Picini v. Gillette
Opinion of the Court
This is an action of assumpsit by plaintiffs, owners of a building, against defendant, a building contractor, for damages for failure to complete a building project in accordance with the terms of a written contract. The failure and subsequent abandonment of the project by the contractor was conceded and the questions at issue concern damages only. Plaintiff claims the return of the money advanced on the contract, together with damages to be measured by the cost of completion so far as possible to obtain the results contemplated by the contract. Defendant claimed in diminution of damages the extra cost he was put to by reason of the unwarranted interference by plaintiffs with the method of performing the contract and allowance for performance of a part contract, which he claimed was severable from that part which he ultimately abandoned, and
The jury returned a verdict for $300. Plaintiffs now move for a new trial and press these reasons:
1. That the trial judge was in error in permitting the jury to consider the cost of the partially performed work in diminution of damages.
2. That the verdict was inadequate and not consistent with any aspect of the evidence as to damages.
The written contract between the parties clearly specified separate work to be done on the exterior and interior of the building and specified a flat price for the complete job, $1,450. No time was specified for either the beginning or the completion of the job. There was evidence that the contract was entered into in December 1949, while plaintiffs’ building was in course of construction and before it was ready for the application of the exterior surfacing material contemplated by the contract. There is further evidence that within a few weeks thereafter plaintiffs demanded that defendant commence the work, although in the middle of winter and against the warning and protest of defendant that the exterior tile could not be successfully applied in that weather because of the nature of the binding materials required, and that plaintiffs agreed to take the chance of success because of their desire for early completion of their entire project. The contract itself carried no time or date for either the beginning or the completion of the contract. Accordingly, if this evidence was believed, it justified the jury in considering the evidence of defendant of an initial failure and subsequent preparation for replacement of the defective work as caused by unwarranted interference by plaintiffs with defendant’s prerogative of performing the work in accordance with
Plaintiffs do not question the theory that extra expense to the contractor, caused by the owners’ unwarranted interference with the execution of his contract, may be proved in diminution of damages, but do submit that the evidence does not warrant finding any specific amount. However, as noted above, we believe that the calculation was not difficult and was clearly deducible from the evidence.
The contract also provided for surfacing of part of the walls of the restrooms with the same material as to be applied to the exterior of the building and to provide flooring for these rooms of asphalt tile. The evidence shows that this work was completed and has been accepted by plaintiffs and there is evidence from which the reasonable cost of that work can be placed at $650. Plaintiffs, however, contend that since the contract was a flat rate, this item should not be allowed as in diminution of damages, since if defendant here had in turn been a plaintiff he could not have recovered this amount in a suit on a contract, because completion of so much of the contract would not amount to substantial per
Taking the evidence most likely to support the verdict, therefore, plaintiffs’ direct loss would be their advance payments on the contract, $700, plus the cost of completing the exterior job, which at figures deducible from defendant’s evidence would be $670 or a total of $1,370. If the jury placed credence on defend
Now, June 16, 1952, the rule to show cause why a new trial should not be had in the above-entitled case is discharged.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.