Hardie v. Bateson
Hardie v. Bateson
Opinion of the Court
Opinion by
The bond on which this suit was brought is dated 15th May, 1913. It recites that William Bateson and Thomas F. Manning, trading and doing business as the Keystone Company of Pittsburgh, as principal, and the Massachusetts Bonding and Insurance Company, as surety, are bound unto Edward Hardie in the sum of $8,450.0(1 conditioned that if the principal — The Keystone Construction Company — shall indemnify the obligee against any loss or damage directly arising by reason of the failure of the principals to faithfully perform its engagements arising under a certain building contract entered
The two assignments next following, fifth and sixth, complain of the allowance of the item, “Carpenters, $813.11” on the ground that the architect did not make out certificates for this work or expenditure, agreeably to the requirements contained in the fifth clause of the
Mechanics’ liens amounting to $4,793.02 were filed against the building by subcontractors and material-men. These liens the plaintiff was required to discharge by payment, and for this he asked reimbursement, and his claim was allowed. A fourth condition in the bond is, “that until the expiration of the time within which liens or notices of liens may be filed, and until the discharge of such liens, if any, the obligee shall at all times preserve and exercise all rights provided for his protection by the laws relating to liens of the state wherein said contract is to be performed.” It is contended that the owner was bound under the terms indicated to file a no-lien contract, which admittedly was not done. The contract on. which the appellant became surety contemplated the filing of liens; at least it contains no provision prohibiting the filing of liens by contractor or subcontractors. The appellant must be held to have had full notice of this when it executed the bond, and the above-recited provision in the bond is to be construed in the light of this fact. Our attention has not been direcited to any right provided by the laws of this State relating to liens, which the appellee neglected to observe -and enforce to the prejudice of the appellant. The assignment relating to this branch of the case is without merit and is accordingly dismissed. So too the last remaining assignment which claims that discharge of the surety resulted from a discontinuance of the action against the two parties designated in the contract as principals, Manning and Bateson. It clearly appears, :and indeed it is admitted, that Manning was not a member of the partnership when the contract was entered into for the construction of the building. The discon
The judgment is affirmed.
Reference
- Cited By
- 2 cases
- Status
- Published
- Syllabus
- O ontract — Suretyship—Building contracts — Bonds — 0 onstruction — Liability of surety — Discontinuance of action against principals. 1. In an action against the surety upon a contractor’s bond, where the contractor had defaulted, and plaintiff, the owner, had finished the work at a cost in excess of the contract price, it was no defense that certain payments for the work had been made by the owner to a party other than the contractor with the contractor’s consent; the surety was not thereby discharged, there being no evidence that it was prejudiced by such payments, especially where it appeared that the liability of the surety was thereby reduced. 2. In such case a provision in the contract that for failure, refusal or neglect of the contractor to supply a sufficiency of properly skilled workmen, or failure to prosecute the work with promptness and diligence, the owner might terminate the employment of the contractor, enter upon the premises and finish the work and that the expenses incurred by the owner in so doing should be audited and certified by the architect, whose certificate thereof “shall be conclusive upon the parties,” did not require that where the contractor defaulted and abandoned the work, the expense of completing it should be audited by the architect. 3. Where in such case, the bond provided that “until the expiration of the time within which liens or notices of liens may be filed, and until the discharge of such liens if any, the obligee shall at all times preserve and exercise all rights provided for his protection by the laws relating to liens of the state wherein said contract is to be performed,” the owner was not required to file a no-lien contract, and was properly allowed reimbursement for payments made in discharging mechanics’ liens filed by subcontractors and materialmen, particularly where it appeared that the contract which the surety company executed contemplated the filing of liens and contained no provision prohibiting the filing of liens by the contractor or subcontractors. 4. In such ease where the action was brought against the principals as partners, and one of the principals died after suit brought, and the other was not a member of the partnership when the contract was made, the discontinuance of the action against the principals did not relieve the surety, and the court properly refused to direct a verdict for defendant.