Becker v. Joyal
Opinion of the Court
Several of these stipulations merely relate to the condition of the site during and after construction.2 Other stipulations, however, relate to approvals that Bucci must receive in order to construct the project:
"2. The petitioner will obtain, from the Planning Board, all required approvals including, but not limited to Section 17 of the North Smithfield Zoning Ordinance.
. . . .
5. The final approval of the project is dependant [sic] upon the petitioner receiving approval from both the Rhode Island Department of Environmental Management and the Rhode Island Department of Transportation for applications of plans presented to each department as well as the North Smithfield Planning Board. Any changes in these applications will require the petitioner to return to both the North Smithfield Planning Board and the North Smithfield Zoning Board of Review to review their respective decisions regarding the proposed project in light of the changes.
6. Approved [sic] of this petition is contingent upon the petitioner obtaining water rights from the City of Woonsocket and sewerage rights from the Town of North Smithfield." Id.
Bucci has not yet received all of the required permits for the proposed development. (See Decision of the North Smithfield Zoning Bd. of Review on behalf of Daniel Becker, 173, July 19, 2006 (hereinafter "Becker Decision")).
North Smithfield's Zoning Ordinance (Zoning Ordinance) contains a provision relating to the expiration of special-use permits. Section 9.4 of the ordinance states:
"A special-use permit or a variance from the provisions of this ordinance shall expire eighteen (18) months from the date granted by the Zoning Board of Review unless the applicant exercises the permission granted or receives a building permit to do so and commences construction and diligently prosecutes the construction until completed. No re-application for a special-use permit or variance shall be granted without a hearing."
Because of this ordinance, Bucci's counsel sent a letter to the North Smithfield Building and Zoning Official (Building Official) to clarify the effect of this ordinance on the proposed development. (See Letter of April 4, 2006 from Michael A. Kelly, Esq. to Robert E. Benoit). The Building Official responded that "[i]t is my opinion, that the eighteen-month period, for which the Special-Use Permit was granted should not begin its toll, until all of the Boards [sic] stipulations or conditions have been satisfied." (Letter of April 26, 2006 from Robert E. Benoit to Michael A. Kelly, Esq. (emphasis omitted).)
Plaintiff Daniel Becker appealed the Building Official's determination to the Zoning Board, and it upheld the Building Official's determination. (Becker Decision 173). During the hearing before the Zoning Board, the Building Official stated that the permits from the Rhode Island Department of Environmental Management (RIDEM) and Rhode Island Department of Transportation (RIDOT) had been obtained as of August, 2005, but that the Planning Board approval was still pending. (Bucci Mem. Law Supp. Obj. Pl's Appeal, Exh. F., Transcript of June 27 Hearing 20:10-20 (hereinafter "June 27 Hearing Transcript")). Along with the Valley Alliance for Smart Growth, Inc., a non-profit corporation, Becker filed this appeal in the Superior Court pursuant to §
The Zoning Enabling Act provides for situations where an applicant requires permits from other agencies in addition to the zoning board. Zoning boards have the power to issue
"conditional zoning approvals where a proposed application would otherwise be approved except that one or more state or federal agency approvals which are necessary are pending. A conditional zoning approval shall be revoked in the instance where any necessary state or federal agency approvals are not received within a specified time period." §
45-24-57 (1)(vii).
A zoning board may also attach "special conditions" to the grant of a special permit in order to "promote the intent and purposes of the comprehensive plan and the zoning ordinance of the city or town." Section
The Court finds that the language contained in the November 2004 Decision expressly makes approval of the special permit conditional. Stipulation 2 requires Bucci to obtain "all required approvals" from the Planning Board. (See November 2004 Decision 411, ¶ 2.) Stipulation 6 also makes approval "contingent upon" Bucci obtaining water and sewer rights. Id. ¶ 6. Finally, stipulation 5 states that "final approval of the project is dependant [sic]" upon RIDEM, RIDOT, and the Planning Board approving the petitioner's application in a form unchanged from that which was presented to the Zoning Board. See id. ¶ 5.
Because the approval is a conditional approval, the eighteen month limitation period will not begin to run until all of the following events occur: RIDEM approval, RIDOT approval, Planning Board approval, and the obtaining of water and sewer rights.See id. ¶¶ 2, 5, 6. That date will be the operative date which starts the limitations period under § 9.4 of the Ordinance. Only at this time will the conditional approval ripen into a final approval and allow Bucci to obtain a building permit. (See Becker Decision 173 (noting that the Building Official would not issue a building permit until certain conditions were met).)
If any changes are made to the applications, then the condition of approval in stipulation 5 would not be met and Bucci must "return to both the North Smithfield Planning Board and the North Smithfield Zoning Board of Review to review their respective decisions regarding the proposed project in light of the changes." (See November 2004 Decision 411, ¶ 5.) However, Plaintiffs have made no such allegations to the Board or to this Court that the application has changed.
The Plaintiffs argue to this Court, as they argued to the Zoning Board, (see June 27 Hearing Transcript 12:2-7), that the Building Official's interpretation of § 9.4 could result in a developer taking many years to exercise his rights under a special permit. (Pl's Mem. 5). However, the Zoning Board has the power to specify in its decision a time period after which, if the other permits have not been obtained, the conditional zoning approval will be revoked. See G.L. 1956 §
Of course, not all of the stipulations in the November 2004 Decision are conditions of approval. The Building Official's decision states that the limitation period does not begin until "all of the Boards [sic] stipulations or conditions have been satisfied," but as Plaintiffs point out, this cannot be accurate. (Pl. Mem. 4.) Some of the "stipulations" relate to hours of operation, signage, and building size, and have no meaning until after the project is actually built. (See November 2004 Decision, 411, ¶¶ 1, 7, 8, 9.) These are more accurately labeled "special conditions" under §
Counsel for the prevailing party may present an order and judgment consistent herewith after notice to counsel for the Plaintiff.
"1. The North and South entrance signs will not remain lit after 10:00 p.m. daily. . . . . 7. No building in this project will exceed 45 feet (including any façade) in height. 8. Operating hours will be restricted to Sunday through Saturday 8:00 a.m. to 10:00 p.m. . . . 9. The total area of any sign will not exceed 880 square feet as presented in P-9A" November 2004 Decision 411, ¶¶ 1, 7-9.