Sports Management Group, Inc. v. Allensville Planing Mill, Inc.
Opinion of the Court
This action was brought by plaintiff following the collapse of the roof of its gymnasium building during January of 1979. The gymnasium had been erected during the summer of 1976 for its previous and original owner. Plaintiff purchased the building during early 1977.
By complaint filed March 12, 1979 plaintiff commenced this action in trespass and assumpsit against Allensville Planing Mill, Inc. (Allensville), the construction contractor who built the gymnasium for plaintiff’s predecessor in title, and Alpine Engineered Products, Inc. (Alpine), the supplier of the roof design utilized by Allensville in its construction of the building. Both defendants filed preliminary objections in the nature of a demurrer. No other matters were raised by defendants’ prehminary objections. Argument was heard on August 6, 1979.
Count III of plaintiff’s complaint sounds in assumpsit and is based on breach by defendant Allensville of express and/or implied warranties that the gymnasium building and roof were merchantable and fit for the purpose for which they were
In Elderkin v. Gaster, 447 Pa. 118, 128, 288 A. 2d 771, 777 (1972), the Supreme Court held that a residential developer/builder-vendor “impliedly warrants that the home he has built and is selling is constructed in a reasonably workmanlike manner and that it is fit for the purpose intended— habitation.” In Spencer v. Leo S. Firanski & Son, Inc., 67 D.&C. 2d 235 (1974), the courtfound that a remote purchaser (who purchased the house from the party for whom defendant-builder originally constructed it) could enforce the implied warranty established by Elderkin v. Gaster, supra. The court relied upon Salvador v. Atlantic Steel Boiler Co., 457 Pa. 24, 319 A. 2d 903 (1974), which established that lack of “horizontal privity” no longer barred suit for breach of warranty. In other words this decision meant that an aggrieved party could sue regardless of lack of contractual privity with the party which had allegedly breached an implied warranty. The suing party was no longer required to be the original purchaser in order to bring suit. The abolition of the requirement of “vertical priv
In light of the above authorities and the legal developments reflected therein, we cannot say that extension of implied warranty to the instant factual situation would be unreasonable. Such extension would not constitute a quantum leap in legal development but rather a logical extension consistent with the progression of legal development as reflected in the above cited cases. While the present case does not deal with a builder/vendor of a residential dwelling it does not appear that extension of the holding in Elderkin v. Gaster, supra, to the present case would be illogical or inconsistent with recent legal developments.
Count IV of plaintiff’s complaint is also in assumpsit. It charges Allensvüle with breach of a contractual provision to the effect that all work on the gymnasium was to be completed in a workmanlike manner according to standard practices. Even if this express contractual provision were held applicable to plaintiff there are problems of contract verification to be considered with respect to this count. A copy of the purported contract containing this aüegedly breached provision is attached to plaintiff’s complaint as Exhibit “A.” The document is a proposal by Allensvüle submitted to one Ed Isabella of Camp Woodward in Woodward, Pa. At the bottom of the document adjacent to a paragraph entitled “Acceptance of Proposal” there is an apparently undated signature. The signature is illegible. Nothing appears in the document or in the complaint to establish that this was the contract between Allensvüle and plaintiff’s predecessor in title and original owner of the gymnasium, National Centers, Inc. No connection between Ed Isabella and the original owner is ascertainable. The only link between the two would appear to be the reference to Camp Woodward in Woodward,
There would appear, then, to be no contractual rights in plaintiff arising from a contract between Allensville and plaintiff’s predecessor in title for which the gymnasium was built unless same could be extended to plaintiff as an intended or third-party beneficiary under the rationale that all subsequent owners possess the right to enforce standards of workmanship set forth in the original contract. While we believe that it is extremely doubtful that plaintiff could establish third-party beneficiary rights, we would point out that the relief sought in Count IV of plaintiff’s complaint could be adequately pursued by Count III. The two counts are essentially parallel and would reach the same end if plaintiff prevailed on either or both. Accordingly we will sustain the demurrer to Count IV.
Count II sounds in trespass. Plaintiff charges therein that Allensville is strictly hable in tort for the loss occasioned by the collapse of the gymnasium roof under the principles of section 402A of the Restatement, 2d, Torts. As noted by counsel for Allensville in its reply brief, the case of Cox v. Shaffer, 223 Pa. Superior Ct. 429, 431, 302 A. 2d 456, 457 (1973) (allocatur refused), would appear to render section 402A inapplicable. There it was stated, in a case charging the defendant with strict liability in connection with the construction and design of a silo for and on land belonging to plaintiff’s employer, that “the language of Section 402A reveals, that section applies only to ‘One who sells any product in a defective condition.’ A silo constructed in place on the employer’s land is not a sale of a ‘product.’ We find the section inapplicable by virtue of its very clear language and find no need to
ORDER
Now, February 15, 1980, after argument of August 6, 1979, defendants’ demurrers are overruled as to Counts I, II, III and V of plaintiff’s complaint and sustained as to Count IV.
Defendants shall plead over within 20 days after notice hereof.
. Assisted by John K. Mort, Esq., Law Clerk.
. Krisovich v. John Booth, Inc., supra, involved a construction contractor who installed an underground gas main beneath a dirt sidewalk. As a result of improperly tamped back fill, the plaintiff was injured while walking on the sidewalk when the ground suddenly gave way underneath him. Defendant was found liable despite the fact that he had finished his work and that same had been accepted by the township which hired him because the injury to plaintiff was a foreseeable result of the construction contractor’s negligence.
. See Metropolitan Edison Co. v. United Engineers & Constructors, Inc., 4 D.&C. 3d 473 (1977).
. See, for example, Patitucci v. Drelich, 153 N.J. Super. 177, 379 A. 2d 297 (1977), wherein the New Jersey Superior Court held that a developer/builder vendor was strictly hable in tort for the sale of a lot and house with a sewage disposal system which placed raw effluent upon the surface of the yard around the house. In applying section 402A the court stated, “It is the completed packaged product as sold which invokes a strict liability doctrine regardless of which technical aspect of the law of property be labeled.” Id. at 299. Such a ruling recognizes and is consistent with the principle that an unduly narrow and restrictive definition of “product” serves to undermine the vitality and purpose of the doctrine announced by section 402A.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.