As a result of the overturning of Félix Toledo’s truck, driven by Rivera Echevarria, when one of its wheels fell into a deep hole in the road in front of a house which belongs to appellant, said truck collided against said house causing it damages. The hole in question was formed when the road caved in after an excavation was made, for the purpose of placing a pipeline, and filled in by the Puerto Rico Aqueduct and Sewer Authority. The court concluded that the accident was due to the negligence of said Authority in failing to fill and properly cover the excavation in the road.
The controversy centers on the extent of the damages and the cost to repair them.
Appellant points out that the trial court erred in fixing an insufficient and inadequate compensation, out of proportion with the damages caused and that it abused its discretion in refusing to accept his expert evidence.
The evidence showed that the damages consisted in the destruction of a fence, deep cracks “in the front and central wall,” cracks in the floor, and displacement of the tiles; that the repairs would include plastering and painting.
The estimate of appellees’ expert (1) does not contain the necessary details for the repairs and (2) he is necessarily mistaken in partly basing the repairs on covering the cracks in the walls after admitting that the resistance of the walls was affected by the cracks and that covering the cracks would not restore the resistance the walls had before the accident. So that the court was not justified in accepting only appellees’ estimate.
In view of the foregoing it is proper that we determine the cost of repairing the damages in this case on the basis of such evidence of the parties that best conforms to reality and the nature of the damages suffered and in relation to which there is a reasonable degree of conformity, for the purpose of restoring the property to its condition before the accident. Ortiz Rivera v. Aetna Life Insurance Company, 89 P.R.R. 628 (1963); Kathan v. Bellows Falls Village Corporation, 223 A.2d 470 (Vt. 1966); Kentucky Stone Company v. Gaddie, 396 S.W.2d 337 (Ct. App. Ky. 1965); Kirst v. Clarkson Construction Company, 395 S.W.2d 487 (Ct. App. Mo. 1965); Southern Railway Company v. Wooten, 137 S.E.2d 696 (Ct. App. Ga. 1964). The different items of
said costs so determined are:
1) Floor repairing and installation of tiles $546
2) Plastering repairs 150
3) Fence repairs 75
4) Insurance and permits 16
5) Painting 150
TOTAL $937
To this, $64 should be added, which, according to the trial court, represents income for rent not received. This item is justified under the rule of compensatory damages
In view of the foregoing, the judgment rendered by the trial court in this case is modified, for the purpose of increasing the amount for the cost of repairs to $1,001 and as thus modified it is affirmed.