This case is submitted, by stipulation of counsel, on the-printed briefs of both parties. The plaintiff, which is a corporation engaged in the manufacture of sugar, brought suit against the defendant, an agriculturist, in the District Court, of ITumacao, to recover eight hundred and ninety dollars and seventy-two cents ($890.72), for the rents of a farm leased by the plaintiff to the defendant, and for two hundred and eighty-nine (289) empty sacks, suitable for sugar, sold to him.
The defendant answered the complaint and set out as a counterclaim that there was a contract of sublease between, the plaintiff and the defendant of a piece of land described;, and that afterwards, by virtue of an agreement made between, the parties, the Resach Bros., made a sublease to him of another hundred acres of the tract of land previously described,, whereby the defendant was to have all the benefits of a contract existing between the said Resach Bros, and the Juncos. Central Co.; and that as substantial conditions of these contracts the defendant, Rodriguez, was obligated to pay, as a rent, to the Juncos Central Co. twelve mills ($0.012), for each hundred pounds (quintal) of cane raised upon the lands so. leased; and the central company, on its part, was obligated to-render a complete and detailed account of the number of quin-tals of cane delivered on each grinding day; which the said, company had not done in proper form, but had done in a defective manner, notwithstanding it had been required so to do-by the defendant, Rodriguez.
Further, that on November 21, 1904, Messrs. Roig, G-ay & Co., a joint stock company, then the sole owners of the Juncos.
‘'Messrs. Roig, Gay & Co., a joint stock company, in behalf of themselves and their assigns, bind themselves to grind in their Juncos Central all the canes raised on at least 50 acres, to be delivered by Mr. Juan Rodríguez Márquez, which canes shall be paid for by them at the rate of five per cent (5%) of their net weight — that is to say, five pounds of sugar for every hundred pounds of canes — which they shall deliver in centrifugal sugar, grade used in the States, polarizing not less than 96 degrees, said central to be given the preference in the purchase of the same at equal prices.”
That the defendant, Juan Rodríguez Márquez, had planted, for the grinding seasons of 1905, 1906 and 1907, more than 50 acres of canes, in compliance with the agreement, and had always cut, to he ground in said central, the amount of canes apportioned to him by the management of the central, hauling them to the place designated, and notwithstanding the fact that said Rodríguez Márquez had fulfilled all the obligations contracted by him in his private contract in regard to the grinding of canes, the Juncos Central Co., or their assignors, Mesrs. Roig, G-ay & Co., for causes beyond the control of the tenant, Juan Rodríguez Márquez, and owing to circumstances solely imputable to lack of foresight or to the negligence of Messrs. Roig, Gay & Co., stopped the said Rodríguez Már-quez from cutting the canes on September 20, 1906, the grinding season having begun in a regular manner in the previous month of August — that is to say, he was stopped at an improper time — preventing the said Rodríguez Márquez from grinding 23 acres of seed canes which were not cut, thereby causing said tenant a real loss of two thousand two hundred and ten dollars and fifty cents ($2,210.50), due not only to the shrinkage in the output of the said 23 acres of canes, but also on account of the damages done to the cane stumps, and from the increased expenditure required in the cultivation of said canes.
That the total of the damages suffered by Juan Rodriguez Márquez,' leaving aside the moral damages and exemplary damages which are incalculable, amount to two thousand seven hundred and ten dollars and fifty cents ($2,710.50), which sum the Juncos Central Co., the assignee of Messrs. Roig, Gay & Co., refuses to pay, although payment ha.s been required of the same.
And based on these allegations in his pleadings, the defendant, Rodríguez Márquez, made the three following prayers to the court:
(a) That the Juncos Central Co. should render to said Juan Rodríguez Márquez, within a reasonable time, a faithful and correct account of the number of quintals of canes ground, day by day, in the factory of said corporation, and coming exclusively from the lands subleased to said Rodríguez Már-quez.
(b) That the Juncos Central Co. be sentenced to pay to Juan Rodríguez Márquez, as damages, the amount claimed of two thousand seven hundred and ten dollars and fifty cents ($2,710.50); and
(c) That the costs herein be adjudged against said corporation.
Thus it may be summarized: The defendant claims in his answer, in the first place, that the plaintiff and defendant had a rental contract by which the latter was to pay to the former as rents at the rate of 12 mills per quintal for all the cane produced; and in the second place, that there existed between the parties a contract for grinding cane, with which the plaintiff had not complied, thereby causing actual dam
The trial court, on the trial, rendered the following judgment, to wit:
‘ ‘ On the 21st and 22d days of December, 1908, the days previously set, the hearing of this action took place in which A. Aponte Jr., and Juan Yias appeared as counsel for plaintiff and defendant, respectively, and both parties announcing themselves to be ready for trial, the court, after reading the writings of the parties, the evidence introduced and argument of counsel, reserved its decision. To-day, the 30th of March, 1909, the court is of the opinion that the law and the facts are in favor of-the plaintiff, the Juncos, Central Co., and, therefore, decrees that the -latter recover from the defendant, Juan Rodriguez Márquez, the sum of eight hundred and forty-seven dollars and fifty-one cents, as claimed in the amended complaint, with costs assessed at-against the defendant, and that an order of attachment be issued on his estate for the execution of this judgment; and in regard to the second cross complaint, the court is of the opinion that the law and the facts are in favor of the defendant, Juan Rodriguez Márquez, and, therefore, decrees that the latter recover from the plaintiff, the Juncos Central Co., the sum of two thousand seven hundred and ten dollars and fifty cents, and that an order, of execution be issued on the estate of said plaintiff corporation for the execution of this judgment. Given under my signature to-day the thirtieth day of March nineteen hundred and eight.”
From that part of the judgment, which awards to the plaintiff $847.51 against the defendant, no appeal is taken, and it is not in controversy here. It is only with the second part of the judgment, awarding to the defendant, $2,710.50, that we have to deal. From this the plaintiff takes this appeal and it is now under our consideration.
As grounds of appeal the appellant sets out -seven alleged errors said to have been incurred on the part of the trial court, and enumerated as follows:
1. The District Court of Humacao should not have considered as a cross complaint (contra-demanda) what the defendant himself called a counterclaim (reconvención), which writ
2. The District Conrt of Humacao onght not to have eliminated the writing of the plaintiff central denying the answer of the defendant.
3. Even granting that the elimination of the answer to the alleged cross complaint was proper, the conrt shonld not have refnsed to the plaintiff central the filing of the same by-permission of the conrt, since the petition was made in proper manner, to wit, by a written application, affidavit of merits, and copy of the proposed or intended answer, besides the reasons, excuses or inadvertencies which were alleged, which showed that their claims were well founded.
4. It is alleged that the conrt below'onght never to have decided that it was not necessary to previously enter the default of the defendant in order to render a judgment by default, a thing which it did on the consideration of the cross complaint in so far as the central was concerned.
5. The District Conrt of Hnmacao shonld not have included a judgment, sought to be taken by default, in the final judgment on the merits of the action.
6. The court below could not enter, and ought not to have-entered, a judgment against the plaintiff on the merits of -the cross complaint because it did not set forth a cause of action.
7. Lastly, it is firmly believed that the District Court of Humacao had no jurisdiction to enter that part of the judg-men on the cross complaint in favor of the defendant, adjudging the plaintiff central to make the payment of two thousand seven hundred and ten dollars and fifty cents ($2,710.50).
Let us take up these supposed errors in the order presented by the appellant in his assignment.
As to the first proposition: It does not matter much what the pleader calls his pleading in the heading thereof; we-must determine its classification by its contents and give it effect accordingly. (McDougal v. Hulet, 132 Cal., 154; Hecker v. Dalton, 75 Cal., 156; Gregory v. Bovier, 77 Cal., 124.)
A countercomplaint is thus defined:
“A claim presented by a defendant in opposition to, or deduction from, the claim of the plaintiff. A series of set-off or recoupment introduced by the Codes of Civil Procedure in several of the States, of a broad and liberal character. A counterclaim must be one ‘existing in favor of a defendant and against a plaintiff, between whom a several judgment might be had in the action: (1) A cause of action arising out of. the contract or transaction set forth in the complaint as the foundation of the plaintiff’s claim, or connected with the subject of action; (2) In an action arising on contract, any other cause of action arising also on contract and existing at the commencement of the action.’ ” (Code Proc. N. Y., section 150.)
“The term ‘counterclaim,’ of itself, imports a claim opposed to, or which qualifies, or at' least in some degree affects the plaintiff’s cause of action.” (35 Wis., 626.)
‘.‘A counterclaim is an opposition claim, or demand of something due; a demand of something which of right belongs to the defendant, in opposition to the right of the plaintiff.” (8 How. Pr., 122.)
“A counter claim is that which might have arisen out of, or could have had some connection with, the original transaction, in view of the parties, and which, at the time the contract was made, they could ■have intended, might, in some event, give one party a claim against the- other for compliance or noncompliance with its provisions.” (7 Ind., 523, 524; Black’s Law Dictionary, p. 284.)
Reconvention is thus defined:
“In the civil law. An action by a defendant against a plaintiff in a former action; a cross bill or litigation. The term is used in practice in the States of Louisiana and Texas, derived from the' recon-ventio of the civil law. (Reconvention is not identical -with set-off, but more extensive.”. (See 6 Tex., 414; 5 Tex., 501, 504; Black’s Law Dictionary, p. 1003.)
Then for the purpose of this appeal we must pass over the first assignment of error as immaterial.
‘ ‘ The invariable practice has been that, notwithstanding the lapse of time limited by the rules of court, pleas may be filed and should be received at any time until default taken. And this practice, which is plainly in no way inconsistent with the purposes of justice, we regard so well established that citation of authorities in support of it may be regarded as wholly unnecessary. But reference may be had to 1 Tidd’s Practice, 566; King v. Hicks, 32 Md., 460; Crabtree v.*295 Green, 36 Ill., 279; Bowers v. Dickerson, 18 Cal., 420; Dole v. Young, 11 Johns. (N. Y.), 90; Boyd v. Canal Co., 17 Md., 195.” (Banville v. Sullivan, 11 Ct. App., D. C., 31.)
Cases apparently at variance with this doctrine may he found in a note to 31 Cyc., 597; but the correct rule appears to us to be stated by the Court of Appeals of the District of Columbia in the Banville-Sullivan case. It is certainly rational and merits our approbation. Then the trial court should not have stricken out the answer made by the plaintiff to the cross complaint of the defendant.
In regard to the third assignment of error, it seems to be stated very broadly. G-ranting that the answer made by the plaintiff to the cross complaint had been properly stricken out, then the reinstatement of it became a matter within the sound' discretion of the court. It is true as stated by the respondent, that the discretion of the trial court is generally held, on appeal, to have been well exercised, and the authorities cited on this point have great force. (Wolff & Co. v. Canadian Pacific, 89 Cal., 332; Buel v. Emerich, 85 Cal., 116; Dougherty v. Nevada Bank, 68 Cal., 275; Bailey v. Taaffe, 29 Cal., 424.)
The real reason why the reinstatement should have been made was because the answer should not have been stricken out in the first place. Though we may not have been willing to exercise judicial discretion as the trial court did, in this particular, we hestitate to find an abuse of that discretion, without reference to the attending circumstances. Besides, the exception made by the plaintiff that the counterclaim of the defendant did not set forth facts sufficient to constitute a cause of action could he presented at any time, according to section 109 of the Code of Civil Procedure. (Abbe v. Marr, 14 Cal., 212.) • Then, on the whole, we must consider the ruling of the trial court on this point as erronéous.
In regard to the fourth assignment of error presented,, we must certainly consider that it is well taken. It was clearly
So the fifth assignment announces a correct proposition when it' says that the trial court should not have included a default judgment against the plaintiff in the final judgment on the merits. Judicial proceedings should be conducted in a regular and orderly manner and the Code of Procedure carefully followed and fulfilled.
In considering the sixth assignment of error, we must examine the allegation of the cross complaint to ascertain the basis of the demand for the $2,710.-50. It arises out of a contract alleged to have been made with Roig, G-ay & Co., and not with the plaintiff in this suit. To our mind no sufficient allegation is set forth to connect the Juncos Central Co. with this claim; nor does any obligation appear on the part of the said corporation to pay the same. The mere fact that Roig and Gay are connected with the said central company, or even that they organized the same and became officers thereof, does not render the newly organized company liable for their debts. This seems to us a fundamental error requiring a reversal of the judgment.
In regard to the seventh and last assignment of error, we must say that we do not see any want of jurisdiction in the trial court to render such a judgment, had the question been properly presented by the pleadings and maintained by the proofs. The court certainly had jurisdiction of the parties and the subject matter of the litigation. If the appellant, by asserting a want of jurisdiction in the court to render a
For the errors indicated the judgment should be reversed and the cause remanded to the District Court of Humacao, to be conducted to a conclusion in accordance with this opinion.
Reversed.