Clements v. Schuyl. R.
Clements v. Schuyl. R.
Opinion of the Court
CLEMENTS V. RAILROAD CO.
Opinion,
The question whether a sum named in a contract, as a compensation for its breach, is to be regarded as a penalty or as liquidated damages, has been so recently considered and discussed that it is not deemed necessary to review the authorities: Streeper v. Williams, 48 Pa. 450; Mathews v. Sharp, 99 Pa. 560; Moore v. Colt, 127 Pa. 289. The intention of the parties has much to do with it. Yet even that will be controlled where equity demands it. A sum expressly stipulated as liquidated damages will be relieved from if it is obviously to secure a sum capable of being compensated by interest. It is difficult
It remains to apply these principles to the facts of this case. In the contract between the plaintiffs and Ellis, by which the latter agreed to raise the house No. 2503 Hamilton street, the damages for the delay are not designated either as a penalty or as liquidated damages, but the said Ellis is to pay $150 per' week “ for each and every week after the expiration of thirty days from the date of the delivery of the property to the party of the first part,” (Ellis.) The work was not completed within the thirty days. The evidence is not clear as to the exact extent of the delay, but the jury returned a verdict for the plaintiffs for $4,400. The learned judge below was requested by the defendants’ second point to instruct the jury as follows: “ The weekly amounts named in the contract in case of delay in the completion of the work, upon Avhich the plaintiffs rely for a verdict, are to be considered as a penalty, and not liquidated damages. The jury, therefore, cannot in any event allow any larger sum as damages for delay than that sum which will repay for actual losses proved by the plaintiffs due to such delaju” The learned judge refused this point, and instructed the jury that the sum named Avas to be treated as liquidated damages. The jury allowed $150 per week for the delay.
When it is considered that the house and lot in question
This disposes of the controlling point in the case. As it must go back for re-trial, however, it is proper to say that the change of grade referred to in the twelfth assignment possesses little significance. The contract was to raise the house to the grade of the city, as provided by the ordinance approved July 3, 1885, and the contract would have been fulfilled by conforming to that grade, notwithstanding a subsequent change of the grade by the city.
There are some other matters which might be referred to as error, but they result from the theory upon which the case was tried. They will doubtless be corrected upon another trial.
The judgment is reversed, and a venire facias de novo awarded.
THOMPSON V. RAILROAD CO.
Opinion, Mr. Chief Justice Paxson :
This case is ruled by Clements v. same defendants, just decided.
The judgment is reversed, and a venire facias de novo awarded.
Reference
- Full Case Name
- J. C. CLEMENTS v. SCHUYL. R. ETC. R. CO. W. R. THOMPSON v. SCHUYL. R. ETC. R. CO.
- Cited By
- 5 cases
- Status
- Published
- Syllabus
- 1. When it is difficult or impossible to ascertain the damages for the breach of a contract by any fixed rule, there is a reason whjr the parties should liquidate them in advance, as stipulated damages, and why the courts should afterwards hold them to such liquidation. 2. But, when the damages can be assessed easily and accurately, and they are fixed by the contract itself at an unconscionable sum, it is the plain duly of a court exercising equity powers to relieve against such injustice, and to treat the sum named as a penalty merely, which will do no injustice to either party. 3. A contract to raise a dwelling, the rental value of which was about $25 per month, provided that the owner should be paid $150 per week after the extriration of the period within which the work was to be completed; in such ease, the weekly payment was to be treated merely as a penalty and not as stipulated damages.