Point Bridge Co. v. Pittsburg & West End Railway Co.
Point Bridge Co. v. Pittsburg & West End Railway Co.
Opinion of the Court
Opinion by
For a number of years the defendant railway company had operated a line of horse cars across a bridge belonging to the plaintiff bridge company. In 1892 the motive power was changed to electricity and a disagreement arose concerning the compensation to be paid for the future occupancy of the bridge. The railway company filed a bill asking that the bridge company be restrained from interfering with the operation of its cars, and praying the court to fix the compensation to be paid for the use of the bridge. On November 12, 1892, a decree was entered which fixed the compensation at $8,000 per annum for the next five years, and expressly provided, “either party hereto at any time may, during the continuance of this order make application to the court, and for proper cause may move a modification of this decree or such other and further order in this case as may, under the circumstances then existing, be proper.” This decree was affirmed in Pittsburg & West End Passenger Ry. Co. v. Point Bridge Co., 165 Pa. 37; and the defendant company paid the compensation stipulated therein until June 1, 1896. At that time the city acquired control of the stock of the bridge company and freed the bridge to the general public; whereupon the railway company declined to make further payments. On January 20, 1898, this suit was
The defendant now contends that a court of equity had no jurisdiction to enter the decree sued upon. It is too late to raise that question. We said in Pittsburg & West End Ry. Co. v. Point Bridge Co., 165 Pa. 37: “We have not overlooked the contention which denies to a court of Equity, jurisdiction of the matter complained of, but we cannot assent to it. On the contrary we think that the Railway Company applied to the proper tribunal for the relief sought.”
The appellant also questions the appropriateness of the present action at law. When these parties were before this court in Pittsburg & West End Ry. Co. v. Point Bridge Co., 223 Pa. 133, we said: “In 1898, upon the correct theory that the decree of 1892 was but a substitute for an agreement between the parties . . . ., an action, which is still pending, was brought by the appellee on the law side of the Court-to recover the amount due from June 1, 1896 to November 12, 1897. That action is an adequate remedy for the recovery of any sum that may be due for the use of the bridge during the five year period.” This was said in reference to the present action, and we see no reason to depart from that view.
It is further contended- that the plaintiff has no right to maintain this action because the city of Pittsburg has acquired all of the stock of the bridge company and has taken over the actual maintenance and control of the structure as a free bridge. This is not the first time that such a point has been before us for consideration. In Monongahela Bridge Co. v. Pittsburg & Birmingham Traction Co., 196 Pa. 25, the action was to recover compensation for the use of a bridge. The defense was that the stock of the bridge company had been purchased by the city of Pittsburg and that it had thereby acquired the “possession, ownership and' control of said .... bridge, and that the same was purchased at public ex
The present case is not to be distinguished from those just reviewed. Although in this case the ordinance authorizing the purchase of the stock of the bridge company. refers to “acquiring the bridge,” yet it expressly authorizes the city to acquire it “by the purchase of the entire stock of the said Point Bridge Company,” and it must be assumed that the legal effect of such a purchase was known to and intended by the city. The provision that “The contract now existing between the said Bridge Company and the. . . . Passenger Railway Company .... shall be duly and legally assigned by the said Bridge Company to the said City . . . ., so that the same shall continue in full force and effect . . . .” was incapable of being carried out for the reason that no such contract existed.' Its only effect was to show that the city had no intention of making the bridge free to the railway company. In view of our decisions there can be no doubt of the right of the plaintiff to maintain this action.
Here the plaintiff sued on the solemn decree of a court of competent jurisdiction which fixed the compensation to be paid by the defendant. No application having been made to modify that decree, the question of how the rate of compensation is to be determined is not in this case. That point as well as the question of the authority to charge a street railway company for the use of a public bridge which is free to others is passed upon in an opinion filed to-day in the case of Beaver County v. Beaver Valley Traction Co., 229 Pa. 565.
We are not impressed with the argument that since the bridge was free to others the charge against the defendant was an unlawful discrimination. The defendant’s use was of a different character from that of the general public, and as it was the only railway company that crossed the structure it cannot be charged that there was any discrimination within a class of users.
The assignments are all overruled and the judgment is affirmed.
Reference
- Full Case Name
- Point Bridge Company v. Pittsburg & West End Railway Company
- Cited By
- 5 cases
- Status
- Published
- Syllabus
- Bridges — Equity — Equity practice — Decree—Street railways — Compensation — Action at law — Cities—Ownership of bridges. 1. Where a disagreement arises concerning the compensation to be paid a bridge company for the future occupancy of a bridge by a street railway company which had changed its motive power to electricity, after having, for a number of years, operated a line of horse cars across the bridge, a bill in equity, filed by the railway company asking that the bridge company be restrained from interfering with the operation of its cars and praying the court to fix the compensation to be paid, is an appropriate proceeding and equity has power to enter a decree therein fixing the compensation at a stated sum for a term of years thereafter with a provision for modification of the decree for proper cause on application of either party. 2. Where in such case the city in which the bridge is located acquires control of the stock of the bridge company and opens the bridge to the general public and, thereupon the railway company declines to make further payments, the bridge company is entitled to maintain an action at law against the railway to recover the amount due under the terms fixed in the decree. Bridges — Purchase of stock by cities — Compensation for use — Street railways. 3. The purchase of the entire stock of a bridge company by the city in which the bridge is located does not dissolve the corporation or vest in the city the title to the property of the bridge company or prevent the bridge company from collecting compensation for the use of the bridge from a trolley company under arrangements theretofore existing, although the bridge is made free to other travel.