Hoffman Co. v. Title Guaranty & Surety Co.
Hoffman Co. v. Title Guaranty & Surety Co.
Opinion of the Court
Opinion by
The W. H. Hoffman Company, contractor, brings suit to tbe use of its surety, .the Massachusetts Bonding and
On August 25, 1911, Earle and Sullivan, owners of a lot of ground in New York, entered into a contract with the Hoffman Company by which the latter agreed to erect and complete, on the New York property, on or before December 24, 1911, a moving picture theatre, at a sum not to exceed $63,020 for a compensation of eight per cent, of the maximum cost plus one-third the amount saved on that cost and to furnish’ the owners a bond in the sum of $30,000 conditioned for the faithful performance of the contract. On August 22, 1911, three days before the contract with Earle and Sullivan was signed, but in contemplation of its execution, the Hoffman Company entered into a subcontract with McGavern & Lytle, by which the latter agreed to do the excavating, structural and carpenter work on the building for a consideration therein specified and complete their contract not latér than December 1, 1911. The Hoffman Company procured the Massachusetts Bonding and Insurance Company as surety on its bond to the owners, but before this bond was executed the Massachusetts Company required McGavern & Lytle to furnish a bond with surety to the Hoffman Company for the completion of the work as per their contract. In accordance with this requirement at the time of executing the subcontract with Mc-Gavern & Lytle, the latter gave to the Hoffman Company a bond with the defendant as surety, containingthe conditions above recited, and on which bond the present action is founded.
McGavern & Lytle failed to prosecute the work with proper diligence and finally in November, 1911, because of lack of funds, abandoned the contract. Notice that
The three items of damages claimed in the original statement are sums paid out not by the Hoffman Company, the obligee in the bond, but by Earle and Sullivan, the owners, and by the Hoffman Company’s own surety. No action was instituted on these claims against the Hoffman Company, and, from the evidence as to its financial condition, it does not appear that a judgment against it, if obtained, could be collected. A discussion as to whether these items were a proper measure of damage for the breach of contract by defendant’s principal, is unnecessary. Assuming, however, they were a natural result to be anticipated by the parties as a consequence of the breach of contract, it does not appear the Hoffman Company has suffered “pecuniary loss” in the matter. That company has paid nothing on its own account and while its liability exists for the amounts paid by others in its behalf, defendant has not undertaken to indemnify against liability. Its contract is one of indemnity against actual pecuniary loss and the mere incurring of liability does not give rise to a cause of action. The existing indebtedness of the Hoffman Company may never be paid or enforced by the claimants, or their claims may be comproniised for a considerably less amount than the face of the obligations. In the former case no loss is sustained and in the latter the loss would be measured not by the extent of the obligation but by the amount paid in settlement. In the case of Faulkner v. McHenry, 235 Pa. 298, the distinction between indemnity against liability and indemnity against loss is clearly pointed out by this court and our ruling there is applicable to the present case. It was there held a judgment obtained against a mortgagor for a deficiency in the proceeds of foreclosure proceedings on land conveyed under and subject to the mortgage, can not be made the basis of recovery against the grantee of the land on his implied covenant for in
The amended statement claims $5,041.60 alleged loss in commissions, sustained by the Hoffman Company by reason of failure of defendant’s principal to carry out its contract which resulted in preventing the Hoffman Company from completing its work. The obstacle to this claim is the absence of evidence tending to show to what extent the Hoffman Company would have realized profits had the building been fully completed under its contract. That company never completed the work it contracted to do, but, on the contrary, abandoned it entirely necessitating a new contract between the owners and third persons. True, it claims the making of the new contract was due to the default of McGavern & Lytle; assuming this to be correct and that the loss of profits would be the proper measure of damage, what evidence have we from which the amount of such profits may be ascertained. As in other matters, loss of profits must be shown with sufficient definiteness and certainty to warrant the jury in estimating their extent and in absence of such proof as in this case, they will be rejected: Wilson y. Wernwag, 217 Pa. 82. The contract between the Hoff
The amended statement of claim avers the loss of the $5,041.60 by reason of defendant’s default, but at the same time avers the additional cost to the owner of finishing the work was $5,730. The proportion of this cost due to the subcontractor’s default and the amount due to other causes, do not appear. The offer of evidence on this point is also devoid of anything tending to show the amount, if any, of the net profits the work would have realized to plaintiff. Had he completed the contract instead of abandoning it altogether, his loss would be readily ascertainable. In view of the course adopted it, would seem he voluntarily relinquished the only practical method of determining the amount of loss.
The "judgment is affirmed.
Dissenting Opinion
Dissenting Opinion
It seems to me, to deny the plaintiffs a right of recovery on the ground that, under the circumstances at bar, the Hoffman Company incurred no loss, is not only wrong in
Faulkner v. McHenry, 235 Pa. 298, is not in any sense analogous to the present case. There a grantor of real estate created a bond and mortgage, and the grantee contracted to indemnify him against loss by reason thereof; a judgment was entered against the grantor for part of the mortgage debt; whereupon he instituted suit against the grantee on the contract of indemnity. We held that the grantor had no right of recovery until the judgment was paid, on the ground that, where the covenant for in-' demnity is against loss, there can be no recovery until an actual loss occurs, saying, “When the contract is strictly one of indemnity the indemnitee cannot recover until he has suffered actual loss or damage; the mere incurring of liability gives him no such right.” The case in question was properly decided, and the governing principle correctly stated; but, as before said, it is not analogous to the one at bar.
In Faulkner v. McHenry, if there had been a surety for the grantor, to the holder of the mortgage, and such surety had paid the judgment on his principal’s account, then the cases would have been practically analogous; and, on such a state of facts, it could not have been said the grantor had merely incurred a liability, but had suffered no Joss.
In other words, had the circumstances in the Faulkner case been as just suggested, it, like the present case, would have been an instance where the plaintiff had not merely suffered a liability by the entry of a judgment against him, but where, through his surety, he had actually paid the judgment and thereby incurred a loss which entitled him to sue and recover on the indemnity covenant in his favor. Under such circumstances, the mere fact that the surety, instead of the principal, had paid the judgment, and the latter had thereby incurred a liability to the former, would not properly enter into a subsequent case between the grantor and the grantee on
In my opinion, we should view the case at bar as though the surety had handed the $7,500 to the Hoffman Company, and the latter had paid Earle and Sullivan that amount, and thereby incurred a loss. The mere fact that the surety, instead of handing over the money, paid it for the Hoffman Company’s account, does not alter the situation; that is to say, this is not a case where the Hoffman Company has merely incurred a liability to Earle and Sullivan, but where, through its surety to whom it is liable, the Hoffman Company has actually paid its debt to Earle and Sullivan and thereby suffered a loss.
For the reasons stated, I cannot concur in the majority opinion, and, therefore, mark my dissent.
Reference
- Full Case Name
- Hoffman Company, to the use v. Title Guaranty and Surety Company
- Status
- Published
- Syllabus
- Contracts — Building contracts — Bond—Principal and surety— Subcontractors — Default—Liability of surety. 1. Where, in an action on a subcontractor’s bond conditioned to protect the general contractor from “pecuniary loss,” it appeared that the subcontractor defaulted, causing the general contractor to default, and that the owners of the property on which the building was to be erected made payments to materialmen for work performed, thereby acquiring a cause of action against the general contractor, the general contractor could not recover from the surety on the subcontractor’s bond the amount of such payments in the absence of evidence showing that the general contractor had actually suffered pecuniary loss in consequence of the’ liability so incurred. 2. In such ease the general contractor could not recover from the subcontractor’s surety for loss of commissions sustained by the general contractor in consequence of the subcontractor’s failure to carry out the contract, in the absence of evidence tending to show to what extent the general contractor would have realized profit had the building been completed under the contract. 3. In such case where the general contractor assigned his claim to the owner and brought suit to his use, no recovery could be had for the cost of finishing the work in excess of the contract price, in the absence of evidence showing the proportion of the cost which was due to the subcontractor’s default. Moschzisker and Potter, JJ., dissent.