Interstate Nav. v. Coastal Res. Mgt.
Opinion of the Court
Before the CRMC held hearings to consider the Applicant's proposal, the Applicant modified the proposal in response to several requirements imposed by the Army Corps of Engineers. Among the changes that took place were limiting the first two slips to boats of no more than twenty-six feet in length and shortening the dock to twenty feet.
On February 9, 2005, CRMC Staff Engineer Danni Goulet ("Mr. Goulet") filed a pre-hearing report with CRMC Executive Director Grover Fugate. (Admin. R. at 2-8.) While Mr. Goulet deferred to the Council to determine many issues, the report did comment on several aspects of the proposal. Mr. Goulet expressed that he did not have any construction or structural concerns with the Applicant's revised proposal. Id. at 2-3. Mr. Goulet's pre-hearing report also addressed the Applicant's variance requests. With respect to the parking and dredging variances, Mr. Goulet deferred to the CRMC to determine if the Applicant met the requisite six criteria for *Page 3 the variances. Id. at 3-4. However, Mr. Goulet had no objections or engineering concerns with the granting of the setback variance. Id. at 4. Mr. Goulet also noted that the proposed marina would be in Type 5 waters and therefore was "in keeping with the goals of maintaining a vibrant mix of port related activities including recreational boating, commercial fishing and ferries." Id. Mr. Goulet's report also expressed that the proposed dredging plan met the Council's standards, as well as industry standards for hydraulic dredging with beach nourishment disposal. Id. at 8.
CRMC Staff Biologist David Reis filed his report with Executive Director Fugate on February 18, 2004. Id. at 9-11. Mr. Reis set forth several recommendations regarding the Applicant's mitigation proposal, which addressed the destruction of eelgrass beds at the site of proposed dredging. Mr. Reis stated that "[c]onsidering the developed nature of the Type 5 water use designation of Old Harbor, [he] did not object to the proposed 8-slip marina, provided, the complete loss of the exiting eelgrass bed is replaced through an appropriate mitigation effort."Id. at 11. Mr. Reis commented that the Applicant's current mitigation proposal was insufficient, and the Council should stipulate that no work be allowed until a mitigation proposal is submitted and approved by the CRMC. Id.
On February 21, 2005, the Rhode Island Department of Environmental Management (DEM) granted Water Quality Certification to the Applicant. Id. at 12-15. The DEM opined that the project was in compliance with the Dredging Regulations and Water Regulations provided that the Applicant complied with several stated conditions, including a new eelgrass mitigation plan. Id.
Appellants Interstate Navigation and Interstate Nav filed petitions to intervene, and the CRMC granted these petitions. Interstate Navigation and Interstate Nav are individual companies that fall under the same Connecticut-based family of corporations. Interstate *Page 4 Navigation operates the traditional and high-speed Block Island ferries from Point Judith to Old Harbor, Block Island. Interstate Nav owns the property immediately adjacent to the proposed marina and is the operator of a seasonal ferry service to New London, Connecticut. In May 2005, both Interstate Navigation and Interstate Nav submitted memoranda to the CRMC, which cited numerous safety concerns and the Applicant's failure to obtain necessary local approvals and variances.
Over the course of seven hearings between March and June 2008, the CRMC received evidence from thirteen witnesses and reviewed two depositions. The CRMC held its final meeting to discuss the proposed project on June 28, 2005. Further details of these hearings will be discussed in the sections that follow.
The CRMC issued its decision on October 28, 2005. The decision included fifty-five findings of fact. The Council approved the application by a vote of seven to one after concluding that the proposed activity did not have a reasonable probability of causing a detrimental impact upon the coastal resources of the State of Rhode Island. The CRMC's October 28, 2005 Assent required compliance with various general stipulations, as well as stipulations specific to this project.
In November 2005, Interstate Navigation and Interstate Nav filed individual appeals pursuant to Rhode Island Gen. Laws 1956 §
(g) The court shall not substitute its judgment for that of the agency as to the weight of the evidence on questions of fact. The court may affirm the decision of the agency or remand the case for further proceedings or it may reverse or modify the decision if substantial rights of the appellant have been prejudiced because the administrative findings, inference, conclusions or decisions are:
(1) In violation of constitutional or statutory provisions;
(2) In excess of the statutory authority of the agency;
(3) Made upon unlawful procedure
(4) Affected by other error of law;
(5) Clearly erroneous in view of the reliable, probative, and substantial evidence on the whole record; or
(6) Arbitrary or capricious or characterized by abuse of discretion or clearly unwarranted exercise of discretion.
"In essence, if `competent evidence exists in the record, the Superior Court is required to uphold the agency's conclusions."Auto Body Association of Rhode Island v. State of Rhode IslandDepartment of Business Regulation et al.,
Accordingly, this Court will "reverse factual conclusions of administrative agencies only when they are totally devoid of competent evidentiary support in the record." Baker v. Dept. ofEmployment Training Bd. Of Review,
In order to act as an agent for the state, the "CRMC has been given authority to develop policies, programs and regulations that pertain to coastal areas." Strafach v. Durfee,
CRMC "Assent" is required for any alterations or activities that are proposed for tidal waters, shoreline features, and for areas that are contiguous to shoreline features. See
CRMP § 100.1. Contiguous areas are defined as "all lands and waters directly adjoining shoreline features that extend inland two hundred (200) feet from the inland border of that shoreline feature." Id. Thus, an Assent is required for the construction of a marina. Pursuant to Section 300.4A.3 of the CRMP, "marina" is defined as any "dock, pier, wharf float, floating business, or combination of such facilities that accommodate five or more recreational boats." The Council has promulgated *Page 8
a specific set of rules under the CRMP, establishing the procedures to be employed when an individual seeks to construct a new marina.See CRMP §
An applicant looking to build a marina located in a manmade shoreline is required to file a Category B application.See CRMP § 16-2-1:100. All Category B applications must go before the full Council, and the applicant must demonstrate, in writing, that all (11) requirements set forth in Section 300.1 of the CRMP are met. Once an applicant has filed a Category B application in compliance with the pertinent guidelines, a public notice is issued. See CRMP §
Furthermore, Section
In Arnold, applicants of medical assistance sought to enjoin hearing officers of the Rhode Island Department of Human Services (DHS) from engaging in ex parte off-the-record communications about contested cases currently before the DHS hearing officer.
Unless required for the disposition of ex parte matters authorized by law, members or employees of an agency assigned to render an order or to make findings of fact and conclusions of law in a contested case shall not, directly or indirectly, in connection with any issue of fact, communicate with any person or party, nor, in connection with any issue of law, with any party or his or her representative, except upon notice and opportunity for all parties to participate; but any agency member:
(1) May communicate with other members of the agency, and
(2) May have the aid and advice of one or more personal assistants.
The Arnold Court elucidated precisely which types of exparte communications are allowed and prohibited during the administrative adjudication of a contested case.Id. at 821. The Court stated:
*Page 11(1) §
42-35-13 of the APA prohibits ex parte communication with anyone about contested or material adjudicatory facts or opinions concerning the merits of an applicant's pending appeal. The function of this requirement is to prevent litigious facts from reaching the decision-maker off the record in an administrative hearing.
(2) §
42-35-13 authorizes hearing officers to engage in ex parte communication with agency staff members about general matters pertaining to the discharge of his or her duties.(3) In accordance with §
42-35-9 (e) and §42-35-10 (4), the hearing officer must provide notice to the parties before a hearing if he or she intends to consult any documentary source or person concerning facts or opinions about the merits of an appeal. In addition, the parties must be afforded an opportunity to contest any such evidence and to cross-examine any people consulted. This is similar to the regulations followed by many federal agencies.(4) All evidence that is received or considered must be on the record. This basic requirement, which facilitates judicial review, is consistent with current DHS regulations. Id.
Importantly, the Arnold Court stated that all evidence received or considered must be on the administrative record.Id. The court summarized:
Unless the parties are given notice and an opportunity to respond on the record, including cross-examination, if appropriate, a DHS hearing officer may not communicate with anyone, including DHS staff members, about contested adjudicatory facts. . . . All facts and opinions, including opinions of agency professionals and staff, as well as information obtained from an outside source . . . must be included on the record if the hearing officer plans to base his final decision on such facts. In short, no litigious facts should reach the decision-maker off the record in an administrative hearing. . . . Id.
Thus, the Arnold Court upheld the trial justice's finding that the APA prohibits "hearing officers `from engaging in exparte communication with anyone, whether inside or outside the agency, about facts or opinions of an applicant's pending case' and requires that applicants receive notice and an opportunity to challenge all sources of evidence received or considered."Id. at 819; see also Thibaudeau v. Thibaudeau,
In the present case, Appellants cite various findings in the CRMC decision that purportedly demonstrate that the CRMC relied upon evidence prohibited under Arnold. Appellants contend that they were not provided notice or the opportunity to contest and cross-examine such evidence. However, the reports and testimony of Director Fugate and other CRMC staff did not constitute prohibitedex parte communications in violation of §
Our Supreme Court did not intend that the principles ofArnold apply to on-the-record testimony such as this. Therefore, this Court concludes that the evidence relied upon by the Council did not constitute ex parte communications under Arnold. Because all evidence considered by the Council was on the record, and Appellants were afforded the opportunity to respond on the record, this evidence was not in excess of the statutory authority of the agency and its findings were not made upon unlawful procedure. See Arnold,
Appellants also dispute several of the Council's findings of fact that rely on information obtained from CRMC staff through pre-hearing staff reports, depositions, and testimony at hearings.See id. at ¶¶ 19-24, 26-27, 31. In one instance, Appellants argue that the CRMC's reliance upon the testimony of CRMC Executive Director Fugate was in violation of Arnold. (CRMC Decision at ¶¶ 8-10, 12.) The Council adopted the findings made by Executive Director Fugate, including, for example, his statement that the work associated with the bulkhead is treated as maintenance work pursuant to CRMP Section 300.14. Seeid. at ¶ 9. Other findings of fact disputed by Appellants were derived from staff reports that were readily available to Appellants in the administrative record. For example, Appellants contend that the Council improperly relied upon the CRMC's staff conclusion that the dredging standards set forth in the CRMP for the project have been met. See id. at ¶ 23. The hearing transcripts reveal that Executive Director Fugate testified on the record at several hearings that the bulkhead work was treated as maintenance work under CRMP Section 300.14. (Hr'g Tr. 83-84, March 19, 2005; Hr'g Tr. 75-76, May 3, 2005.) Similarly, the Council evidently relied on Staff Engineer Goulet's on-the-record deposition, as well his pre-hearing report, to support its finding that the CRMP's dredging standards were met. (Admin. R. at 8; Goulet Dep. 118-20, March 28, 2005.)
This Court finds that these examples of on-the-record evidence are not the types of evidence that our Supreme Court sought to guard against in Arnold. Unlike Arnold and the other cases applying these principles, Appellants have presented no competent evidence that any facts significant to this litigation reached the Council off the record. See Champlin's Realty,
Pursuant to G.L. 1956, §
The Council made numerous findings of fact with respect to the navigation concerns expressed by Appellants. (CRMC Decision at ¶¶ 41-52.) The Council found that the evidence presented by the Applicant was more credible than the evidence presented by Appellants on the issue of whether a sufficiently safe distance existed between the proposed marina and the ferry *Page 15
dock. Id. at ¶ 43; see Mendonsa v. Corey,
It is clear that the Council's findings of fact regarding navigation safety are based upon competent evidence in the record.See Environmental Scientific,
Appellants also argue that the CRMC did not give proper weight to evidence demonstrating the presence of navigational dangers. Appellants point to testimony like that of Captain Joseph Welch, who operates the Nelseco ferry. Captain Welch testified as to the potential for mechanical failures and the risk of running aground in the area of the new marina. (Hr'g Tr. 15-16, 18-19, April 19, 2005.) Captain Welch opined that because of the risk of mechanical failures, the proposed marina posed a safety hazard to navigation.Id. at 19-20. Appellants cite various other testimonies on the record to support their asserted safety and navigational concerns.
Despite this conflicting evidence, however, this Court finds that there was competent evidence in the record upon which the CRMC based its decision on the issue of navigational safety. SeeMendonsa v. Corey,
The Council made several findings of fact with respect to the issue of homeland security. The Council found that the CRMC staff was advised by the Coast Guard that they were not going to intervene or recommend any action in the matter. (CRMC Decision at ¶ 36.) The Council based this finding on Mr. Goulet's testimony that he received an email from Commander LeBlanc of the Coast Guard, asserting that the Coast Guard had no plans to intervene. (Goulet Dep. 61, March 28, 2005.) The Council found that the presented evidence demonstrated that the concerns raised by Appellants occurred during Maritime Security (MARSEC) Level II conditions, which occur infrequently. Id. at ¶ 37. The Council also found that the evidence demonstrated that even at MARSEC Level II, access to vessels is specific to the area, vessel, and facility.Id. at ¶ 40. The Council stated that it heard conflicting testimony from various experts as to whether the proposed marina would impede or help meet new homeland security requirements set forth by the federal government. Id. at ¶¶ 38-39.
It is evident that the Council's finding was based in part on the conflicting testimony of Captain McGurl and company security officer of Interstate Navigation, William McCombe. Mr. McCombe testified that before the construction of the proposed marina, the area between the ferry dock served as a buffer zone where suspicious activity was more visible. (Hr'g Tr. 23-24, May 3, 2005.) Captain McGurl, on the other hand, expressed his opinion that the marina could actually increase homeland security as a result of the presence of tied up and signed in boats, as opposed to unidentified boats on moorings or anchors. (Hr'g Tr. 77, May 9, 2005.) The Council found that given the congested nature of Old Harbor and the existing conditions, there is *Page 18 no detrimental impact to vessel security as a result of the proposal of purposes of the CRMP. Id. at ¶ 40.
This Court finds that the Council's findings of fact on the issue of homeland security are based on competent evidence in the record and support the CRMC's decision. See Champlin's Realty v.Tikoian,
The record evidences that Executive Director Fugate advised the Council that all relevant activities associated with the proposed marina were being performed below mean high water, and therefore, in his opinion, the Applicant was not required to seek any local approvals. (Hr'g Tr. 50, March 29, 2005.) The Council adopted this finding. (CRMC Decision at ¶ 8, 10.) Marina consultant Ken Kubic also testified that all of the work to be done by the Applicant would be below the mean high water mark. (Hr'g Tr. 60, March 29, 2005.) *Page 19
The Council also adopted Executive Director Fugate's statement that the work related to the replacement of the bulkhead was treated as "maintenance" pursuant to CRMP Section 300.14, and therefore, no applicable local approvals were required.Id. at ¶ 9, 10. Section 300.14 of the CRMP defines maintenance as: "rebuilding, reconstructing, repairing, or reestablishing to previously approved conditions and dimensions a damaged or deteriorated structure or facility." Executive Director Fugate testified at the May 3, 2005 hearing that the replacement of the bulkhead was clearly "maintenance" because it was a replacement of an existing bulkhead rather than a new construction project. In addition, the Council relied on Executive Director Fugate's testimony that, there were no applicable state or local standards related to bulkhead replacement, and thus, CRMC 300.14 was the only pertinent regulation that the Council should take under consideration. (CRMC Decision at ¶ 9; Hr'g Tr. 76, May 3, 2005.) Accordingly, the Council's decision is supported by legally competent evidence.See Milardo,
The Council also adopted the findings of Executive Director Fugate and the Town of New Shoreham with respect to the necessity of local approval for upland parking. (CRMC Decision at ¶ 10) (stating that "all local, state, or federal ordinances must be complied with"). Executive Director Fugate and the Town of New Shoreham represented that local approval would only be required if upland parking was required or if there were infrastructure activities taking place on the upland, which the Applicant stated was not going to take place. (Hr'g Tr. 64, March 29, 2005); see Champlain'sRealty Associates L.P. v. Tillson,
When rendering a decision, the Court remains mindful that "[a]dministrative agencies retain broad enforcement discretion and, as always, considerable deference is accorded to such agencies about how to enforce regulations." Arnold,
Here, the Council's adoption of Executive Director Fugate's findings was within their statutory authority.See Section
While the CRMC was free to disregard the recommendations made by Director Fugate, its adoption of his findings is clearly supported by adequate evidence on the record. See id. These technical questions such as the potential environmental impact of the marina and the impact of any dredging, were properly addressed and synthesized by Director Fugate for the Council's review. Seeid. Where both the Executive Director and CRMC Council reached the same conclusion after analyzing the evidence presented to them, this Court will give deference to the CRMC's decision. Seeid. Furthermore, after reviewing the record, this Court is satisfied that the CRMC's decision was based on legally competent evidence within the record. See Milardo,
The Council found that that no dredging variance was necessary because there was no CRMP standard requiring that all dredging associated with a marina project is accomplished within the marina perimeter limit. (CRMC Decision at ¶ 12.) The Council based this finding on testimony from Executive Director Fugate, who stated that a dredging variance was unnecessary. (Hr'g Tr. 35, June 28, 2005.) Therefore, the CRMC determined that the Applicants needed only to obtain variances for parking and the federal channel setback pursuant to CRMP § 300.4. (CRMC Decision at ¶ 12.)
CRMP § 300.4.E.1(j) requires that a marina shall be set back three times the authorized project depth from federal channel navigation projects. With respect to the setback variance, the Council found that although the normal setback would be forty-five feet given the channel depth, the evidence demonstrated that the existing jetty was already within twenty feet of the federal channel.Id. at ¶¶ 28-29. The Council found that reports from the CRMC staff and evidence before the Council demonstrated that the Army Corps of Engineers was willing to accept the setback of twenty feet from the federal channel without any navigational concerns.Id. at ¶ 31. This finding was based on Mr. Goulet's pre-hearing report and deposition testimony, as well as testimony from marina consultant, Ken Kubic. (Admin. R. at 4.; Goulet Dep. 43-44, March 28, 2005; Hr'g Tr. 31, March 29, 2005.) Therefore, the Council ultimately found that based on the evidence before it, and notwithstanding the evidence presented by Appellants, it did not have any navigational concerns regarding the setback variance from the federal channel. (CRMC Decision at ¶ 32.); see Larue v.Registrar of Motor Vehicles, Dept. of Transp., Office of OperatorControl,
CRMP § 300.4.E.1(b) requires one parking space for every 1.5 boats and one parking space for every 1.2 employees. The Council found that the evidence demonstrated that the proposed marina would be a transient marina located on an island, and the marina's patrons would typically arrive by boat and not require permanent parking.Id. at ¶ 33. The Council based this finding on the testimony of Paul Filippi, who, as owner of Ballard's Wharf Realty was familiar with the area in question. (Hr'g Tr. 97, April 19, 2005.) Mr. Filippi described the Ballard's Wharf Realty's business plan to rent only to transient boaters. Id. Thus, the Council found the evidence demonstrated that any parking associated with the project would be temporary and that there was sufficient parking within the vicinity. (CRMC Decision at ¶ 34.) The Council found that the evidence before it demonstrated that there was no parking available within the parcel to satisfy the standard set forth in the CRMP. Id. ¶ 35. The Council also found that the Applicant's proposed requests for the parking variance met the requisite criteria. Id. at ¶ 53; see Larue,
This Court finds that there is reliable, probative, and substantial evidence on the record to support the CRMC's grant of the Applicant's setback and parking variance requests. This Court is tasked with applying an evidentiary test which is not satisfied by "any" evidence but only that which is determined, from a review of the record, has probative force due to its competency and legality.Salve Regina College v. Zoning Board of Review of the Cityof Newport,
In this case, the Council considered the testimonial evidence of Mr. Filippi, who has extensive knowledge of the property in question, the business plan of Ballard's Wharf Realty, and the parking in the area, due to his ownership interest in Ballard's Wharf Realty. As such, the *Page 24 CRMC's decision demonstrates that the Council considered competent evidence in the record, to support its findings of fact.
For the foregoing reasons, the decision of the CRMC dated October 28, 2005, which granted Ballard Wharf Realty, LLC f/k/a Marion C. Filippi's application to build a new marina providing for eight new boat slips, is affirmed. Counsel shall confer and submit forthwith an agreed upon form of order and judgment that is consistent with this Decision.