Benzinger Twp. Authority v. West Penn Power Co.
Opinion of the Court
— Defendant, West Penn Power Company (West Penn) seeks dismissal of scire facias sur municipal claim of plaintiff, Benzinger Township Authority (authority) and that Municipal Lien no. 81-144 of the authority in the amount of $2,563 plus accrued interest be stricken.
Plaintiff is a municipal authority created by the supervisors of Benzinger Township, a Second Class Township, for the express purpose of constructing a sanitary sewer system in designated areas of the township. Defendant is a public utility as defined in the Public Utility Code, 66 Pa.C.S. § 101 et seq., providing electric service to approximately 568,198 customers in a service area comprising all or parts of 23 counties in southwestern and central-Pennsylvania having a population of about 1.5 million persons. . West Penn is the owner of a parcel of property in Benzinger Township, Elk County, which is used by West Penn for the location of an electric substation and for the placement of poles and electric lines leading to and from the substation. The substation has been in existence since 1955, and is a fully automated facility used to transform line voltage from 46 kilovolts to 15 kilovolts for the eventual distribution of electric service. The authority stipulates that West Penn’s subject substation premises has no present need or use for sanitary sewer service.
FINDINGS OF FACT
The entire tract of property is necessary for the ■operation of the substation. While the substation transformers and platforms do not occupy the entire property, the incoming and outgoing electric distribution lines require right-of-way over the property. These electric distribution lines, at voltages of 15
The authority is empowered to assess - property owners for the cost of construction of sewer lines by section 4B of the Municipal Authorities Act of 1945, 53 P.S. §306B. This section recognizes the rule that only the property which has.benefited from a municipal improvement may be assessed therefor. It provides that a municipal authority has the power:
“(r) To charge the cost of construction of any sewer or water main constructed by the Authority against the properties benefited, improved or accommodated thereby to the extent of such benefits. . .
“(s) To charge the cost of construction of any sewer or water main constructed by the Authority against the properties benefited, improved or. accommodated thereby according to the foot-front rule. Such charges shall be based upon the foot frontage
The Pennsylvania Supreme Court in Palmer Township Sewer Authority v. Witty, 479 Pa. 240, 388 A. 2d 306 (1978), held that the foregoing provisions of the Municipality Authority Act require that the properties assessed must have received an actual benefit from the municipal improvement. The court stated:
“Whether subsection (r) (the “benefits” method) or subsection (s) (the “foot frontage” method) is utilized/an assessment must always be related to the benefits conferred upon the property owner. “ ‘When the property is not benefited, our courts have not hesitated to declare that the assessment could not be sustained. While there is a presumption that a property is benefited by the construction of a sanitary sewer adjacent to it, this presumption may be rebutted. . . .’ ” Whitemarsh Township Auth. v. Elwert, 413 Pa. 329, 334-35, 196 A.2d 843; 847 (1964) quoting Upper Moreland-Hatboro Joint Sewer Auth. v. Pearson, 190 Pa.Super. 107, 112, 152 A. 2d 774, 776 (1959).
Palmer Township Municipal Sewer Authority, supra, involved a situation where a parcel of property was assessed for two different sewer fines along adjacent streets. The only dwelling on the property received sewer service from one of the fines and the owner of the property contended that the property was not benefited from the second sewer fine. The owner also relied on the fact that a local zoning ordinance prohibited further subdivision of the property, so that use of the second sewer fine was impossible. The Commonwealth Court speculated that at the time of construction of the two fines, the property owner may have had (he benefit of either sewer fine. The Supreme Court reversed, holding that the
“[W]e agree with the trial court and the court en banc that any benefit to appellants’ property by the [second] sewer line was speculative. The assessment based upon that portion of the construction project cannot, therefore, be permitted to stand.” 388 A. 2d at 309-310.
The rule that a benefit may not be a speculative benefit was also indicated by the Commonwealth Court in Township of Harborcreek v. Erie Drive-In Theater Corporation, 27 Pa. Commw. 294, 367 A.2d 348 (1976). In that case the property in question was assessed for a municipal water line despite the fact that it was already served in part by a preexisting line. While the court held that the property owner had failed to show a lack of benefits, it stated:
“Not only are portions of the appellant’s property 'presently available for subdivision and use, there is no evidence that the property as a whole is not presently benefited. . 367 A.2d at 350. (Emphasis added.)
The court’s reliance on the concept of a present benefit is relevant to the case at hand. The facts as set forth in West Penn’s affidavit of defense state that the sewer line in question does not provide a present or a future benefit to the West Penn property. The authority speculates that the substation may someday be abandoned by West Penn, and that the property would be developed and would' benefit from the sewer line. This reasoning would render every property adjacent to a municipal improvement subject to a municipal assessment because, with some imagination, one can speculate that every property will undergo a change in use so as to
We find Muhlenberg Township Authority v. City of Reading, 75 Pa. Commw. 227, 461 A. 2d 654 (1983) to be inapposite. In that case the Commonwealth Court held that city property does not enjoy blanket exemption from assessments by a municipal authority. The case did not disturb the rule that property may not be assessed for municipal improvements unless the property is benefited therefrom. Also, plaintiff’s reliance on City of Philadelphia v. Philadelphia and Reading Railroad, 1 Pa. Super. 236 (1896) and Mitchener v. Philadelphia, 118 Pa. 535 (1888), makes no allowance for subsequent enactment of the Municipal Authorities Act of 1945 and cases subsequent thereto, including Palmer Township Sewer Authority, supra, and cases cited therein.
Pursuant to Palmer, supra, we recognize the presumption that a property is benefited by construction of a sanitary sewer adjacent to it, which presumption may be rebutted. We find that defendant has, by an overwhelming preponderance of the- evidence, rebutted this presumption as any possible benefit at the very most would be speculative.
We therefore make the following
Now, January 10, 1985, the scire facias sur municipal claim is dismissed and the prothonotary is directed to strike the Municipal Lien no. 81-144 of the Benzinger Township Authority in the amount of $2,563. plus accrued interest.
Larkin v. Philadelphia Electric Co., 38 Pa. PUC 777 (1961).