Moreau v. Department of Environmental Management, 91-6342 (1994)
Opinion of the Court
TGP filed for a hearing on the denial of their original application, but that hearing never took place because, as a result of settlement negotiations during which a revised plan was submitted by TGP, DEM approved TGP's application. Tr. at 36. On August 27, 1991, a permit for wetland alterations was issued based on the revised plans. Id. The revised plans never went through the public notice procedure because they did not show any new wetland alterations. Tr. at 33. The modified plans showed the pipeline ending at Natick Road in Cranston. Tr. at 30. This termination point was different from the original plans in which the pipeline proceeded on from Natick Road through Plaintiff Moreau's property. Id. Providence Gas Company would receive its gas deliveries from a meter station at the revised end of the pipeline at Natick Road. After the plans were revised, the municipalities also withdrew their disapprovals. The issuance of this permit was appealed by Plaintiff.
Construction of the pipeline began in September, 1991 in accordance with the permit and its specifications as to how to treat the affected wetlands depicted on the revised plans submitted in support of TGP's application. Tr. at 107. Some time after construction of the pipeline began, TGP noticed that a wetland ("Wetland 70") not depicted on the revised plans was being altered by the construction. It is disputed exactly when this wetland was discovered by TGP and when DEM was made aware of its existence. TGP claims that it discovered Wetland 70 on December 17, 1991 and told a DEM inspector about it the next day. Tr. at 262; TGP Br. at 6. TGP included a description of its treatment of Wetland 70 in the progress reports submitted to DEM. Tr. at 264. DEM admits receiving, sometime in December, 1991, complaints about illegal wetland alterations, but contends that no formal on site inspections took place until June 9 and June 23, 1992 when DEM officially realized the potential that a wetland not covered by the issued permit was being altered. Tr. at 45, 50. As a result of those inspections, DEM's suspicions were confirmed.
Because a wetland that had not gone through the public notice and comment procedures required of R.I.G.L. §
The Hearing Officer found that Wetland 70 was not included in the application materials submitted in support of TGP's permit, but that there was insufficient evidence "to prove the allegations set forth in the NSPO by a preponderance of the evidence." Hrg. Off. at 40. The Hearing Officer also found that DEM had jurisdiction over the wetland at issue. Id. Nevertheless, the Hearing Officer recommended to the director that the NSPO not stand. The basis for the finding that the NSPO should be revoked was not only that the allegations contained in the NSPO were not proven to the satisfaction of the Hearing Officer, but also that the NSPO was not issued until after TGP had essentially completed the pipeline construction. Id. Thus, "the submission of new plans (or other documentation) at this time for the specific area of concern, would serve no useful purpose." Hrg. Off. at 39-40.
On August 11, 1993, the director of the Department of Environmental Management rejected two of the recommendations of the Hearing Officer. Final Decision at 1. The director found that DEM did prove by a preponderance of the evidence that TGP's application materials were false and erroneous and that, consequently, DEM was entitled to the relief requested in the NSPO. Id. However, despite finding sufficient evidence to support the NSPO, the director accepted the Hearing Officer's recommendation to deny the relief requested in the NSPO. Id. The director found that TGP had "demonstrated good cause why the Notice of Suspension of the Permit and Order should not stand in that the construction of the pipeline has been completed under the permit and the requested remedies would serve no useful purpose." Id. The director's rejection of the NSPO was appealed by Plaintiff.
Plaintiff's timely appeal of the original granting of the permit to TGP is No. 91-6342. Consolidated with that appeal is Plaintiff's timely appeal of the denial of the NSPO, which is No. 93-4996. Both appeals are currently before this Court.
(g) The court shall not substitute its judgment for that of the agency as to the weight of the evidence on questions of fact. The court may affirm the decision of the agency or remand the case for further proceedings, or it may reverse or modify the decision if substantial rights of the appellant have been prejudiced because the administrative findings, interferences, conclusions, or decisions are:
(1) In violation of constitutional or statutory provisions;
(2) In excess of the statutory authority of the agency;
(3) Made upon unlawful procedure;
(4) Affected by other error or law;
(5) Clearly erroneous in view of the reliable probative, and substantial evidence on the whole record; or
(6) Arbitrary or capricious or characterized by abuse of discretion or clearly unwarranted exercise of discretion.
Accordingly, when reviewing an agency decision, the court must not substitute its judgment for that of the agency with respect to the credibility of witnesses or the weight of the evidence.Costa v. Registry of Motor Vehicles,
Plaintiff's amended complaint makes several allegations that TGP's construction will harm Plaintiff's property. Plaintiff claims that blasting might impair a historic farmhouse on her property; noise, dirt and blocked access will cause injury to Plaintiff; and harm might result to a nearby brook. Since December 10, 1991 when the amended complaint setting forth these allegations was filed, TGP has completed construction of the pipeline. As the potential harm to the nearby brook, the harm to the historic farmhouse and the inconvenience of the noise, dirt and blocked access did not materialize, these issues have been rendered moot by the lateness of this appeal. See Town ofScituate v. Scituate Teachers Association,
Plaintiff's amended complaint further alleges that TGP's project requires alteration of a wetland which crosses Plaintiff's property and which is not covered by TGP's permit. Based on this allegation and the allegations dismissed above, Plaintiff contends that the permit should be revoked. At this time, TGP's permit has terminated by its own terms.1
Furthermore, all of the alterations the permit purports to allow, plus the alteration of Wetland 70, have been completed. Tr. at 108. Therefore, revoking the permit now will achieve nothing and is, in fact, impossible since no permit even exists any longer. Thus, consideration of this issue is also rendered moot. Usually, a "court will not review a case if its mandate would be of no assistance to the party seeking review — especially when that which is sought has already been accomplished." Phelps v. BayStreet Realty Corp.,
The pipeline depicted on TGP's initial application for the permit did not interfere with Wetland 70, so that wetland was not included at all in that original application. Tr. at 37. When the pipeline route was changed, after DEM's denial of TGP's first application, and Wetland 70 became affected, apparently neither DEM nor TGP was aware of the wetland's existence. Consequently, it was not included in the revised application materials either. DEM approved TGP's application based on the revised plans because the revisions did not appear to alter any wetlands not already depicted in the original application, which had already gone through the public notice and comment requirements under R.I.G.L. §
Although DEM followed the proper procedure with respect to the permit, TGP did not, and that has resulted in inaccuracies in the plans submitted in support of TGP's permit application. Such inaccuracies formed the basis for DEM's issuance of a NSPO on July 15, 1992 pursuant to the then applicable Rule 10.01 of the Rules and Regulations Governing the Enforcement of the Freshwater Wetlands Act. This NSPO is the subject of appeal No. 93-4996.
It is uncontroverted in the record that the permit did not include permission to alter Wetland 70, which TGP did, in fact, alter. Since "this evidence was not discredited either by other positive testimony or by circumstantial evidence. . . [it] is ordinarily conclusive. . . ." State v. A. Capuano Bros., Inc.,
The first remedy ordered by the NSPO was for TGP to "cease and desist" from further work under the 1991 permit. Such a request is rendered moot at this time not only because all work is completed on the pipeline project, but also because the permit has now terminated on its own terms so no more work could be done under that permit even if it had included Wetland 70.
The NSPO further ordered that the permit be suspended. Again, this order is moot since the permit is no longer valid. Consequently, there is no permit to suspend.
Lastly, the NSPO ordered TGP to comply with the permit and notice requirements of R.I.G.L. §
TGP has contended that when it discovered the wetland shortly after the permit was granted, it did not think the wetland qualified for protection under the applicable statutory scheme. Tr. at 315. As a result of this inaccurate belief and TGP's alleged reliance on comments made by employees, and not the director of DEM, TGP made no effort to apply for a permit to alter this wetland. Tr. at 316. However, §
DEM could have ordered restoration as a part of the NSPO pursuant to R.I.G.L. §
Unfortunately, the Hearing Officer and the director were never given an opportunity to explore fully whether restoration activities are necessary in this case. By a motion in limine which the Hearing Officer granted, DEM prohibited the introduction of testimony regarding "(1) the value of the freshwater wetland, (2) the impact of alterations on the wetland, and (3) any mitigating efforts allegedly taken with respect to the alterations." Tr. at 297-98. Such evidence was held irrelevant to the issue of whether the plans contained false or erroneous information, the subject of the NSPO hearing. Not only did the Hearing Officer agree that the presentation of evidence should be specifically limited to the validity of the NSPO, but he also ruled that restoration and mitigation evidence was not properly before him at the NSPO hearing because the Administrative Adjudication Division is not a court of equity. Tr. at 285. However, unlike the Hearing Officer in the Administrative Adjudication Division, the director of environmental management possesses the power to order restoration as a remedy, but because such relevant testimony was prohibited at the hearing, DEM was never fully informed on the restoration issue. As a result, the director's ability to order restoration relief was restricted.
A restoration order under §
As to appeal No. 91-6342, this Court makes no specific findings because that appeal has been rendered moot by subsequent events. Therefore, appeal No. 91-6342 is denied. However, this Court does hold, in accordance with the admissions of the parties, that the permit issued to TGP for construction of the pipeline did not include permission to alter Wetland 70. Despite this incompleteness, the procedures followed by DEM were proper and the resulting permit was valid. When Wetland 70 was officially made known to DEM, DEM took the proper measures to rectify the situation by issuing a NSPO.
As to appeal No. 93-4996, this Court finds that legally competent evidence supports the Final Decision of the director of environmental management. Sufficient evidence exists to find that the plans supporting TGP's wetland permit did not accurately include all of the wetlands which were eventually altered by the pipeline construction. Furthermore, the remedies requested by the NSPO would, at this late date, serve no useful purpose. Therefore, the Final Decision is affirmed. This illegal alteration violated R.I.G.L. §
Counsel should submit the appropriate judgment for entry.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.