Murphy v. Liberty National Bank
Murphy v. Liberty National Bank
Opinion of the Court
Opinion by
There was a large amount of very intelligent and important testimony on the trial, to the effect that the cause of the falling of the arches was the weakness and insufficiency of the iron work to sustain the weight of the arches. As this was one of the questions submitted to the jury, and the verdict was in favor of the plaintiffs, it must be presumed that they found the iron work to be insufficient, and that this was the cause of the falling of the arches. A careful reading of the testimony on both sides convinces us that the finding of the verdict on that subject was correct. The case is practically argued on the part of the defendant upon the basis that the verdict is conclusive in relation to this matter, and therefore the rule is invoked that
The rule is not strictly and in terms applicable to this case, because the building was completed and was accepted by the owner. And it was completed by the present plaintiffs, the contractors. But a portion of the work was done by another contractor. That is, the filling in of the arches between the beams where the arches had fallen out or been removed for fear of their falling, was done by another sub contractor than the ones who had put in the first fireproofing. This was done at the instance of the architect, and the question is, so far as this matter is concerned, who is responsible for that work, and are the plaintiffs chargeable with a deduction on that account. There is perhaps another reason why the rule invoked for the defendant, is inapplicable. It has an exception if the work to
The eleventh assignment is not sustained. The contract provided that either tile or improved make of concrete construction may be used, and that bids should state what material is contemplated. The contractors having named tile as their material, and their bid having been accepted, and there being no defect in the tiles used, this was a compliance with the contract, and when they actually furnished perfectly good tiling and placed it in the arches, they complied with their contract in
The remaining assignments relate to the claim for extras. There was an amount of $522.38 of extras, which was admitted to be due.' A portion of the claim was for work done in removing the material that had fallen from the arches, and the remainder of the material that had not fallen. This it is claimed was done by specific orders of the architect to'the subcontractor, without consulting with the plaintiffs. There were a few other items, but as to the whole, the evidence raised a question of waiver of the provision of the contract which required that no claims for extras should be made “ unless the same shall be done in pursuance of a written order from the architect.” There was evidence enough on that subject to justify the court in leaving the question to the juiy, and we cannot say there was error in so doing. There was a large diminution by the verdict of the amount of the plaintiffs’ claim for extras, and it is not at all clear that any injustice was done to the appellant by the verdict of the jury in regard to these matters. We do not think that error has been shown in any of the assignments after the eleventh, and they are therefore all dismissed.
Judgment affirmed.
Reference
- Full Case Name
- James A. Murphy and Thomas J. Hamilton, trading as Murphy & Hamilton v. Liberty National Bank
- Cited By
- 9 cases
- Status
- Published
- Syllabus
- Contract—Building contract—Belay—Architect—Befects m plans and specifications. In a scire facias on a mechanic’s lien to recover a balance alleged to be due on a building contract which provided that the work should be done according to the plans of the architect, and that “ whenever the contractor knows or thinks that the drawings or specifications or both for any part of the work will not produce secure construction, it is his duty then to stop the work and to instantly notify the architect of this in writing ” and the work shall not be resumed “ until the contractor receives an order in writing from the architect over his own signature as to what is to be done anti when to proceed,” it appeared that certain arches fell down after they had been built, and that the completion of the work was delayed beyond the stipulated time. Plaintiffs’ evidence tended to show that the falling of these arches was through no fault of theirs, but wholly on account of the architect’s plans. The plaintiffs notified the architect in writing of the entire insufficiency of the iron work to support the arches, and received a reply from the architect in writing that the work would be done by other parties. They never received notice from the architect to proceed with the work, and the fallen arches were replaced by others. The defendants claimed a deduction for the work which was done by other parties and the penalty which was provided in the contract for the delay beyond the specified time for completing the building. The court left it to the jury to say whether the falling of the arches was the fault of the plaintiffs or of the architect. The jury found for the plaintiffs. Held, (1) that if the plans were defective, the rule that a contractor must complete his contract notwithstanding any accident by inevitable necessity did not apply to the facts of-this case; (2) that the plaintiffs did all that was required of them under the contract when they stopped work and notified the architect; (8) that, assuming that the plans were defective, the plaintiffs did not lose their lien because the material which they had placed in the arches had been removed and other material substituted in its place; (4) that if the arches fell and the work was delayed on account of the defective plans of the architect, the expense of rebuilding the arches and the penalty provided by the contract for the delay of the work beyond the stipulated time could not be deducted from the amount duo on the contract. Building contract—Extras— Waiver. A building contract provided that no claims for extras should be made by the contractors “ unless the same shall be done in pursuance of a written order from the architect.” There was evidence that the architect notified certain of the subcontractors to do some extra work, but gave no notice or written directions to the contractors. Held, that it was for the jury to say whether the provision of the contract as to written notice had been waived.