Ridge Avenue Passenger Railway Co. v. City of Philadelphia
Ridge Avenue Passenger Railway Co. v. City of Philadelphia
Opinion of the Court
Opinion by
This is a suit for damages against defendant for illegally permitting obstruction to travel on Ridge avenue, a street of the city, for several years prior to March 30, 1875. Under act of assembly of March 30,1811, the Ridge Avenue Turnpike Company was incorporated, with right to construct a road from the intersection of Yine and Tenth street to Perkiomen bridge in Montgomery county. This was done, and in, and for a considerable distance out of the city limits was known as the “Ridge Road.” By the terms of the charter, the road was to be macadamized and constructed not less than forty nor more than sixty feet wide, with a good and sufficient summer road at the side thereof where practicable, and the company was thereafter forever to maintain it in perfect order and repair. By the Consolidation Act of 1854, the boundaries of the city were extended to include within its limits all of the road up to the Montgomery county line, and on the city plan the turnpike was adopted as a city street by the name of “Ridge avenue.” By act of April 15,1858, the Girard College Passenger Railway Company was authorized to construct a railway down Ridge avenue from the college to Tenth and Ninth streets. By act of March 28, 1859, the Ridge Avenue and Manayunk Passenger Railway
1. The referee does find plaintiff was inconvenienced by the detention of its cars; was obliged to run fewer cars ; its rolling stock and horses were injured; the passenger traffic and receipts fell off; and, that plaintiff suffered serious damage but,
2. He finds, “ There was not, in the course of the performance of the work under the contracts, any wilful, malicious and intentional delay in the construction of the work or.obstruction in the operation of the railway, or in the traffic and travel there-over.”
Putting aside the question as to the extent of the city’s answerability for the conduct of independent contractors, and assuming for the present that it must respond in damages for them, nevertheless, it seems to us, under the evidence, as well as under the referee’s finding of fact, the plaintiff cannot recover. There was some evidence tending to show unnecessary delay in the work, but, on the other side, the weight of it tended to show nothing more, in the most unfavorable view, than an error of judgment. It is indisputable that the grade adopted by the city could not, from its very nature, have been constructed on the ground, without more or less interruption to travel on the street, both by vehicle and railway. The length of street affected by the change was four miles; to have put at work a sufficient force of men, animals and machinery to accomplish the change in the shortest possible time, would for that time have stopped all travel for the whole length of the avenue. To avoid this total interruption for this distance, the city authorities contracted for the work by nine contracts,, in sections. In 1870, the work between Columbia avenue and Dauphin street was contracted for; in 1872, the paving from Dauphin to Huntingdon streets; in January, 1873, the grading of the avenue between the same points ; in April, 1873, the paving between Allegheny avenue and Wissahickon creek ; in June, 1873, the grading of the street between same points; and so down to October 25, 1873, the date of the last contract. While by this method there was partial obstruction all these years at one or more points, there was not a total stoppage of the travel the whole distance at any one time. As testified by Mr. Jones, president of the railway company, “The whole road from end to end was not impassable, but just such sections as were being worked upon.” It is not demonstrated to a certainty, by the event, that the method adopted was not the best. When the improvement was determined on tbe problem presented was, is it better to absolutely exclude the public from the avenue, including the passenger railway, for one year, and put sufficient force on to complete the work in that time ? Or, should it be done in sections, one piece at a time, leaving the avenue open its whole length, but the public more or less in
Taking the facts to be as found by the referee, are his conclusions of law sustained ? The railway company was only an artificial person using the street in common with natural persons. Whatever rights it may possess in the use of the street, by reason of its construction and purpose, distinct from those of the general public, it has no peculiar or special exemption from the interruption and damage necessarily resulting from municipal improvements. It occupied the highway by grant from the commonwealth, with the written consent of the turnpike company. This very grant, instead of exempting, specially enjoined conformity to the grade of the street now established, or hereafter to be by law established. Afterwards, the turnpike, by proper proceedings, became a city street; the city did not take it subject to indefinite liens or contracts made by the turnpike company in favor of other corporations; it took the subject, the incorporeal hereditament; if thereby any injury resulted to the railway company it must seek reimbursement from the damages paid for the taking, or must have recourse to the contracting party on its covenant. The municipality, under its right, has taken all there was in the turnpike company to take. The very purpose of the taking, and the reason for granting the authority to take the turnpike, is, that for the good of the general public,
It is alleged further the change of grade was unlawful because of failure to have confirmed a revised plan of the grade. While this point seems to have been made before the referee, he barely mentions it in his report, without a specific finding; neither appellant nor appellee has pointed out to us the evidence on which the one avers and the other denies it. The referee does find, however, that the contracts for grading Ridge avenue from Columbia avenue to Dauphin street were, by authority of resolution of councils of March 26, 1870, to accord with the established grade, and that the work should be done as specified in accordance with ordinance approved March 27, 1868; and so, in every contract for grading, each purports to be authorized by a resolution of councils, the grading to be done in accordance with an established city grade. We will not now assume, in absence of full proof, after a trial on the merits, that this irregularity, if it exists, is of such gravity as to render defendant a trespasser in improving its own streets.
We are clear the city had authority to grade and improve this street. In doing this, it had the right to adopt such method of allotting and carrying on the work as to it seemed best. For the damage resulting to the public because of the necessary interruption to travel during the progress of the work, under the plans adopted, it is not answerable to one of the public, unless the complainant shows a damage different in kind and peculiar to himself. The damage here shown by
All assignments of error are overruled, and the judgment is affirmed.
Reference
- Full Case Name
- Ridge Avenue Passenger Railway Company v. The City of Philadelphia
- Cited By
- 2 cases
- Status
- Published
- Syllabus
- Arbitration — Conclusiveness of referee's findings of fact. A finding of fact by a referee is as conclusive upon a court oí error as the verdict of a jury. Street railways — Municipalities—Change of grade — Damages. A street railway company which occupies a street, subject to the right of a city to change the grade, cannot recover damages from the city for inconvenience, detention of cars and loss of business caused by changing the grade, where there has been no intentional delay or neglect in the prosecution of the work; although the damages may be consequent upon a mistake of judgment by the city in the manner of making the change. Street railways — Turnpike companies — Municipalities. A city has the right to establish or change the grade of a street which had once been the bed of a turnpike, without regard to the contracts of the turnpike company with a street railway company antedating the lawful acquisition of the street by the city. A street railway company was given authority by the legislature to lay its tracks upon a turnpike with the consent of the turnpike company. The railway tracks were to conform to the established grade, or the grades thereafter to be established. The railway company stipulated in an agreement with the turnpike company that if the city should at any time purchase the turnpike, the turnpike company would provide in some manner that there should be no interference with the grade of the railway company, and no alteration of the same without the consent of the railway company. The city subsequently acquired the turnpike, and changed its grade. In-making the change of grade the railway company was delayed and injured in its business. Held, that the city was not liable to the railway company for its loss. Street railways — Municipalities—Change of grade — Confirmation of plan. A street railway company occupied a street subject to the right of the city to change the grade. The city entered into various contracts for grading the street, each purporting to be authorized by a resolution of councils, the grading to be done in accordance with an established city grade. The street railway company sued the city for injuries resulting from delay in business during the course of the grading. The case was referred to a referee who found in favor of the city. It was alleged that the change of grade was unlawful because of failure to have confirmed a revised plan of the grade. This point was made before the referee, but he made no specific finding upon it, and the evidence to support it was not pointed out to the Supreme Court. Held, that in the absence of full proof, after trial on the merits, the Supreme Court will not assume that the irregularity, if it existed, was of such gravity as to render the city a trespasser in improving its own streets.