Eastern Transp. Co. v. East Carolina Lumber Co.
Eastern Transp. Co. v. East Carolina Lumber Co.
Opinion of the Court
The propositions by which this case is ruled are broadly stated these:
2. This obligation could be met only by performance or something which excused performance in whole or part.
The parties to this action have, by their sins of commission and omission, or at least the confusion in their dealings with each other, created so many difficulties with which their proctors must cope, and have cast upon the trial court such an unnecessarily heavy burden of work, that they have forfeited all claims to consideration, and deserve to be left where, at the close, they found themselves to be. In the first place, they left open to dispute whether they had made one contract or two. In the second place, neither had, or at least neither acted upon, any clear concept of what contract it claimed to have. In the third place, although this is doubtless a consequence of the others, each was seeking to secure all the rights which could possibly flow to it out of the contractual dealings between them, without paying the slightest attention to the obligations upon which those rights depended. Neither even seems to have known or regarded as of any importance with whom it had a contract.
The thread by which we may find our way out of the labyrinth which the parties have builded is found, if there is any, in the thought that the two lumber companies made one or more contracts, and then sought to perform by following the requirements of another contract, which the respondent Turner had made with the garnishee. The result was that each was complaining of defaults of the other, based, not upon the charter party between them, hut based upon the Turner contract. The same explanation, in another form, is that the libelant was looking to the first contract, and the respondent to what has been called the second contract of July 23d.
Proctor for respondent and the cross-libelant has cut the gordian knot of his difficulties by averring the existence of a second contract, and taking his stand upon it. In consequence, all he claims depends upon the finding of. such second contract. Proctor for libelant and the cross-respondent has been able to find no such short and .straight road out of his difficulties. Pie has made it entirely clear that the libelant' seeks to recover the freight claimed to have been earned by two barges and demurrage due to seven others.
The basis of his claim of right, or his cause of action, is, however, by no means of like clearness. The best he has been able to do, as it is perhaps the best which could be done, is to take his stand upon the broad ground that the libelant had a contract which, if performed, or which, so far as performed, gave it the right to what is claimed, and that full performance was excused by respondent’s breach, which, when
The proposition of law involved in this statement of the position of the libelant is in itself clear enough and is sound. The difficulty is in applying it to the fact situation which this case presents. A statement of the facts in anything like detail would expand this opinion, already overlong, to an impossible length. The proctor for the libelant, with an industry and care for which he is to be commended, has grouped some of them for us in his brief. This statement we have found very helpful. Notwithstanding his efforts, however, to keep the statement within limits, by confining it to the most salient facts, he has,required nearly 60 pages for the discussion. This gives a foretaste of what an inquiry into all of the matters in controversy would involve. To meet the task as best we may, we will confine this opinion, so far as possible, to a statement of the main facts upon which the rulings made depend, and discuss the evidentiary facts, along with the findings of fact, which will be filed herewith.
We feel grateful, also, to the proctor for respondent; who has, as before stated, rested his defense, so far as it is affirmative, and his cross-libel wholly, upon the existence of the second contract, which he asks us to find.
One of the many difficulties which an adequate discussion of the merits of this case presents is that there are so few, if any, facts which may be called undisputed. The contract, even of the parties, is in dispute. It is not in dispute however, that the lumber companies executed the charter party, which bears date July 10, 1915. Nor is its meaning in dispute.
The libelant was to have ready for loading at the James City wharves, Newbern, N. C., 18 barges, one on each of named dates. These dates covered the period from August to March, both inclusive, and called for two barges a month, one on the 1st and the other on the middle day of the month, except during the months of October- and November, when a third barge was to report on the 26th of each month. These arrivals were to be “on or about the date named, weather conditions permitting.” The freight was made payable on delivery of cargo. As will appear by the findings of fact, in which the movements of each barge are followed, the libelant had a barge to report for loading always on time, and usually ahead of time, until November 26, 1915. This statement includes 9 barges out of the 18. There was a barge due on that date, and another on December 1st following. The next barges to arrive reported December 6th and 10th. No other barges reported until February 14, 1916, although there were 4• barges due on the intermediate dates and one on that date. The next contract arrival dates were March 1st and 16th (the latter being the closing date of the contract), but no barges reported until March 20th and April 20th. The freight on neither of the two last barges was paid. The libelant supplied no more barges.
It is to be observed that it supplied 9 barges in accordance with its contract; then 2 barges, each of which was 11 days behind schedule; then no barges for four trips; then one barge, which was 2 months
The only answer counsel for libelant puts forth is that the respondent nagged and harassed the libelant, by asking for barges faster than the contract schedule, and then not loading them, and by not paying promptly either demurrage or freight, and that libelant was hampered in having its barges on time by its inability to get tugs to tow them.
However real its troubles and difficulties may have in fact been, and they were real enough, we see in them no legal excuse for nonperformance. The first excuse is either unjustified or a dangerous one to make. The charter party called for a schedule which, until November 26fh, was more than met. The answer of libelant to complaints made during this time was ready at hand. It was more than living up to its contract. Complaints after that date were not only justified, but respondent might well have called off the contract.
The respondent has set up a second contract to furnish one additional barge per month. This second contract the libelant denies. If the complaints of the respondent were because of nonperformance of this second contract (and the fact is it was in no respect performed), the libelant recognized the existence of this contract by attempting to perform or to excuse nonperformance.
The conclusions reached are that the libelant has shown no cause of action, because it has admittedly not performed in full, nor has it shown a right to recover for part performance, through excusing full performance by declaring a breach because of the default of the other
A contract, even after one party is in default, is either on or off, and although the innocent party has the right of election, and although the right recurs at each succeeding default, it is a right which must be exercised during the life of the contract, and the election cannot be deferred until after the contract is at an end, and the rights of the parties have become otherwise fixed:
An order may be prepared, dismissing both the libel and cross-libel, each party to pay their own costs, and neither party to pay costs to the other, the record costs to be paid by the one by whom incurred. To give definite date to the order none is now made, but either party has leave to submit the form of one to be entered.
<gs»Por other cases see same topic & KEY-NUMBKR in all Key-Numbered Digests & Indexes
Reference
- Full Case Name
- EASTERN TRANSP. CO. v. EAST CAROLINA LUMBER CO. (PHILADELPHIA & READING COAL & IRON CO., Garnishee)
- Status
- Published