Terrerri v. Jutte
Terrerri v. Jutte
Opinion of the Court
Opinion by
If this case were here on a, motion for a new trial, there might be some excuse for the implied reflection on the integrity of the
It is conceded that plaintiff was employed by defendants in the spring of 1890, and continued in their service for nearly three months, but the parties differ very widely as to the terms, etc., of their contract relation. Plaintiff alleged and testified, in substance, that he was first employed by defendants as superintendent of their stone quarry at a salary of $100 per month; that, afterwards, and in addition thereto, he was requested by them to procure supplies, provisions, etc., for boarding their men engaged in and about the quarry, and to transact other business for them; for which expenditures, outlays for traveling expenses, etc., as set forth in his statement of claim, they promised to reimburse him, etc.
It is conceded that, for amount due him as monthly salary, plaintiff brought suit before a justice of the peace in Fayette county and recovered a judgment for $266.66, which was after-wards paid by defendants, and, of course, is not included in this action.
The defendants testified to an entirely different version of the contract; that, in substance, plaintiff undertook to’operate the stone quarry, at his own expense for employees, etc., for which they were to pay him $4.25 per cubic yard of stone at the quarry. They denied having made any other than this single contract with the plaintiff, in relation to,the matters in controversy.
Without further reference to the testimony of the respective parties to the suit, it is very evident there was a direct conflict as to the facts upon which the right of the plaintiff to recover depended. His testimony was in support of his statement of claim. As to material facts, lie was contradicted by one or
In view of plaintiff’s testimony, before the jury, for their consideration,,it would have been error to have charged as requested in defendants’ first point. If the contract was as he testified, that defendants agreed to pay him $100 per month for his'services as superintendent of their quarry, he had an undoubted right to bring suit for that as a distinct and independent claim, which had no necessary connection with either of the items of claim embraced in this suit. He was not bound, under penalty of forfeiting his right to the latter items to include them in his suit for services as superintendent. Authority for so plain a proposition as that is unnecessary. The transcript of the justice, before whom that suit was brought, clearly shows that plaintiff’s claim in that case was for services at defendants’ stone quarry, “ two months and twenty days at one hundred dollars per month, amounting to two hundred and sixty-six and two thirds dollars.”
For a like reason, there was no error in refusing to charge that “ under all the evidence the verdict should be for defendants, so far as the claim for board is concerned.” If plaintiff’s testimony, as to the contract, was believed, as it evidently was, he was entitled to recover for that as well as other items.
The case was carefully and correctly tried, and fairly submitted to the jury with full and adequate instructions. There is nothing in the record that would justify a reversal of the judgment.
Judgment affirmed.
Reference
- Cited By
- 1 case
- Status
- Published
- Syllabus
- Contract — Entire and severable — Evidence—Question for jury. In an action upon a contract, plaintiff alleged that he was first employed by defendants as superintendent of their stone quarry at a certain salary per month; that afterwards and in addition thereto he was requested by them to secure supplies, provisions, etc., for boarding their men engaged in and about the quarry, and to transact other business for them, for which he was to be reimbursed. This suit was brought for expenses incurred for boarding the workmen. Defendants denied that such was the contract, and averred that plaintiff undertook to operate the quarry at his own expense for employees, for which he was to receive from defendants $4.25 per cubic yard of stone at the quarry. It appeared that plaintiff had previously recovered a judgment against defendants before a justice of the peace, the record of the justice showing that the claim was merely for salary. Eeld, that the second action was maintainableand that the question as to what was the contract between the parties was for the jury.