Carvalho v. Lincoln, 00-5899 (r.I.super. 2005)
Opinion of the Court
"Sale is subject to all approvals from the State and Town of Lincoln for a 21 lot sub-division, said approvals to be paid for by seller). All state and local permits to be paid for by buyer. Buyer shall close within ten (10) days after all final approvals have been given."
Section 20 of the Agreement also contains a default provision stating that if either party defaults, the other is entitled to the deposit, specific performance, and any other available legal remedies.
At the time the Agreement was executed, Carvalho was involved in litigation with the Town of Lincoln in Providence County Superior Court (C.A. No. 00-5899) regarding a subdivision application that he had previously filed with respect to the Property. The Court had to determine which year's regulations were to be applied by the town Planning Board in assessing Carvalho's proposal. According to Carvalho, sometime in September of 2001, while his suit was pending, he met with Houghton, who told him that the subdivision approval process would take three to six months.
On December 27, 2001, the Court ruled that Carvalho's subdivision proposal was vested under the 1986 regulations of the Town of Lincoln and remanded the matter to the town's Planning Board. Shortly thereafter, on January 15, 2002, Houghton met with the Lincoln Town Solicitor and Town Administrator regarding the proposed subdivision of the Property. The town representatives expressed concerns with respect to the proposed sewage system and informed Houghton that it had to be altered.
Thereafter, Houghton assigned all of his rights and duties under the Agreement to LPD. Carvalho's then-attorney authorized LPD to "proceed with the development of the Subject Property for a residential subdivision in accordance with the plans submitted." LPD met with the Planning Board during the summer of 2002 and attempted to test the suitability of the land for installing individual septic disposal systems in December of that year, but because the ground was frozen the testing had to be postponed until the spring of 2003. Some time in late October or early November of 2003, the Department of Environmental Management ("DEM") application was prepared and ready for Carvalho to sign Although it is unclear exactly when Carvalho was presented with the DEM application for his signature, it is undisputed that he had received the document some time in the fall of 2003.
In an October 29, 2003 letter, Carvalho's attorney informed LPD's counsel that Carvalho considered LPD in breach of the Agreement because of its failure to receive approval for the subdivision and failure to proceed with the closing. As a result, Carvalho refused to sign the DEM application to allow LPD to move forward with the approval process. On January 5, 2004, LPD requested the Court to order Carvalho to sign the document. Thereafter, the parties signed a consent agreement, filed with the Court on March 29, 2004, stating that Carvalho agreed "to sign any and all applications, along with all the required plans, exhibits and documents and fees for processing any regulatory permits necessary to obtain approval for a subdivision." That consent agreement also provided that the purchase and sales contract was to remain in "full force and effect, without any waiver of claims or defenses, or ability to raise the same." On June 4, 2004, Carvalho finally signed the DEM application so that LPD could proceed with the approval process.
At a July 28, 2004 meeting, the Lincoln Planning Board voted to approve LPD's preliminary plan to develop a 13 lot subdivision on the Property. The Board also decided to delegate final plan approval to the Town Planner for recording, once all of the necessary state and local permits could be obtained and upon LPD's posting a performance bond to complete all of the required public improvements.
On November 5, 2004, while the permit applications were still pending, LPD filed an amended complaint with the Court seeking specific performance of the Agreement and alleging a breach of contract by Carvalho resulting from his refusal to acknowledge the validity of the Agreement and his obligations therein. Carvalho denied those allegations and, by counterclaim, alleged that LDP breached the Agreement by failing to perform.
Subsequently, LPD filed a motion for partial summary judgment, arguing that the assignment of the Agreement, and the Agreement itself, was valid and enforceable and, as a result, Carvalho was legally obligated to perform under the contract. Associate Justice Michael A. Silverstein issued a bench decision on April 26, 2005, granting LPD's motion. In his decision, he noted that "[t]he facts in this matter thereafter are somewhat twisted, but those twists do not impact the decision that the Court makes because they are not substantive or necessary to this decision." (Tr. at 3-4). Ultimately, he held that "the purchase and sale agreement constituted a valid and binding agreement; that the assignment of the purchase agreement was a valid and binding assignment." (Tr. at 6). Furthermore, in granting LPD's motion, Judge Silverstein stated:
"[T]here is no question but that at all times the parties here have acted, as evidenced by the letter and as evidenced by the signing by Mr. Carvalho of the permits, consistently with the final sentences of Paragraph 23 of the purchase and sales agreement, calling for a close within ten days after all final approvals had been given." Id.
In addition to finding that the Agreement was valid and enforceable, Judge Silverstein's Order provides:
"[T]he decision of the Court to grant LPD's Motion for Summary Judgment on the enforceability of the purchase and sales agreement is without prejudice to the right of Carvalho to contest before this Court the amount and reasonableness of the expenses he may be required to pay LPD pursuant to paragraph 23 of the Agreement in connection with LPD's procurement of all state and local approvals in this matter."
On June 1, 2005, LPD requested a one-year extension of the preliminary plan approval issued by the Planning Board because it had not yet received the DEM wetlands and individual septic disposal systems ("ISDS") suitability determination permits. (The Planning Board later granted the requested extension at its July 27 meeting.)
On June 3, 2005, LPD filed a Status Report with the Court, referencing a February 4, 2005 letter sent by the DEM to Carvalho which stated that the freshwater wetlands application had been reviewed and was found to be incomplete or deficient. In addition, the letter indicated what needed to be revised and/or provided so that the application could continue to be processed. LPD, however, had been unaware of the letter until its engineer received notice of the deficiency by a fax on April 26, 2005. Eventually, on July 26, 2005, the DEM issued the ISDS and Physical Alteration permits necessary to present the final plan for approval to the Town of Lincoln.
Carvalho contends that summary judgment should not be granted because there remain some legal issues to be determined independent of whether the Agreement is valid and enforceable by its terms. Carvalho also claims that a genuine issue of material fact exists as to whether, considering the absence of a "time-is-of-the-essence" clause, LPD performed its duties as set forth in the Agreement within a reasonable time. In addition, Carvalho maintains that partial summary judgment should not issue because the Court must determine whether LPD committed a substantial delay, meriting an award of damages.
Although a party may effectively waive a condition for its benefit by seeking specific performance prior to the condition being met, that does not mean that the party resisting performance is entitled to do so as a result of the failure of the occurrence of a condition provided for the other's benefit. See Blanchard v. Wells,
The issues now before the Court are not identical to those decided by Judge Silverstein in LPD's prior motion for partial summary judgment. Judge Silverstein held that "the purchase and sale agreement constituted a valid and binding agreement [and] that the assignment of the purchase agreement was a valid and binding assignment." Here, the validity of the Agreement and/or the assignment is not in question; rather, the Court must determine whether there are genuine issues of material fact regarding the application of the Agreement. More specifically, the Court must consider Carvalho's breach of contract counterclaim which alleges that LPD breached the Agreement by unreasonably delaying its performance. The issue of whether the valid agreement was subsequently breached has not yet been reached, and this Court is not being presented with the same question in an identical manner as was previously presented to and decided by Judge Silverstein. Therefore, the law-of-the-case doctrine is inapplicable.
Carvalho has failed to meet his burden of presenting an adequate basis to demonstrate that a genuine issue of material fact exists as to whether LPD acted within a reasonable time. Carvalho's half-hearted attempt to submit any such evidence is contained in his affidavit wherein he says (1) that he was initially told by Houghton that the approval process would take three to six months, (2) that he interpreted a statement by Paul Larisa of LPD, "if you think this is a mess you should have seen the one I was in in Massachusetts with my partner," to mean that LPD lost interest in the project, and (3) that LPD failed to obtain any approval for a two-year period because, he believes, it did not have the financial ability to buy the property. These claims amount to nothing more than barren and conclusory allegations that are insufficient to surmount a summary judgment motion. See Small Bus. Loan Fund Corp. v. Loft,
Last year, in Lajayi v. Fafiyebi, the Rhode Island Supreme Court noted that contract provisions that refer to time do not automatically or necessarily transmute that reference to a time-is-of-the-essence mandate.
Here, Carvalho has failed to present any evidence indicating that LPD was not diligent or that it somehow acted in bad faith in seeking approval for the subdivision. In fact, the record more than suggests a contrary conclusion. It was, after all, Carvalho who delayed the approval process by impermissibly refusing to sign documents and by failing to inform LPD of the DEM deficiency letter. The only perceptible delay that could somehow, if at all, be laid at LPD's doorstep occurred when the ground was too frozen to test its suitability for individual septic disposal systems. Any such postponement, however, was not as a result of LPD's actions. It is the view here that Carvalho has failed to set forth any articulable foundation that might expose a genuine issue of material fact to support his empty breach of contract claim. Accordingly, LPD is entitled to the summary judgment it seeks.
Having obtained all of the requisite permits in support of its application, and there being nothing left undone but to present the final plan to the Town for approval and move forward with the construction of the planned subdivision, LPD has clearly demonstrated that it was at all times ready, able, and willing to perform on the contract once that final approval was issued. As a result, LPD is entitled to this Court's order of specific performance of the Agreement and an order directing Carvalho to proceed with the closing. See, Lajahji,
Counsel shall submit an appropriate judgment for entry.