Hartford Accident & Indemnity Co. v. Flanaghan
Opinion of the Court
Hartford Accident and Indemnity Company, plaintiff, sued T. M. Flanaghan, defendant, in assumpsit on a book account to recover a net balance of premiums claimed to be due for various types of insurance. None of the items of the book account are in dispute except those relating to bond no. 1988964, with respect to which Flanaghan had admittedly paid the original premium. The dispute has arisen because Flanaghan contends that only a part of his premiums was earned, and that he, therefore, is entitled to a rebate. Both parties, through their counsel, stipulated at the trial that the respective claims of plaintiff and defendant are $2,329.27 and $774.21. Each party presented a single point for binding instructions in the amount of such party’s
The additional work was done in accordance with four change orders dated, respectively, 10-26-42, 7-2-43, 8-18-43, and 8-23-43. Each was marked as a change order under order no. 956, defendant’s original order and subcontract number. No new or separate contract was entered into between Tompkins Company and defendant for the additional work. No additional bond was given by defendant or requested from him for such additional work. The general contractor likewise was in possession of relevant change orders from the Government to the general contractor. Of the work done by Flanaghan, under the change orders, all was outside groups 1, 2, 3 and 4; some was physically outside the Naval base, and some physically inside the Naval base; all of them were connected with the necessary construction of the Naval base. Some of the additional work was contained in the original plans, and some was not. All the work was for the base and done at or near it, and all was of the same general nature, viz., sewer and water system construction.
Since the Government retained power under its general contract to change the work contracted to be done, or even the projects themselves, subject to equitable adjustment with the contractor, and since the subcontractor contracted with the contractor subject to the provisions of the general contract between the general contractor and the Government, and since defendant’s subcontract also permitted change orders to be made or given subject to equitable adjustment
It is true that defendant’s four change orders came after the date on which he had contracted to complete his performance of the work originally assigned to him. This circumstance in a project of such magnitude as the training camp ought not to control the decision, inasmuch as new ideas such as the Happy Valley Interceptor were naturally to be expected to suggest themselves and find approval with the Government (United States Navy). The further fact that Chas. H. Tompkins Co. saw fit to ask for bids for the new work given to defendant is not controlling, since the general contractor was free, whether with or without bids to negotiate and assign such work either to defendant or to a third person. More significant in our opinion is the fact that no new bond was. exacted from defendant or given by him, although the work assigned to and done by him eventually exceeded his original subcontract and its accompanying bond. For any such increase, he agreed with plaintiff to pay a correspondingly increased additional premium. It appears, therefore, that also from the course of conduct of the parties interested, the conclusion must be reached that the
We have read all the cases cited by defendant. In Freund et al. v. U. S., 260 U. S. 60, the court held it impossible to fix a fair compensation for Freund by reference to his original contract, because of the entire dissimilarity of the additional work to that called for by his original contract. To the contention that Freund’s performance of the additional work amounted to a consent by him to be compensated under the original contract, the court replied that under the circumstances he was subject to an unfair duress. In the present case, on the other hand, there is no such dissimilarity between the work originally contracted for and that ordered through the change orders, nor does the price of the original work assigned to defendant bear, either by the amounts or through any averment, any aspect of duress, since such price was fixed by defendant’s own bid. The case of Morse et al. v. City of Boston et al., 253 Mass. 247, 148 N. E. 813 (1925), involved the powers of the City of Boston, a subordinate municipal body of the Commonwealth of Massachusetts, under the statutes restricting such powers. It is not germane to the present case. The case of Mueller et al. v. Eau Claire County et al., 108 Wis. 304, 84 N. W. 430 (1900), involved an admitted departure from what the court held was the mandate of the statute, which restricted the power of the county to contract. The case is not apposite to the present facts. The general proposition that an alteration of a contract by the principal parties, without the assent of the surety, is fatal to its enforcement against the surety, “has no application to a building contract which by its terms contemplates or expressly provides for changes”: Koch v. Moyer and Burkhart, 103 Pa. Superior Ct. 270, 273. Any doubt as to the meaning of the guaranty of a compensated surety “is to be resolved
And now, to wit, January 5, 1950, defendant’s rules for new trial and for judgment n. o. v. are discharged.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.