McKenna v. Vernon
McKenna v. Vernon
Opinion of the Court
Opinion by
This was an action to recover a balance alleged to be due on a building contract. By written agreement under date of January 20, 1914, the plaintiff undertook the erection and completion of a moving picture theatre at 1526-28 Cumberland street in the City of Philadelphia, agreeably to certain plans and specifications which accompanied and were made part of the agreement, he to receive therefor, in full compensation, the sum of $7,750.00, to be paid by the owner to the contractor wholly upon certificates of the architect as follows: Eighty per cent, of the work set in place as the work proceeds, the first payment within thirty days after the completion of the work; all payments to be due when certificates of the same shall have been issued by the architect; the building to be completed by April 20, 1914,
The several assignments of error, in one form and another, relate directly or indirectly to this one feature of the case, and are all based on the theory that in the absence of a certificate from the architect of the final completion of the building in accordance with plans and specifications, no right of action existed. Not only is there no express provision to this effect in the contract, but the contract itself shows that no distinction is there made between final payment and the payments on account of the eighty per cent, of work in place. All payments were to be made only on certificate of the architect, and yet with a single exception each of the seven payments made as the work progressed was made without a certificate being asked for. With such constant
Reference
- Cited By
- 3 cases
- Status
- Published
- Syllabus
- Contracts—Building contracts—Architect’s certificates — Condition precedent to payment—Waiver. In an action for a balance alleged to be due under a building contract defendant alleged that improper materials had been used in disregard of the specifications. The contract provided that all payments should be made only on certificate of the architect but it appeared that no certificate had been given and that the provision' of the contract relating thereto had been repeatedly disregarded, that the architect was satisfied with the work, and that deviations from the contract complained of had been made at his direction. It further appeared that the work had been almost daily under the supervision of the owner, who made no complaint with respect thereto. Held, a verdict for the plaintiff was warranted by the evidence and the court properly refused to enter judgment for defendant n. o. v.