Linker v. Central Trust & Savings Co.
Linker v. Central Trust & Savings Co.
Opinion of the Court
Opinion by
This action was brought on the defendant’s agreement to guarantee the payment of certain sums of money due to the plaintiff on its contract with S. W. Hahn, for cement work on a building operation at Sixtieth street and Chestnut avenue, Philadelphia. The defendant seeks to evade liability because of certain changes in the defendant’s work, contrary to the plans and specifications. The guarantee contract provided that the defendant was to pay “in accordance with the terms of a certain contract in writing......upon vouchers signed by the said S. W. Hahn and upon approval of the said work by this company.” The original contract bore date of February 27, 1911, and the contract sued on of November 8, 1911. It is the plaintiff’s contention that whatever changes were made in the written contract were made by agreement of the parties then interested, and the defendant’s contract of November 8,1911, must be considered as embodying the contract of February 27, 1911, in its modi
The case does not exactly present a question of the .inspector’s power. Approval of the vouchers in the form outlined would amount to a ratification of his supposed authority were it in issue. He was the company’s representative and what he saw the company was supposed to then know, and it would be charged with full knowledge thereof. It cannot at this time question either the inspector’s acts or its own acts in approving as correct what it now urges was a manifest wrong.
We do not consider the reduction of the claim by the jury as materially affecting the proposition. The amount sued for was slightly in excess of the deferred payment of $800, and it may be possible that the jury considered the appellee not entitled to any interest. Upon the evidence thus presented, there was but one question before the court: Did the plaintiff substantially perform the written contract as modified? If the original contract had not been altered, the plaintiff’s work would not have been a substantial performance of that contract, and it would have been the duty of the court to so declare as a matter of law, but the oral and written testimony places these matters clearly before the jury. Nor do we consider the . release of surety as material in view of the facts found by the jury and here discussed. The question would be serious if the written contract, in an unchanged form, still existed. When the inspector went on the work and certified to it, his action, approved by the defendant, was an approval of the work, and as to the balance sued for, considering the appellee’s evidence, the defendant’s fifth point covers the law applicable thereto.
The assignments of error are overruled and the judgment is affirmed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.