Lehman Bros. v. Redevelopment Authority
Opinion of the Court
This matter is before us on defendant’s exceptions to our opinion and order dated November 30, 1972. Plaintiff, Lehman Bros., Inc., and defendant, Redevelopment Authority of the City of Harrisburg, had entered into a contract on March 26, 1969, whereby defendant was to sell and convey to plaintiff a tract of land in the City of Harrisburg, commonly referred to as the “Walnut Street Project,” for purposes of private redevelopment by plaintiff. Pursuant to the terms of this agreement, plaintiff placed an $80,000 good faith deposit with defendant.
Plaintiff, in its complaint, averred that defendant had failed to make a proper tender of title to the land in question within the time allowed following notice by plaintiff that it was invoking the 30-day “cure period” as provided in the contract. Specifically, plaintiff claimed that defendant had not fulfilled conditions precedent to the conveyance contained in the contract which included the determination of a definite purchase price, approval of the Amended Urban Renewal Plan by the authority, approval of the Amended Urban Renewal Plan by the Department of Housing and Urban Development (HUD), and approval of the conveyance by the Harrisburg City Council. The authority denied that it had made an invalid tender and refused plaintiff’s demand for return of the $80,000 deposit. Whereupon, plaintiff had instituted this action.
The court found that the cure period had commenced to run on February 20, 1970, on which date plaintiff had sent by letter a demand that defendant sign certain amendments to the contract and, in the event that defendant refused, the letter would servé as notice of the invoking of the 30-day cure period. Within the 30-day period, on March 20, 1970, the authority tendered an offer of title which the court nevertheless
The authority now takes the position that the court incorrectly stated the date upon which the cure period began and that by using the correct date as proposed by the authority, the tender would have been effective before the cure period expired. Because plaintiff had not sent the notice of cure by registered mail, as required by the contract, it is the contention of defendant that the cure period ran not from the date of its mailing, February 20th, but rather from the date of its receipt, February 23, 1970, to March 26, 1970. Defendant authority insists that this time difference is crucial on the theory that on March 24,1970, when the Harrisburg City Council approved the resolution required by HUD, the conditional approval of HUD automatically became final. Therefore, defendant claims that the tender of March 20,1970, did become effective prior to the expiration of the cure period.
While the contention of defendant as to the dates governing the running of the cure period appear meritorious, we fail to see that this would necessitate a change in our original decision inasmuch as we continue of the opinion that until the final approval was actually forthcoming from HUD, on April 9, 1970, the authority could not make a valid tender. We are satis
Defendant further now contends that section 702 of the contract required that plaintiff give notice not only of the invoking of the 30-day cure period but also of its desire to terminate following the expiration of this 30-day period. Although this matter is raised for the first
The cautionary exceptions to the court’s order and opinion of November 30, 1972, filed by plaintiff need not be considered in light of the foregoing.
Accordingly, we make the following
ORDER
Now, August 8, 1973, the exceptions of defendant Redevelopment Authority of the City of Harrisburg to our opinion and order dated November 30, 1972, in the above-captioned matter, as well as the exceptions thereto of Lehman Bros., Inc., are hereby overruled each and severally and the order affirmed.
Dissenting Opinion
DISSENTING OPINION
I would sustain the Redevelopment Authority’s exceptions to the opinion and order dated November 30, 1972, and hold that it is entitled to retain the $80,000 deposit.
We cannot overlook that we are dealing here with taxpayers’ money. On the strength of the contract with Lehman, a large tract of land was condemned and, I assume, a very substantial amount of money paid to the condemnees. Lehman’s good faith deposit was in the nature of a bond for performance. The urban renewal plan was fashioned to meet the specific needs of this redeveloper and, except for the Lehman agreement to purchase and redevelop, the condemnation and demolition would not have been done. The administration costs as well as the money already paid out must be very considerable. It appears that some two years after forfeiture, the authority has still not been able to interest another developer in the project. Tax revenues have been, and will continue to be, lost. How else is compensation to be obtained for a default of the redeveloper than by this forfeiture? Accordingly, I feel that this case must be viewed in the light of the principle of law that a contract with public authorities will be interpreted in favor of the public: Henry Shenk Co. v. Erie Co. et al., 319 Pa. 100, 178 Atl. 662 (1935);
As to the events themselves, I don’t think that the Lehman notice of February 20, 1970, required the authority to do anything within 30 days. That the letter was sent by regular mail contrary to section 7, part I, of the contract strongly suggests that it was not a demand for tender under section 702(a), part II. Whatever it purported to say, and it is my own feeling that it may be construed as an anticipatory breach of the contract, it was not a written demand for “tender of conveyance of the property, or possession thereof, in the manner and condition . . . provided in this Agreement.” That is precisely what Lehman did not want. The letter was, in fact, a demand for acceptance of enclosed amendments to the contract. To construe the letter as a demand for tender under section 702(a), part II, would mean that Lehman was acceding to tender of performance under the contract without amendment which is patently contrary to Lehman’s intention.
Rather than construing the forfeiture provision so that it operates as an escape clause for Lehman, we must construe this contract to favor the public interest. As to the so-called conditional approval by HUD, on which the majority opinion turns, I simply cannot see why the public interest should receive such slight concern on this point. This redeveloper was looking for a way out, after having caused the public agency to tear down a couple of city blocks and incur great expense. The redeveloper then says that unless the public agency agrees to his contract changes it will be deemed in default. It is perfectly clear that Lehman never contemplated performance of the contract after
Accordingly, I respectfully dissent.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.