Nertavich v. PPL Electric Utilities
Opinion of the Court
— Plaintiff Vincent Nertavich, Jr. suffered catastrophic injuries when he fell 40 feet from a electric transmission pole that he was painting owned by defendant PPL. He sued defendant PPL and the manufacturer of the ladder he used to climb the pole, defendant Thomas & Betts Corporation. After
Defendant PPL owns 90-foot-high, 10-foot-in circumference tubular steel electric transmission poles. Some of these poles need to be repainted from time to time to prevent structural decay. PPL contracted with QSC Corporation, plaintiff’s employer, to paint the poles. The contract called for work to begin in August 2007 and be completed by November 2007.
That PPL specification document contained a variety of detailed requirements about the job. It prescribed each step how to paint the poles. The paint, a special type specified in the contract, would arrive at the worksite compounded and ready for use, could only be thinned with the approval of PPL’s field representative, and had to be mixed and stirred frequently.
Paint shall be applied by roller, brush, and/or mitt. When brushing is used, all brush marks and laps shall be concealed and joints between successive days’ work shall not be visible. All paint shall be applied without runs or sagging of the paint. Additional coats shall be applied when undercoats, stains, or other conditions show through the final coat of paint, until the paint film is of uniform finish, color, appearance and thickness.7
The workmen were to be extremely careful to paint all hard to reach surfaces.
Third, once a coat of paint had been applied, it had to
While the workmen painted, power might continue to surge through the lines attached to the poles.
Pursuant to PPL’s internal guidelines for safety and health procedures, the PPL field representative had the duty to “monitor the contractor to ensure that safety requirements of the contract are adhered to. The PPL contract filed representative will, as warranted by the nature of the work being performed and the contractor’s record of performance, observe the contractor’s performance.”
PPL’s poles dated from the 1980s.
On September 23, 2007, plaintiff Vincent Nertavich was 40 feet off the ground working on a PPL pole. More experienced workers were painting the pole above him. He was standing on one of the climbing ladders. QSC provided plaintiff with a pole belt, a body harness, and two lanyards.
Grim was at the worksite every day.
Another PPL employee, Gallus Wukitsch, also testified at trial. He was a senior engineer in 2007, and PPL’s contract administrator for the QSC job.
Q: That was, in other words, telling QSC how, in one manner, how they were going to be doing their work around the insulators on the poles; is that right?
A: Yes.60
He was asked about the contract provision requiring workers to lay out tarps before work began to catch debris:
Q: [Tjhat’s how you’re telling them in the contract how they’re supposed to do this part of the work[?]
*363 A: Yes.61
He was also asked about the contract provision mandating how spot repairs had to be feathered-edged:
Q: So this was basically telling QSC, in one respect, how they were to do the actual touch-up work, spot painting work; is that right?
A: Yes.62
Mr. Wukitsch also testified about PPL’s role in ensuring job site safety. He admitted that under the terms of the contract and PPL’s internal operating documents, PPL retained a duly to monitor the work during the existence of the contract.
At trial plaintiff called Stephen Estrin as an expert on occupational safety and health.
Plaintiff also presented an electrical consulting engineer, Gregory Booth, as an expert in engineering design and project management.
According to Booth, Mr. Grim asPPLfieldrepresentative had overlapping safety obligations with QSC’s supervisor at the worksite, including the obligation to stop work whenever he observed a worker endangering their life or the life of others.
PPL claims multiple errors it believes entitle it alternately to judgment notwithstanding the verdict or a new trial. Judgment notwithstanding the verdict, or JNOV, is the court directing verdict in favor of the losing party despite a verdict to the contrary.
Grant of a new trial is an extraordinary remedy.
Many of the claimed errors overlap.
A. PPL’s Negligence was Properly Submitted to and Determined by the Jury under the Retained Control Exception to Landowner Liability.
PPL argues that it cannot be held liable for plaintiff’s injuries. Particularly PPL relies on Pennsylvania Supreme Court’s decision in Beil v. Telesis Construction. Inc.
Generally, a landowner who employs an independent contractor owes only the duty of reasonable care to have the property in a safe condition for work, and to warn of known defects, but is not otherwise vicariously liable for injuries to the independent contractor’s employees.
Section 414 of the Restatement (Second) of Torts provides the retained control exception to the no-duty rule:
One who entrusts work to an independent contractor, but who retains the control of any part of the work, is subject to liability for physical harm to others for whose safety the employer owes a duty to exercise reasonable care, which is caused by his failure to exercise his control with reasonable care.102
The comments to §414 further outline the exception. Comment (a) explains “[i]f the employer of an independent contractor retains control over the operative detail of doing any part of the work, he is subject to liability for the negligence of the employees of the contractor engaged thereinf.]”
The employer may, however, retain a control less than that which is necessary to subject him to liability as master. He may retain only the power to direct the order in which the work shall be done, or to forbid its being*369 done in a manner likely to be dangerous to himself or others. Such a supervisory control may not subject him to liability under the principles of Agency, but he may be liable under the rule stated in this Section unless he exercises his supervisory control with reasonable care so as to prevent the work which he has ordered to be done from causing injury to others.104
Comment (c), however, explains that the owner must exercise at least some modicum of control over the way and means that the contractor performs:
In order for the rule stated in this Section to apply, the employer must have retained at least some degree of control over the manner in which the work is done. It is not enough that he has merely a general right to order the work stopped or resumed, to inspect its progress or to receive reports, to make suggestions or recommendations which need not necessarily be followed, or to prescribe alterations and deviations. Such a general right is usually reserved to employers, but it does not mean that the contractor is controlled as to his methods, of work, or as to operative detail. There must be such a retention of a right of supervision that the contractor is not entirely free to do the work in his own way.105
The Pennsylvania Supreme Court applied the retained control exception to determine a landowner was liable for a contractor’s injuries in Byrd v. Merwin.
In two subsequent cases, the Supreme Court determined that the retained control exception did not apply. In Farabaugh v. Pennsylvania Turnpike Commission, the landowner showed a safety videotape to the contractor’s workers before work began, and hired a construction manager to supervise safety issues for the project and conduct safety inspections.
The Supreme Court most recently addressed the retained control exception in Beil.
The court stated that the control required to meet §414’s retained control exception can be demonstrated through contractual provisions that give the landowner control over the manner, method, and operative details
Here, PPL through its contract and specifications told QSC workers what paint to use, and every step of how to use it. It told the workers to lay out tarps beneath the poles, to mix and stir the paint, to clean and dry the poles, to paint the poles with rollers, brushes, and mitts, to let the paint dry hard and firm, then to apply successive coats, to
The contract also called for safety provisions to be followed, and established the position of the PPL contract field representative. PPL’s contract field representative, Mr. Grim, was at the worksite every day, and knew that it was his duty to stop work if he saw an unsafe condition, even if he was not knowledgeable enough to know when such a condition existed. Mr. Grim was supposed to hold safety meetings every day for the workers, even though he did not. He had the duty to inspect worker fall protection.
Also, PPL exerted great control over access to the property. Through its green tag procedure, PPL retained control of the property, and significantly limited worker access to the poles because of the live electric wires. Workers could not get on the poles until Mr. Grim let them. Also, the available ways to scale the poles were essentially limited to the single-rail ladders because the poles were energized, and there were no other attachment points on the poles to rig other climbing devices. QSC had to request these ladders from PPL to climb the poles.
These facts, especially the way in which PPL dictated how QSC workers were to perform their painting work coupled with evidence of control over safety and access, evince the quality of control that the Supreme Court found lacking in Beil.
B. The Jury Charge, Based on the Standard Instructions, Accurately Provided the Jury with the Law Necessary to Determine the Factual Issues Presented.
Defendant PPL claims multiple errors in the jury charge related to negligence on the basis that it inaccurately conveyed the principles of Beil.
This is a negligence case. And the first question is: was PPL Electric Utilities Corporation negligent? And it has a place for you to check yes or no. The legal term negligence, otherwise known as carelessness, is the absence of ordinary care that a reasonably prudent person would use under the circumstances presented. Negligent conduct may consist of an act or or a failure to act when there is a duty to do something....Now, you’ve heard two weeks, I guess, of testimony about PPL and [QSC]. And that’s what we call an independent contractor. PPL hired [QSC], an independent contractor. The employer of an independent contractor — and all that means is PPL — is not usually responsible for any negligent conduct of the contractor or its employees. The exception is where the employer, PPL, retains control over any part of the work. Also, you should*375 know that a person or a corporation, PPL, who undertakes to provide services necessary for the safety of somebody else, assumes a duty to use reasonable care in performing those services.121
While acknowledging that it constitutes the standard jury instruction, defendant PPL argues that the portion of the charge explaining the retained control exception, and the sentence of the charge that explains that an individual who provides services necessary for the safety of another assumes a duty to perform those services non-negligently are erroneous. Instead, defendant PPL contends that the court should have given its proposed jury charges, consisting of five verbose and repetitive pages containing multiple citations to and quotes taken from Beil}
A court’s primary duty when charging a jury is to clarify the issues so that the jury may understand the questions to be resolved.
Here, the court gave the jury, almost verbatim, the suggested standard civil jury charge related to the retained control exception.
Thus, the court’s jury charge was sufficient and proper.
C. The Court Properly Admitted Evidence of Defendant PPL’s Negligence, Including Industry Standards and the Specifications PPL Dictated for its Poles.
Defendant PPL asserts a bevy of alleged errors related to evidence of its negligence. PPL argues that the court impermissibly allowed evidence of PPL’s OSHA and NESC violations, that QSC did not properly train and institute safety precautions for its workers, Mr. Grim’s lack of knowledge and experience regarding safety issues, the design specifications of the pole and the ladders, and alternative methods of climbing the poles. PPL contends this evidence was irrelevant because PPL did not owe
A claim of negligence consists of a duty, a breach of that duty, causation, and damages.
Here, plaintiff presented evidence that defendant PPL was directly negligent. PPL’s internal operating procedures required that its contract field supervisor to monitor worksite safety. PPL’s field contract supervisor Mr. Grim knew that he had duties to monitor the worksite. He knew he had to stop work if he saw an unsafe condition. He knew that he was supposed to ensure that the workers wore proper fall protection. PPL’s contract administrator Mr. Wukitsch confirmed Mr. Grim’s duties to monitor
PPL set out specifications for its poles that ensured limited access and tie-off points for anyone attempting to scale the pole, even while knowing that the pole would have to be re-painted. The only way to climb the pole was by the single-rail ladders, and the only place for a worker to tie-off is on the ladder itself. Having created this condition, PPL then did not give QSC the bolts to secure the ladders to the pole. Had these bolts been used, the ladders would not have shifted several inches to each side as the worker moved. PPL field representative Mr. Grim should have been aware of the dangers posed by the job to the QSC workers, and admittedly had a duty to ensure the workers knew of the dangers and were prepared to face them. However, neither before awarding the contract nor after work commenced did PPL discern QSC workers’ knowledge, training, or preparedness on how to climb and tie-off on its pole.
Plaintiff’s experts testified that under industry practice, which included OSHA and the NÉSC, defendant PPL breached its duties. PPL should not have allowed QSC workers to tie off to the single-rail ladders, and at the very least should have given QSC the bolt to secure the ladders. PPL had a duty to provide a competent field representative. But, they provided Mr. Grim, who knew so little about climbing a transmission pole that he did not even know plaintiff was tied-off incorrectly. Mr. Grim did not inspect QSC worker equipment, or ensure safety meetings were held.
This evidence ofPPL’s direct negligence was admissible
D. The Court Properly Found that Assumption of the Risk did not Apply Where There was no Evidence that the Plaintiff Appreciated a Risk and Incurred it Anyway.
Defendant PPL contends that the court should have granted it judgment on the basis that plaintiff assumed the risk of his fall, or alternatively put the issue to the jury.
Assumption of the risk is an affirmative defense that arises when a plaintiff apprehends a danger, and then consciously decides to tempt fate and face the danger.
Assumption of the risk is a question for the court to decide and not a matter for the jury.
The doctrine has been severely limited except for the most egregious situations where the plaintiff has clearly taken on the risk. The seminal example of assumption
Here, plaintiff testified that he performed his job in the same way that he always had previously, and that he did not know that he was tied off improperly. He testified that he did not know the danger that he was in. He did not know that he needed to wear a harness. His job, which included reaching out and slapping paint on to the back of a pole, was dangerous. But there was no evidence presented that plaintiff subjectively expected that his lanyard would slip, and yet faced the risk anyway. Defendant did not prove that, as a matter of law, plaintiff assumed the risk. The case properly went to the jury for determination based
For the reasons set forth above, post-verdict motions were denied.
. Contract for transmission structure painting between PPL Electric Utilities Corp. and QSC Painting, Aug. 30,2007, pg. 1 (Ex. P-83).
. Attachment A to contract for transmission structure painting between PPL Electric Utilities Corp. and QSC Painting, Aug. 30, 2007, ¶1 (Ex. P-83).
. Specification for the maintenance painting of transmission structures, Aug. 3,2007, appended to contract for transmission structure painting between PPL Electric Utilities Corp. and QSC Painting, Aug. 30,2007, §§8.2, 8.3, 8.4 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §8.5 (Ex. P-83).
. Attachment A to contract for transmission structure painting between PPL Electric Utilities Corp. and QSC Painting, Aug. 30, 2007, ¶11 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §6.0 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §8.6 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §8.7 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §8.10 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §9.0 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §8.8 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §13.0 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §14.0 (Ex. P-83).
. Specification for the maintenance painting of transmission structures §15.0 (Ex. P-83).
. Attachment A ¶17 (Ex. P-83).
. Attachment A ¶4 (Ex. P-83).
. Attachment A ¶2 (Ex. P-83).
. Attachment A ¶6 (Ex. P-83).
. N.T. 02/29/12, pg. 14 line 2-pg. 15 line 5.
. N.T. 02/29/12, pg. 15 line 25-pg. 16 line 5.
. General Safety & Health Procedures Section 19, “Contractor Safety,” revised January 2005, pg. 8, §7.2 (Ex. P-68).
. Id.
. N.T. 02/29/12, pg. 17, lines 6-8.
. N.T. 02/29/12, pg. 21 line 5-pg. 22 line 15.
. N.T. 02/29/12, pg. 22 line 16-pg. 24 line 4.
. N.T. 02/29/12, pg. 19, lines 6-14.
. A vang is a welded-on piece of metal to which a worker can attach a lanyard or other fall protection. N.T. 03/29/12, pg. 29 line 25 — pg. 30 line 3.
. N.T. 02/29/12, pg. 29 line 24-pg. 30 line 19.
. N.T. 02/29/12, pg. 26 line 10-pg. 27 line 21.
. N.T. 02/29/12, pg. 26 line 18-pg. 27 line 7.
. N.T. 03/07/12, pg. 169 line 2-pg. 170 line 17.
. N.T. 02/29/12, pg. 29, lines 13-18.
. N.T. 02/29/12, pg. 36 line 3-pg. 37 line 9. See also Ex. P-52.
. N.T. 02/29/12, pg. 37 line 24-pg. 38 line 6; N.T. 03/02/12, pg. 40, lines 8-12.
N.T. 02/29/12, pg. 33, lines 7-20.
. N.T. 03/07/12, pg. 160, line 4.
. N.T. 02/29/12, pg. 159, lines 12-20.
. N.T. 03/01/12, pg. 24, lines 2-5.
. N.T. 03/01/12, pg. 33, lines 3-22.
. N.T. 03/01/12, pg. 73 line 24-pg. 75 line 8.
. N.T. 03/01/12, pg. 57 line 22-pg. 61 line 20.
. N.T. 03/01/12, pg. 65 line 24-pg. 71 line 11.
. N.T. 03/01/12, pg. 75 line 6-pg. 76 line 9.
. N.T. 03/01/12, pg. 80 line 16-pg. 84 line 25.
. N.T. 02/29/12, pg. 154, lines 7-13.
. N.T. 02/29/12, pg. 154 line 23-pg. 155 line 3.
. N.T. 02/29/12, pg. 158, lines 9-14.
. N.T. 02/29/12, pg. 158, lines 15-25.
. N.T. 02/29/12, pg. 159, line 25-pg. 160 line 9.
. N.T. 02/29/12, pg. 154 line 14-pg. 156 line 5.
. N.T. 02/29/12, pg. 157, lines 12-13.
. N.T. 02/29/12, pg. 159, lines 2-7.
. N.T. 02/29/12, pg. 167, lines 16-22. He observed plaintiff with great enough detail to remember an occasion on which he saw plaintiff smoking a cigarette while on the pole. N.T. 02/29/12, pg. 184 line 21 — pg. 185 line 9.
. N.T. 02/29/12, pg. 167 line 23-pg. 168 line 4.
. N.T. 02/29/12, pg. 168, lines 5-14.
. N.T. 02/29/12, pg. 169 line 2-pg. 170 line 19.
. N.T. 02/29/12, pg. 172 line 23-pg. 173 line 8.
. N.T. 02/29/12, pg. 168, lines 5-14.
. N.T. 02/29/12, pg. 79, lines 13-15.
. N.T. 02/29/12, pg. 52, lines 7-11.
. N.T. 02/29/12, pg. 54 line 23-pg. 55 line 2.
. N.T. 02/29/12, pg. 56, lines 9-12.
. N.T. 02/29/12, pg. 70, lines 18-22.
. N.T. 02/29/12, pg. 78, lines 4-24.
. N.T. 02/29/12, pg. 79, lines 10-19.
. N.T. 02/29/12, pg. 73 line 22-pg. 74 line 7.
. N.T. 02/29/12, pg. 81, line 8-12.
. N.T. 02/29/12, pg. 82, lines 5-12.
LÑ.T. 02/29/12, pg. 83 line 13-pg. 84 line 9.
. N.T. 02/29/12, pg. 85 line 24-pg. 86 line 16.
. N.T. 03/06/12, pg. 48 line 20-pg. 55 line 23.
. N.T. 03/06/12, pg. 119, lines 19-20.
. N.T. 03/06/12, pg. 70, lines 10-13.
. N.T. 03/06/12, pg. 120, lines 21-23.
. N.T. 03/06/12, pg. 97, lines 10-16.
. N.T. 03/06/12, pg. 116, lines 16-18.
. N.T. 03/06/12, pg. 120 line 24-pg. 121 line 2.
. N.T. 03/06/12, pg. 143, lines 22-25.
. N.T. 03/06/12, pg. 143, lines 2-8.
N.T. 03/06/12, pg. 122, lines 19-22.
. N.T. 03/06/12, pg. 123, lines 5-11.
. N.T. 03/06/12, pg. 123, lines 14-22.
. N.T. 03/01/12, pg. 200, lines 11-18.
. N.T. 03/01/12, pg. 249 line 20-pg. 250 line 10.
. N.T. 03/01/12, pg. 261, lines 3-14.
. N.T. 03/02/12, pg. 18 line 13-pg. 19 line 18.
N.T. 03/02/12, pg. 21 line 20-pg. 22 line 14.
. N.T. 03/01/12, pg. 255 line 19-pg. 256 line 9.
. N.T. 03/01/12, pg. 232, lines 17-22.
. N.T. 03/02/12, pg. 29, lines 5-16.
. Green Valley Dry Cleaners. Inc. v. Westmoreland Cnty. Indus. Dev. Corp., 861 A.2d 1013, 1016 (Pa. Commw. Ct. 2004).
. Rohm & Haas Co. v Cont’l Cas. Co., 732 A.2d 1236, 1248 (Pa. Super. Ct 1999) aff'd, 566 Pa. 464, 781 A.2d 1172(2001).
. Moure v. Raeuchle, 604 A.2d 1003, 1007 (Pa. 1992).
. Criswell v. King. 834 A.2d 505, 512 (Pa. 2003).
. Armbruster v. Horowitz, 813 A.2d 698, 702 (Pa. 2002).
. Harman ex rel. Harman v. Borah, 756 A.2d 1116, 1122 (Pa. 2000).
. Renna v. Schadt, 64 A.3d 658,670 (Pa. Super. Ct. 2013) (internal citations omitted).
. Harman, 756 A.2d at 1122.
. Id.
. 11 A.3d 456 (Pa. 2011).
. Calender v. Allegheney County Sanitary Auth., 222 A.2d 461, 463 (Pa. Super. Ct. 1966).
. Restatement (Second) of Torts §414 (1965).
. Restatement (Second) of Torts §414 com. (a).
. Id.
. Restatement (Second) of Torts §414 com. (c).
. 317 A.2d 280 (Pa. 1974).
. id at 282.
. Farabaugh v. Pennsylvania Turnpike Com’n, 911 A.2d 1264, 1271 (Pa. 2006).
. Id. at 1275. See also LaChance v. Michael Baker Corp., 869 A.2d 1054 (Pa. Commw. Ct. 2005) (holding that retained control exception did not apply where landowner contractually retained and exercised right to safety inspections, but did not exercise any other control over the manner or operational details of the project, because contract language
. Id. at 1282.
. 11 A.3d456 (Pa. 2011).
. Id. at 462.
. Id. at 465.
. Id. at 467.
. Id. See also Hargrove v. Frommeyer & Co., 323 A.2d 300, 304 (Pa. Super. Ct. 1974)(holding that evidence of landowner supervising design and construction of building sufficient ot submit issue of control to the jury).
. Id. at 469.
. Id. at 469 n. 4.
. Id. at 471.
. Plaintiff’s claim survived a motion for summary judgment, a
. Defendant alleges the same defects in the jury verdict sheet.
N.T. 03/08/12,pg. 296 line21-pg. 298 line23.
. These were defendants proposed charges 19 through 23.
. Com. v. Beach, 264 A.2d 712, 714 (Pa. 1970).
. Butler v. Kiwi, S.A., 604A.2d 270, 273 (Pa. Super. Ct. 1992).
. Hawthorne v. Dravo Corp., Keystone Div., 508 A.2d 298, 303 (Pa. Super. Ct. 1986).
. Buckley v. Exodus Transit & Stroage Corp., 744 A.2d 298, 305 (Pa. Super. Ct. 1999).
. Id. at 306.
. Id
. See Ouinby v. Plumsteadville Family Practice, Inc., 907 A.2d 1061, 1069-70 (Pa. 2006) (“A charge will be found adequate unless the issues are not made clear to the jury or the jury was palpably misled by what the trial judge said or unless there is an omission in the charge which amounts to a fundamental error.”).
. See SSJI 6.140 (2003).
. Beil, 11 A.3dat466.
. For this proposition, at oral argument defendant relied upon dicta in Fulmer v. Duquesne Light Co., 543 A.2d 1100, 1105 (Pa. Super. Ct. 1988), that a landowner need not take every precaution to prevent injury to a contractor’s employees. However, that case says nothing that negates a landowner’s duty to act with reasonable care if the landowner does in fact endeavor to take a precaution to prevent worker injuries.
. Feld v. Merriam, 485 A.2d 742, 746 (Pa. 1984).
. Pascarella v. Kelley, 105 A.2d 70, 73 (Pa. 1954).
. Grossman v. Barke, 868 A.2d 561, 566 (Pa. Super. Ct. 2005).
. Scampone v. Highland Park Care Ctr., LLC, 57 A.3d 582, 597 (Pa. 2012).
. Chenot v. A.P Green Servs., Inc., 895 A.2d 55, 63 n.6 (Pa. Super. Ct. 2006).
. Feld, 485 A.2d at 746.
. See Health v. Huth Enigineers, Inc., 420 A.2d 758, 759 (Pa. Super. Ct. 1980).
. Birt v. Firstenergy Corp., 891 A.2d 1281, 1290 (Pa. Super. Ct. 2006).
Bullman v. Giuntoli, 761 A.2d 566, 570 (Pa. Super. Ct. 2000).
. Staub v. Toy Factory. Inc., 749 A.2d 522, 527-28 (Pa. Super. Ct. 2000).
. Bullman, 761 A.2d at 570.
. Staub, 749 A.2d at 528.
. Bullman, 761 A.2d at 571.
. Barrett v. Fredavid Builders, Inc., 685 A.2d 129, 131 (Pa. Super. Ct. 1996).
. Staub, 749 A.2d at 529.
. Struble v. Valley Forge Military Academy, 665 A.2d 4, 8 (Pa. Super. Ct. 1995). Defendant cites to Longv. Norriton Hydraulics, 662 A.2d 1089 (Pa. Super. Ct. 1995), to argue that Pennsylvania law is unsettled regarding whether assumption of the risk is an issue for the judge or the jury. The Long opinion does not hold, as Defendant implies, that assumption of the risk is a jury matter. The Superior Court in Long found that the trial court improperly granted summary judgment on the basis of assumption of the risk because it was not beyond question that plaintiff knowingly and voluntarily faced an obvious danger, and that the case should proceed to trial. 662 A.2d at 1091. The Superior Court did not, however, state that the issue of assumption of the risk should go to the jury. In Struble, an opinion issued approximately four months after Long and authored by the same judge, the Superior Court explicitly stated “that the question of whether a litigant has assumed the risk is a question of law and not a matter for jury determination,” and further made clear that “once the trial court decides that assumption of the risk is not the basis for a compulsory nonsuit, the jury is to be charged only on comparative negligence.” Struble, 665 A.2d at 8.
. Long v. Norriton Hydraulics, 662 A.2d 1089, 1091 (Pa. Super. Ct. 1995).
. Staub, 749 A.2d at 529-30.
. Struble, 665 A.2d at 8.
. 469 A.2d 120, 125 (Pa. 1983).
. Staub v. Toy Fatcory. Inc., 749 A.2d 522 (Pa. Super. Ct. 2000).
. Id. at 530 (internal quotes and citation omitted).
Case-law data current through December 31, 2025. Source: CourtListener bulk data.