain number of carloads of timber during a year by monthly deliveries, the seller cannot excuse a failure to fill orders promptly, because he was compelled to send the orders to a distant state, and have the timber cut, and because the orders in question would have to wait their turn when orders from other persons were ahead'. The contract being to deliver and not to cut and deliver, it is the seller’s duty to make such preparations and arrangements as will enable him to deliver within a reasonable time after the orders were given. In a case involving damages for a breach of contract, it is error for the trial judge to state to the jury that “you can adopt such estimate of damages as you think proper,” without instructing them as to the legal measure of damages that should guide them in determining what estimate it was proper for them to adopt.