Bertocci v. Commonwealth
Bertocci v. Commonwealth
Opinion of the Court
Opinion by
Stripped of its irrelevant facts as well as the disputes which are resolved, the matter before us for decision arises from the interpretation of a road rebuilding contract. Appellant was rebuilding a heavily travelled highway on which it was required by the contract to maintain two-way traffic. On September 16, 1963, it had requested, and on September 27, 1963, it was given, permission to tear up and remove the old pavement. Without replacing the pavement, on October 29, 1963, it requested permission to shut down operations on the project for the winter because the permissible paving date had passed. By letter dated November 19, 1963, appellant was given the requested permission provided, inter alia, it placed stabilized material and maintain it in satisfactory condition. At the same time, appellant was informed that this work had to be started on or before November 25, 1963, or appellee would do the work and deduct the cost from the price. On November 25,1963, appellant requested further information as to the type of stabilized material required and how appellee intended to pay for it. On November 27, 1963, appellant was informed that since
It is important to note that on November 11, 1963, appellant had withdrawn its work force and substantially all its equipment for the winter, leaving perhaps one grader to maintain the surface for travel. On November 8, 1963, appellant’s superintendent had been notified that “work was to be done on project for stabilizing road for travelling public over the winter months, if contractor wanted to shut down project.” Appellee placed the stabilizing material on the roadway at a cost of $24,000.00 and deducted this sum from the final payment on the contract. The matter went to the Board of Arbitration of Claims which sustained appellee’s right to deduct the $24,000.00. This appeal followed. We affirm.
We will not quote the contract provisions which clearly required appellant to maintain the surface of the road for travel but will quote what we perceive to be the vital provision:
“1.4.5. Public Convenience and Safety—
U
í Í
“ (3) Maintenance of Roadway. If the roadway is not maintained in a satisfactory condition, the Department reserves the right to enter upon the project and perform such work as may be deemed necessary for the accommodation of traffic and the cost thereof may be deducted from any monies due or which may become due to the contractor, or his surety. No separate compensation will be allowed for maintenance of traffic, except as provided in Sections 6.15, 9.1 and 9.2.”
The Board of Arbitration of Claims found that the action of appellee in entering upon the project and placing the stabilized material for the purpose of maintaining traffic was a reasonable thing to do.
The findings of fact of the Board of Arbitration of Claims, when amply supported by the record, as they are here, will not be disturbed. Commonwealth v. Berger, 11 Pa. Commonwealth Ct. 332, 312 A.2d 100 (1973).
Accordingly, we enter the following
Order
Now, June 17, 1976, the order of the Board of Arbitration of Claims, dated October 15, 1975, in the above matter, is affirmed.