B. E. Reichenbach, Inc. v. Clearfield County Industrial Development Authority
Opinion of the Court
This matter comes before the court upon plaintiff’s motion for partial summary judgment and motion to amend complaint, and also upon defendant’s motion for judgment on the pleadings.
Prior to October 1976 defendant solicited bids for construction of certain sections of the Clearfield Interchange Industrial Park, Economic Development Administration Project no. 01-01-01392. Plaintiff submitted a bid for Sections A and B of the Industrial Park. On January 6, 1977 plaintiff and defendant executed a contract in the amount of $1,196,514.62 for construction of these sections. The contract provided that plaintiff was to complete the project within 365 consecutive calendar days after the date specified by the owner in a written
The major issue in this case revolves around two separate clauses of the contract. The first of these clauses is relied on by plaintiff. It is one of the general conditions of the contract documents which were prepared by defendant’s engineering firm and the Economic Development Administration (EDA) and provides as follows:
“Prior to the start of construction, the owner shall obtain all land rights-of-way necessary for the carrying out and completion of work to be performed under this contract.”
Plaintiff’s major contention is that defendant breached the contract by issuing notice to proceed before they had obtained all the proper rights-of-
Defendant, on the other hand, argues that section 58 of the general conditions preclude plaintiff from bringing an action for damages based on delay. Section 58 reads:
“Should the owner be prevented or enjoined from proceeding with work, or from authorizing the prosecution either before or after its prosecution by reason of any litigation, contractor shall not be entitled to make or assert claim for damage, by reason of said delay but time for completion of the work will be extended to such reasonable time as the owner may determine will compensate for time loss for such delay with such determination to be set forth in writing.”
Defendant argues that this section is controlling and that further litigation required to obtain the rights-of-way was the cause for delay. Defendant cites the cases of Johnson v. Fenestra, Inc., 305 F. 2d 179 (3d Cir. 1962), and Lichter v. Mellon-Stuart Company, 305 F. 2d 216 (3d Cir. 1962), for the proposition that a contract may validly provide that contractors shall be entitled to no relief except an extension of time for performance if circumstances beyond his control shall delay his performance even though such delay does in fact increase his cost.
Both parties cite Gasparini Excavating Co. v. Pennsylvania Turnpike Commission, 409 Pa. 465, 187 A. 2d 157 (1963), the only case that seems to be close to point in this case. In Gasparini, a contractor sought delay damages from the Pennsylvania
Section 58 calls for no damages for delay caused by litigation that would prevent defendant from proceeding with work. The question is, what was the intention of the parties in including this no delay damage clause. Plaintiff argues that it was not prevented from proceeding by reason of litigation but solely because of defendant’s failure to obtain the required rights-of-way. Plaintiff also contends that section 58 was intended to apply to the type of situation where a suit may be brought by an environmental group to enjoin further develop
Plaintiff has also asked for partial. summary judgment on the issue of liability. Based upon the facts as pleaded, plaintiff’ motion must be granted. Defendant does not deny that notice to proceed was issued before proper rights-of-way were obtained. Their only argument is that section 58 relieves them of liability for the delay to plaintiff. If this court finds that defendant was in breach of the contract clause requiring rights-of-way to be procured before issuing notice to proceed and that such breach was the cause for delay, not litigation, then plaintiff’s motion must be granted.
Finally, as to plaintiff’s motion to amend his complaint, defendant has indicated that should its motion for judgment on the pleadings be denied, it would have no objection to such an amendment, and therefore, this court grants the same.
Wherefore, the court enters the following
ORDER
Now, March 3, 1981, following argument thereon, it is the order of this court that motion for
It is the further order of this court that motion for partial summary judgment filed by plaintiff above-named as to the issue of liability be and is hereby granted, and further, that plaintiff be permitted to amend its complaint in accordance with his request.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.