Pittsburgh's Petition
Pittsburgh's Petition
Opinion of the Court
Opinion by
This was a proceeding instituted on the petition of certain property owners in the City of Pittsburgh claiming to recover costs and expenses incurred in connection with an earlier proceeding on the part of the City of Pittsburgh begun in January, 1911, looking to the opening and the extension of Hamilton avenue. The proceeding had been so far conducted that a report of viewers assessing the benefits and damages arising from the opening and extension of the avenue had been filed. After the filing of the report the city by ordinance repealed the extending and opening ordinance, under the authority of the Act of Assembly of May 16, 1891, P. L. 75, thereby abandoning the proposed improvement and terminating the proceeding. The petition filed in the case asked for the appointment of a commissioner or auditor “to hear all parties claiming costs and expenses by reason of said proceed-, ing,” who “after taking such testimony under oath, shall make a statement to this court of his findings, both as to fact and as to law, and his opinion upon the same.” Pursuant to this petition the court appointed an auditor for this purpose, and subsequently, on the petition of this appellant, amended the order of the appointment by enlarging the duties of the auditor and directing that he was to hear as well “all parties claiming any actual
“The parties, by agreement filed, may in any civil case, dispense with trial by jury, and submit the decision of such case to the court having jurisdiction thereof, and such court shall hear and determine the same, and the judgment thereon shall be subject to writ of error as in other cases.”
. There, was no formal agreement for such submission and waiver filed in this case; but to allow a party at whose instance a proceeding has been appointed,. and .who has taken advantage of it by pursuing it, to after-
The appellant is the owner of a lot of ground in the City of Pittsburgh one-fourth of which in area would have been appropriated and taken by the city had the proceedings for the assessment of damages in connection with the opening of Hamilton avenue not been abandoned, and the ordinance providing for the opening not been repealed. Section 7, of the Act of May 16,1891, P. L. 75, provides:
“In case any such municipal corporation shall repeal any ordinance passed, or discontinue any proceeding taken, providing for any of the improvements mentioned in the preceding section prior to the entry upon, taking, appropriation or injury to any property or materials, and within thirty days after the filing of the report of viewers assessing damages and benefits, the said municipality shall not thereafter be liable to pay any damages which have been, or might have been assessed, but all costs upon any proceeding had thereon shall be paid by said municipal corporation together with any actual damage, loss or injury, sustained by reason of such proceedings.”
. The claim submitted by the appellant embraced these
Another claim made by the appellant was for compensation for an alleged loss or injury sustained under the following circumstances. In January, 1912, one Harry Davis, , a proprietor of several theaters in .the City;
“No lease was entered into by the City Improvement Company with Mr. Davis and neither of the parties was bound in the slightest manner by what took place between them, consequently there was no rent to lose because no one had contracted to pay rent; no lease was lost for there was no lease; no tenant was driven out or evicted for there was no tenant. If the City Improvement Company lost anything, it was the chance or opportunity to make a lease or to make a good bargain.”
The appellant’s claim is thus reduced by the auditor into one for speculative and contingent damages. This conclusion does no injustice to appellant, and correctly states the case as made out by appellant’s own showing. It is unnecessary to discuss the question of what are and what are not speculative damages, since for another quite sufficient reason the claim was properly defeated. Appellant is entitled to be indemnified for any actual damage, loss or injury it has sustained in consequence of the proceeding taken by the city. These words, “damage,” “loss,” “injury,” are used interchangeably, not simply in this particular statute, but generally; within legislative meaning and judicial interpretation they import the same thing. Our attention has not been called to a case where they have been distinguished in meaning. As used in this statute they refer exclusively to injury
“A statute is not presumed to make any change (in the common law) beyond what is expressed in its provisions, or fairly implied in them, in order to give them full operation, — they are to be interpreted in the light of the common law, with references to the principles of the common law.”
Endlich on Interpretation, etc., Sec. 127.
In what we have said we have sufficiently discussed the several assignments of error. Our construction of the act of assembly necessarily excludes the appellant’s claim from its provision, and the assignments of error ar-e therefore overruled and the judgment is affirmed.
Reference
- Cited By
- 31 cases
- Status
- Published
- Syllabus
- Constitutional law — Constitution of Pennsylvania> Art. V, Sec. 27 — Trial without a jury — Written agreement. 1. Where a party to litigation has filed a written petition, praying that he be allowed to unite in a proceeding before an auditor, appointed to ascertain certain damages alleged to have been sustained by him, he cannot afterwards repudiate the conclusion reached by the auditor and the court, on the ground that there had been no agreement filed to dispense with a jury trial within the meaning of Article Y, Section 27 of the Constitution. The purpose of requiring the filing of a written agreement is that the actual consent of the parties to the litigation may be made a matter of record, so that there may be no subsequent denial by either to the disappointment of the other. Where the record shows such consent, no formal agreement is necessary. Municipalities — Streets—Proceedings to open — Discontinuance of proceedings — Act of May 16,1891, P. L. 75, Sec. 7. 2. Under the Act of Hay 16, 1891, P. L. 75, Section 7, which provides that where proceedings for opening a city street have been discontinued “all costs upon any proceeding had thereon shall be paid by said municipal corporation, together with actual damage, .loss or injury sustained by reason of such proceedings,” the witness fees recoverable are such as may be legally taxed in an ordinary legal action, and the “damage, loss or injury,” recoverable are such as are occasioned by depreciation of the market value of the property or the deprivation of use during the'continuance of the proceeding; money expended in the- procurement of expert testimony, or damage for the loss of- an advantageous léase which a property owner could have made bad it not been for tbe action of tbe city, is not recoverable. 3. Proceedings were instituted by a city for tbe assessment of damages and benefits arising from the opening and extension of a street; thereafter tbe proceedings were abandoned and an auditor was appointed under tbe Act of May 16, 1891, P. L. 75, to hear all parties claiming costs and expenses and damage, loss or injury sustained by reach of such proceedings; appellant, a property owner, upon bis written petition was allowed to join in the proceedings ; tbe auditor allowed bis claims for counsel fees and legal witness fees and disallowed claims for cost of plans and copy of testimony, and for damage, loss and injury based upon the lost opportunity to make a remunerative lease and for witness fees in excess of tbe statutory amount paid to expert witnesses; the court dismissed exceptions to tbe report of tbe auditor and entered judgment thereon. Upon appeal ffrom the action of tbe court in refusing tbe claims for expert testimony fees and tbe loss of tbe prospective tenant tbe judgment was affirmed.