Hunn v. Pennsylvania Institution for the Instruction of the Blind
Hunn v. Pennsylvania Institution for the Instruction of the Blind
Opinion of the Court
Opinion by
The plaintiff brought an action of assumpsit to recover an alleged balance due on a building contract and in his statement of claim averred performance. The defendant entered a plea of non assumpsit, payment and set-off, to which plaintiff replied non solvit, no set-off and issue. When the case came on for trial the plaintiff offered in evidence the contract, plans and specifications, and then produced as a witness J. W. Mercur, a member of the contracting firm. Counsel being asked what he intended to prove by this witness, placed on record an elaborate offer covering the purpose of the testimony to be given. Counsel for defendant objected on the ground that the contract between the parties showed that final payment was not to be made until the architects had certified that the work had been completed in accordance with the plans and specifications, and it was not proposed to show that the architects had passed upon questions in dispute between the parties, and for the further reason that complete performance having been averred, proof which shows nonperformance or part performance, is not sufficient to sustain the allegata, which objection was sustained by the court.
No further testimony was offered and the learned trial judge directed the jury to return a verdict for defendant. This appeal raises the question whether the proof offered, but rejected, should have been admitted and, if so, was it sufficient to sustain the averments of the declaration. It is elementary that the probata must sustain the allegata, and of course one who avers performance and fails to prove it has no right to recover. In the present case, however, the contention is
Another and perhaps more important question to determine is that which relates to the failure of the offer to show that matters in dispute between the parties had been submitted to the architects, as required by the contract, or that the architects had certified proper completion. By the terms of the contract the architects were made the arbiters of quéstions that might arise between the parties, and it was their duty to certify when the building was finally completed, and it must be conceded that if the contract referred to the arbitration of the architects, the questions of fact involved in the rejected offer of testimony, or if the architects were made the sole arbiters of these questions, and they have not in point of fact done
Judgment reversed and a venire facias de novo awarded.
Reference
- Cited By
- 19 cases
- Status
- Published
- Syllabus
- Contract — Building contract — Performance—Time—Forfeiture—Allegata and probata — Architect. Where a building contract provides for a penalty in case of non-completion within the time specified, and also contemplates final completion by the owners in certain contingencies with the settlement with the contractors after such completion, an averment of complete performance by the contractors is, in so far as the construction of the building is involved, sustained by proof which shows that the contractors performed a large part of the work, and that the building was finally completed by the owners in accordance. with the contract, although not within the time specified. In such a case when the owners completed the building, the day of final settlement had arrived, subject, of course, to the respective rights of the contracting parties as defined by the contract. The law recognizes the right of parties to a contract to stipulate the method of arbitrating questions that may arise between them in the performance of mutual covenants, but no such right exists in the absence of an express covenant, and he who asserts it has the burden of establishing its existence. The usual arbitration clauses in building contracts refer to questions arising between the contractors and owners, and not questions that concern the performance of duties by the architects themselves. Such clauses are in derogation of the common-law right of trial by jury, and are not to be extended beyond the express covenants of the contracting parties. An arbitration clause, such as is usually inserted in a building contract, is not to be construed as showing an intention of the parties to deliberately enter into a covenant providing that the arbiters should have the right to pass upon and finally determine questions involving their own failure in the performance of duties. Where, under the terms of a building contract, the owners after part performance by the contractors, have taken possession of the building and completed it, it is not absolutely necessary for the contractors in a suit to recover the balance alleged to be due them to produce a certificate from the architects that the building had been properly completed. The certificate was intended as a protection to the owners, and they may waive their right in this respect, and the question whether they have waived their right is for the jury.