Riegert v. Lebanon City School District
Riegert v. Lebanon City School District
Opinion of the Court
Opinion by
The plaintiff entered into a contract to do all the excavating for the erection of a high school building in the City of Lebanon. The contract provided that the excavating contractor “shall also cart away all stone that are not fit to be used in the future operations by the general contractor. No allowance will be made to the excavating contractor for good, old or quarried stone left on the premises”......“Should a solid ledge, boulder or loose stone be encountered in making excavations, the excavating contractor is to excavate the same by blasting or other process, and is to remove unfit stone from or deposit it on the site directed if fit to be used.” The question is, did the above words reserve to the school board such stone as were fit and necessary for use in the school building, or was the word “fit” intended to describe the quality of the stone irrespective of the fact whether such stones were actually required in the erection of the building, or to express it differently, were stones suitable for any building to be the property of the school board, or was it the intention that only such stones as were to be used in the school building were to belong to the board? The court took the view that the object of the school district was to reserve such stone as it could actually use in the building about to be erected. This we think was correct. “The future operations” of the general contractor referred to were not all future operations, but such as he would-be engaged in under the contract. The erection of 'a school building was the
Having construed the contract in this manner the court left to the jury the ascertainment of the value of the stone which was not required for the building and consequently, belonged to the excavating contractor, and which the school board had appropriated and sold. The jury apparently lost sight of the fact that some of the stones could still be used for the building as it was not yet completed at the time of the trial and after verdict the trial judge reduced the sum found by the jury so as to accord with the sum shown by the testimony submitted by the defendant.
There is a provision that the construction placed on the contract by the architect should be final. The language of the contract is, “his decision as to the true construction and meaning of the drawings and specifications shall be final.” We agree with the trial judge that there has been no decision in the matter by the architect. It is true that he stated that all the stone that were fit should be left on .the premises but as the court said that was merely restating the language of the contract without any attempt at interpreting its meaning.
Exception is taken to the admission of testimony showing that there was a change in the specifications and that by such change more stone was required for the completion of the building than under the items contained in the contract. The error charged is that at the time the contract was made the general specifications were not in the hands of the excavating contractor and that he had no means of knowing what quantity of stone would be inquired in the future operations of the general contractor. We see no merit in this objection. Whether the excavating contractor knew or did not know the amount of stone required for the whole building nevertheless, the
Judgment affirmed.