Webster Brick Co. v. Fidelity & Deposit Co.
Opinion of the Court
Each of the parties in
George Danko, Inc. contracted with the Mount Pleasant Area School District to construct an addition to the Mount Pleasant Junior High School. As the prime contractor, George Danko, Inc. was required by state law to furnish a labor and material payment bond to the school district. The bond was obtained from defendant, Fidelity and Deposit Company of Maryland. George Danko, Inc. subsequently ordered a total of 144,500 bricks from Ideal Brick and Tile Company (hereinafter Ideal) for use in the project and agreed to pay $165 per thousand bricks delivered to the job site. Ideal did not manufacture the bricks which were so ordered, but, in turn, ordered bricks from the plaintiff, Webster Brick Co., Inc., and agreed to pay $90 per thousand for said bricks. The bricks were to be delivered to Ideal’s shipping dock in Virginia. Ideal picked up 153,340 bricks in Virginia and delivered them all to the job site in Mount Pleasant. Although George Danko, Inc. paid Ideal in full for the bricks which were ordered
The salient issue involved in this case is whether or not plaintiff is a proper claimant under the terms of the labor and material payment bond. The bond
In order to resolve this issue, the term “subcontractor” must be accurately defined. The language contained in the payment bond was taken almost verbatim from the Public Works Contractors’ Bond Law of 1967, Act of December 20, 1967, P.L. 869, §1, 8 P.S. §191 et. seq., the statute which established the bond requirement in public works construction contracts. Both parties agree that the Pa. Bond Law governs the meaning of the language contained in the payment bond and that there is a dearth of Pennsylvania case law interpreting the Pa. Bond Law. Further, the parties concur that the cases interpreting the federal equivalent of the Pa. Bond Law, the Miller Act (40 U.S.C.S. §270(a) et seq.), are analogous and extremely helpful in construing the Pa. Bond Law. The logic used in interpreting the Miller Act has been transferred and used in deciphering the meaning of the Pa. Bond Law on at least two prior occasions. See: Lite-Air Products, Inc. v. Fidelity and Deposit Company of Maryland, 437 F. Supp. 801 (E.D. Pa. 1977) and Visor Builders, Inc. v. Devon E. Trauter, Inc., 470 F. Supp. 911 (M.D. Pa. 1978). Therefore, a review of the federal cases is appropriate here.
Two main cases analyzing the Miller Act offer some insight into the meaning of the Pa. Bond Law and the specific language contained in the payment bond which is now at issue before the court. In Clifford F. MacEvoy v. U.S. for the use and benefit
In F.D. Rich Co. v. U.S. for the use of Industrial Lumber Co., Inc., 417 U.S. 116, 94 S. Ct. 2157, 40 L. Ed. 2d 703 (1974), the U.S. Supreme Court affirmed its previous definition of a “subcontractor” as it was set forth in MacEvoy, supra. Further, the court reasoned that if the subcontractor has a substantial relationship with the prime contractor, the prime contractor can easily “secure himself against loss by requiring the subcontractors to give security by bond, or otherwise, for the payment of those who contract directly with the subcontractors . . .” 417 U.S. at 710. Therefore, the onus is on the prime contractor to police the financial responsibility of subcontractors. The court determined, however, that it would be an unreasonable burden upon the prime contractor if he was required to also shoulder the “remote and undeterminable liabilities incurred by ordinary material [men], who may be manufacturers], wholesaler^], or retalíeos].” 417 U.S. at 710.
In Rich, supra, the middleman who agreed to supply custom millwork for a government housing project was determined to be a “subcontractor” because he shared a “special, integral, almost symbiotic relationship with” the prime contractor. 417 U.S. at 711.
In Aetna, supra, the court declined to follow the holding in U.S.v. John A. Johnson & Son, 137 F. Supp. 562(W.D.Pa. 1955) in which the middleman was deemed a subcontractor because it provided custom-built steel ladders, stairs, trench covers and frames, and floor expansion joints to the prime contractor.
While the parties would have us reconcile or choose from the two conflicting rulings by the U.S. appellate courts, such action is unnecessary. The product which Ideal agreed to supply to the prime contractor in the present case was neither custom-made to the prime contractor’s specifications, nor was it a complex installation of relative great importance in relation to the entire project. We can think of few building materials which are more interchangeable and less customized than a brick. Plaintiff has not indicated that the bricks it
The relationship between the prime contractor and the middleman in this case was not an “integral,” “symbiotic relationship” and the middleman had not assumed the responsibility for manufacturing a large and definable part of the construction project. In short, Ideal was merely a materialman who furnished common building materials to the prime contractor. The U.S. Supreme Court has determined, in Miller Act suits, that the prime contractor should not be held responsible for the financial irresponsibility of materialmen and the logic used by the U.S. Supreme Court is equally applicable in the present case. Since we have determined that the middleman is a materialman and not a subcontractor, the plaintiff is not a proper claimant under the terms of the Labor and Material Payment Bond.
ORDER
And now, May 16, 1983, defendant’s motion for summary judgment is hereby granted; plaintiffs cross-motion for summary judgment is denied.
George Danko, Inc. refused to pay 8,840 bucks which had been delivered in excess of the number ordered. These bricks were eventually buried at the job site when Ideal failed to remove them as requested.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.