Vulcanite Paving Co. v. McNichol
Vulcanite Paving Co. v. McNichol
Opinion of the Court
Opinion by
This appeal is from an order making absolute a rule for judgment for the amount for which the affidavit of defense was insufficient with leave to proceed for the balance. It appears from the statement of claim that the defendants had entered into a contract with the city of Philadelphia to do all the work and to furnish the materials required in the improvement of a boulevard, and that the plaintiff contracted with them to do a part of this work. There was no formal contract between the parties. The plaintiff submitted a proposal in writing in which it named the prices for which it would do particular kinds of work. The time of payment was fixed by oral agreement. It is alleged in the statement that payments were to be made monthly on estimates furnished by the
The affidavit of defense contains a distinct denial that payments were to have been made on monthly estimates, or that the work done by the plaintiff had been accepted as satisfactory. It sets up an agreement as to the time of payment as follows: “ It was further agreed that when estimates should be made each month by the district surveyor of the fifth district, and rendered to the defendants by the assistant of the bureau of highways for the seventh district, showing the work done and materials furnished by the defendant, up to the date of making the estimate, including the work done and materials furnished by plaintiff, then defendants should pay plaintiff for their work and materials after defendants were paid for the same by the city of Philadelphia; and defendants were not obliged to pay for such work or materials unless and until the same were paid for by the city of Philadelphia; and the plaintiff should do over again at its own expense any part of its work which the defendant should be required by the city of Philadelphia to have done over again in accordance with its contract.”
The additional averments in the affidavit that are material in considering the question before us are that the city had not paid the defendants for any work done under their contract after April 29, but had refused to pay for the same, and had stopped all further work under its contract with the plaintiff. There is an admission in the affidavit that the defendants had been paid by the city the amount of an estimate rendered May 1, 1905, and that in the estimate was included work done by the plaintiff to the amount of $2,270.60.
On the argument of the rule for judgment it was contended by the plaintiff’s counsel that the affidavit was insufficient to prevent judgment for any part of the plaintiff’s claim, and the court was asked to make the rule absolute for the whole amount
The judgment is reversed and set aside, and it is directed that judgment be entered in the common pleas for the amount of the first item of the plaintiff’s claim, $2,270.60, with leave to the plaintiff to proceed for the balance.
The decision of the court on this appeal makes the question presented by appeal No. 60 of the same term unimportant and the appeal is dismissed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.