Banos v. Sabo
Opinion of the Court
In August 1975, plaintiff and defendant Dougan commenced discussions concerning a project contemplated by plaintiff, the construction of a road and bridge over South Run Creek in Monroe Township, Wyoming County, Pa. The discussions culminated in a contract between plaintiff and defendants involving that project for an agreed consideration of $7,475.
The contract documents included specifications dated August 15, 1975, one of the provisions of which was that all “permits” were to be “furnished” by plaintiff.
Construction by defendants commenced in early September 1975 and were continued by them and their employes until on or about October 14th or 15th, by which time defendants had been paid $4,983.34 of the contract price and had erected the bridge abutments and set beams, but had not, as provided for in the contract documents, removed stone walls, dug a trench, excavated for a septic
A controversy arose at or about mid-October 1975, plaintiff asserting that it concerned a demand by defendants for more money, and defendants contending that the problem concerned plaintiff ’s failure to obtain a permit under the terms of the Water Obstructions Act, infra, from the Department of Environmental Resources.
Plaintiff asserted that he first “applied” for the Department of Environmental Resources permit in July 1975, but defendants’ Exhibit 3, an application, was dated October 22, 1975. A permit appeared to have been issued by the Department under date of November 13, 1975, but its efficacy was predicated on plaintiff’s acceptance of conditions within a time limit, and the evidence was silent as to whether plaintiff accepted or not within the time specified.
Plaintiff finished the job called for by the original contract and brought this suit for costs of repair of allegedly defective construction by defendants and the completion cost. Defendants counterclaimed for amounts which they alleged they had expended on the work to the date that they terminated their efforts in excess of the contract payments previously made to them by plaintiff.
At the trial before this court without a jury, the issue of illegality arose, and upon the conclusion of the receipt of evidence, the parties were accorded the opportunity of briefing this issue, which resulted in the submission of the case to this court on April 27, 1977.
Plaintiff’s counsel argued (1) that defendant has the burden of proof of illegality, (2) that the evidence does not establish illegality, and (3) even
The Water Obstructions Act of June 25, 1913, P.L. 555, sec. 4, 32 P.S. §684 provides:
“It shall be unlawful to construct or begin the construction of any . . . water obstruction . . . except in accordance with the terms, conditions, regulations, and restrictions of such consent or permit ...”
Section 1 of the act includes a bridge within the definition of a water obstruction.
The general rule in Pennsylvania is that a contract is illegal if either the formation or performance is prohibited by statute: Wolk v. Benefit Association of Railway Employees, 172 F. Supp. 62 (W.D. Pa. 1959).
The authority cited by plaintiff, Contractor Industries v. Zerr, supra, provides that if the cause of action appears to arise out of a transgression of a “positive law,” no right can be enforced.
We are of the opinion that although the Water Obstructions Act does not prohibit the construe
Having found the performance of the contract between plaintiff and defendants prohibited by statute in that no permit was obtained by plaintiff prior to commencement of construction, and, further, no evidence having been received which indicated that a valid and effective permit for the construction was ever granted, it follows that the contract may not be enforced.
Hence, both plaintiff’s claim and defendants’ counterclaim must fail. See Holst v. Butler, 379 Pa. 124, 108 A. 2d 740 (1954).
ORDER
And now, June 10, 1977, for the reasons set forth in the opinion of even date in the above-captioned matter, we find, in the claim of Joseph Banos, plaintiff, v. Frank J. Sabo and Michael Dougan,
Each party shall bear his own costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.