Texter v. Wachs
Texter v. Wachs
Opinion of the Court
Opinion by
The plaintiffs in this action seek to recover a balance alleged to be due upon a contract for the erection of a building, for additional work in erecting shelving and counters in one of the storerooms of the building and for work done upon other buildings of the defendant. The contract for the erection of the building was in writing and required the building to be finished by June 1, 1907. The principal question in controversy at the trial arose under the following covenant, viz: “Should the contractors fail to finish the work at or before the time agreed upon, they shall pay to or allow the proprietor, by way of liquidated damages, the sum of ten dollars per diem for each and every day thereafter the said work shall remain incomplete.” It is admitted on behalf of the plaintiffs that, in view of the character and extent of the building operations, the amount thus stipulated to be paid in case the contractors failed to finish the building at the time
The court in that portion of the charge which is the subject of the second specification of error charged the jury as follows: “The plaintiff, having entered into this contract, would be required to finish and complete the structure on or before the date named in it, provided there was not any permission given him to delay the work by the defendant or by his agent, namely, the architect, or through weather conditions which would make it absolutely impossible for him to do the work.” If the limitation upon the liability of the plaintiff for delay, as thus stated, had been confined to that part of the instruction which referred to such delay as resulted from the action of the defendant or his agent, the architect, the instruction would not have been so clearly erroneous as to warrant a reversal, for the jury would probably then have understood that the plaintiff was only to have the benefit of such delay as resulted from the action of the defendant or his agent. It would, however, have guarded against misunderstanding by the jury if the court had instructed them that, even if the defendant had to some extent delayed the operation the plaintiff was only entitled to the delay which resulted from that cause. “For the fact 'that plaintiff was obstructed by defendant in strict performance did not absolve it from further effort to speedily perform. When the cause for the delay, the conduct of the defendant, ceased, the obligation to speedily finish was at once reimposed with all its force on plaintiff, and failure then to perform within a reasonable
The instruction complained of in the first specification of error certainly tended to leave upon the minds of the jury the impression that the plaintiff was only to be held answerable for such delay as resulted from his negligence or carelessness. He had covenanted that in case of delay he would pay at a certain rate per diem. The appliances and the number of men which he would employ in the undertaking were for him to determine; if there was delay he must respond according to his contract, unless that delay was caused by the defendant or his agent. The first specification of error is sustained.
The contract contained a covenant that nothing done under the contract was to be considered as extras unless agreed upon in writing and signed by the owner and contractor and certified to by the architect. The appellant
The judgment is reversed and a venire facias ide novo awarded.
Dissenting Opinion
Dissenting Opinion by
I am unable to agree with the conclusion of the majority of the court. While the instructions of the trial judge with respect to damages for delay, complained of in the first and second assignments of error, were technically erroneous as pointed out in the opinion of the court, no harm was done the defendant, for in my judgment, the provision in the contract providing for the payment of a specified sum per day as liquidated damages for delay had been waived by the defendant, and that item should not have been submitted to the jury at all. It was practically admitted by the defendant and his representative, the architect, that the work had been shut down over the winter by agreement of both parties, because the weather was not fit for laying brick, and that the brick work started as soon as the weather permitted.
The case, in my opinion, is squarely ruled by the decision of the Supreme Court in Coryell v. DuBois Borough, 226 Pa. 103, that where a building contract provides for a deduction of a stated amount as liquidated damages from the contractor’s compensation for each day of delay after a time specified, the owner cannot claim such deduction where he has made no objection to the delay and by his conduct has given the contractor grounds for believing that the provisions of the contract as to the penalty for delay would not be enforced.
I would affirm the judgment.
Reference
- Cited By
- 2 cases
- Status
- Published
- Syllabus
- Building contracts — Breach of contract — Liquidated damages for delay — Charge of court. In an action to, recover liquidated damages for delay, under a building contract which provided that the contractor should pay “by way of liquidated damages the sum of $10 per diem for each and every day thereafter the said work shall remain incomplete” it is error for the court to charge the jury that the contractor would not be liable for delay caused by adverse weather conditions but that he would be liable only for delay caused by his own negligence. Where a building contract provides for liquidated damages for delay, the fact that the conduct of the owner has caused delay does not relieve the contractor, as soon as such cause has ceased, from speedily finishing the work, and the failure to do so will warrant the owner in invoking the claim for liquidated damages for every day of unreasonable delay thereafter. When parties enter into the contract for the erection of a building in this climate, they must he presumed to know that the weather conditions will not always be favorable and if they wish to be protected against same, they should make suitable provision therefor in the contract itself. Where the contractor covenants that, in case of delay he will pay a certain rate per diem, the appliances and the number of men which he would employ in the ■ undertaking were for him to determine, and if there was delay he must respond according to his contract, unless that delay was caused by the defendant or his agent. An independent contract, for extras at a price agreed upon, is properly admissible in evidence, in an action for the amount due, where such contract was in addition to and not an essential part of the original undertaking. Keller, J., dissents.