Morton v. Commonwealth
Opinion of the Court
This matter comes before the board on stipulated facts and a motion for judgment on the pleadings. Appellant, D. Herbert Morton, hereinafter “appellant,” on September 4, 1973, applied for a permit under the Pennsylvania Water Obstructions Act
The permit contained a number of standard conditions, one of which provides that the permit itself shall not become effective unless and until there is a written acceptance of its terms within 30 days. Appellant gave no written notice to the department and, on June 28, 1974, was advised that the permit was revoked for non-compliance with condition no. II
DISCUSSION
At the outset, the Commonwealth argues that the matter of the department’s revocation order of June 28, 1974, is not properly before us because, as I understand it, appellant failed to appeal the imposition of condition no. 11, which was a part of the permit issued March 5, 1974. Having failed to ap
The facts in this case indicate that the department has interpreted a condition of its permit issued to appellant requiring notice to the department to mean that failure to give this required notice shall render the permit null and void. This interpretation is so prejudicial to the rights of the would-be “permittee” that we believe it is unreasonable for the department to enforce it without specifically stating these consequences. The terms were, of course, drafted by the department, and it is a rule of construction that such terms should be construed against the party preparing the language, where the meaning is unclear.
A further question arises under the interpretation urged by the department and that is whether a permit has been issued at all. If the language of condition no. 11 is given a literal interpretation, then there has been no permit effectively issued until notice of acceptance is received by the department. In legal terms, the department has
It is not unreasonable for the permit to contain a provision which allows the department to determine whether the project has been abandoned by the permit applicant. This would appear to be the legitimate purpose of condition no. 11.
The problem, however, is that condition no. 9 specifically provides that the permit shall be “null and void” if the work is not completed before December 31, 1975. This would seem to meet the needs of the department as they relate to abandoned approved projects. If this is true, then the question arises as to what purpose condition no. 11 serves.
This is especially a matter of concern because condition no. 2 provides for supervision and inspection by the department as to the work in progress in accordance with maps, plans and specifications.
In conclusion, we believe that, if the department intends to require a written notice of the acceptance of a permit for which proper application has been made and approved, it may do so. If, however, the department desires to go further and construe this requirement to mean that failure to give such
CONCLUSIONS OF LAW
1. The board has jurisdiction of the parties and subject matter of this appeal.
2. The department may require written acceptance of a permit for which application has been properly made and approved by the department.
3. Where the department intends to revoke a properly issued permit solely on the grounds that a timely written acceptance has not been received by it, this intention must clearly, specifically and conspicuously appear as one of the conditions in the permit.
4. The permit is sued to appellant did not properly notify him that failure to comply with the acceptance provision of condition no. 11 of the permit would render the permit null and void.
5. The action of the department was unreasonable.
ORDER
And now, November 8, 1974, the action of the department revoking the permit of appellant D. Herbert Morton is hereby reversed, and the appeal is sustained, upon the condition that appellant comply with requirement no. 11 of the permit within 20 days from the date hereof.
. Act of June 25, 1913, P.L. 555, 32 PS §684.
. The permit provides: “11. This permit shall not become effective until and unless the permittee shall file with the Department within thirty (30) days from the date thereof, upon a form furnished by the Department, its written acceptance of the terms and conditions imposed therein.”
. Condition no. 6 of the permit requires notice to the department of the commencement of work and a further notice within two weeks of the probable completion of the work.