E.W. Burman v. Bradford Dyeing Assoc.
Opinion of the Court
Burman submitted a bid for $1,646,430.00 of which $120,000.00 represented profit. (Burman Aff. ¶ 11.) Burman's bid included "[r]emoval and disposal of machinery, piping, conduit, and electrical wiring in fire affected area" at a price of $48,126.00 and "[removal] and [disposal] of the roof and supporting structural elements. Construction of new roof and supporting structural elements" at a price of $1,598,304.00. (Pl.'s Mem., Ex. B.) Following its bid submission, Commonwealth asked Burman when it could start the project and when it would be completed. (Burman Aff. ¶ 12.) It is uncontroverted that Commonwealth emphasized to Burman that Bradford wanted to complete the repairs at the "earliest possible date" and that the project was to be completed on a "fast-track expedited basis." Id.
On August 23, 2007, Bradford accepted Burman's bid and awarded Burman the contract. Later that day, Commonwealth contacted Burman to explain the method of payment on the project. The parties arranged a meeting for August 27, 200 to finalize the details of the contract. (Burman Aff. ¶ 13.)
It is uncontroverted that, on August 27, 2007, at a meeting attended by representatives of Burman, Bradford, Commonwealth and Liberty Mutual, as well as Bradford's attorneys, Bradford verbally awarded Burman the contract. (Burman Aff. ¶ 14.) It is also uncontroverted that as of that date, Bradford and Burman had agreed that Burman would perform the work, had agreed on the scope of the work, and had agreed on the contract price of $1,646,430.00. (Burman Aff. ¶ 15.)
Burman contends that the parties then began the process of drafting a written contract to reflect their agreement. The parties used modified versions of the Form and the AIA A201 *Page 3 General Conditions of the Contract for Construction. The parties exchanged a draft contract as of September 10, 2007 that contained the following material terms: a contract price of $1,646,430.00 with the work to include "repairs sufficient to allow owner to utilize the building as a functioning business facility." (Pl.'s Ex. C, 2.) In addition, the draft contract provided:
(1). Substantial completion was December 31, 2007;
(2). An incentive payment of $10,000 would be awarded to Burman if it completed the Project by December 17, 2007 (with a $2,500 daily payment for each day Burman completed the Project prior to December 17, 2007); and
(3). Liquidated damages of $5,000 per day would be imposed for each day the Project was late.
(Pl.'s Mem., Ex. C.)
Burman argues that, around this time, Commonwealth had knowledge of and gave consent to Burman's ordering of materials. Conversely, Bradford contends that neither Bradford nor Commonwealth authorized Burman to enter into contractual relationships with subcontractors or material suppliers for the purchase of materials for the [p]roject. (Grills Aff. ¶ 10; Clarke Aff. ¶ 9.)
On September 6, 2007, Burman submitted a purchase order to Reliable Truss Components, Inc. in the amount of $825.00 that authorized it to proceed with the shop drawing process. (Burman Aff., Ex. J.) It is uncontroverted that in response to Burman's September 11, 2007 e-mail requesting information regarding orders for specialty bolts and fasteners to be used for the project, Commonwealth responded substantively to Burman's questions knowing that Burman was relying on these answers in purchasing materials. (Burman Aff., Ex. E.) It is also uncontroverted that on September 13, 2007, with the knowledge of Bradford and/or Commonwealth, Burman issued a $61,800.00 purchase order for customized steel items from Shawmut Metal Products, Inc. (Burman Aff., Ex. J.) *Page 4
Commonwealth communicated with Burman regarding its progress. In response to a September 17, 2007 e-mail from Burman indicating the need for an on-site visit, Commonwealth gave feedback on Burman's field shop drawings, but also informed Burman, "[a]s there is no signed contract, all work done to date and until a contract is signed is at [Burman's] own risk." (Clarke Aff. ¶ 10, Ex. A.) This communication occurred after Commonwealth had authorized Burman explicitly and implicitly to go forward with the project and order materials needed to proceed with the renovation work.
Following a hiatus due to unrelated issues between Bradford and its insurance carrier, it is uncontroverted that on October 23, 2007, Commonwealth told Burman that the "project [was] okay to go." (Burman Aff. ¶¶ 23-24; Burman Dep. pp. 2000-219.) On October 24, 2007, Bradford sent what Bradford referred to as "final versions" of the A101 Contract and the A201 General Conditions to Burman. (Pl.'s Mem., Ex. G.) It is uncontroverted that these draft forms contained "a few revisions, including the deletion of the incentive and liquidated damages provisions, and pushed back the date of substantial completion until February 28, 2008 to accommodate the delays with the insurance company from early September to late October, 2008. The scope of work and contract price remained unchanged, consistent with all prior iterations of these documents." (Burman Aff. ¶ 25.) It is undisputed that the parties never signed this written contract.
Through a series of e-mails between Burman and Commonwealth, those parties scheduled an on-site visit to Bradford for October 25, 2007. (Burman Aff. ¶ 24, Pl.'s Ex. F.) It is uncontroverted that Burman visited Bradford to take field dimensions with the knowledge and consent of Bradford. (Id.; Burman Dep. pp. 200-219.) On October 30, 2007, with the *Page 5 knowledge of Bradford and/or Commonwealth, Burman placed a $50,755.73 fastener order with Tri-State Fasteners, Inc. (Id.; Pl.'s Ex. J.)
Subsequently, on November 12, 2007, Bradford notified Burman that it had altered the roof design for the project. (Burman Aff. ¶ 29.) The work related to the disposal of the damaged roof and construction of a new roof — items that constituted the majority of Burman's bid price. Indeed, all but approximately $48,000.00 of the $1,646,430.00 total contract price to be paid to Burman was for the work Burman was to perform related to roof construction. As a result, Burman was forced to cancel and/or modify certain material orders that it had placed. (Burman Aff. ¶ 29.) Burman was unable to return some materials that it already had received. On December 19, 2007, Burman issued an invoice to Bradford for $99,987.32 — the cost of the non-returnable materials ordered for the original roof design, the labor expended to date, and Burman's contractual fee of 8%. (Burman Aff. ¶ 30, Ex. J.)
Bradford never paid this invoice and refused to go forward with the project. Burman alleges that Bradford thus breached its agreement with Burman. Burman argues that it sustained damages of $99,987.34 (the unpaid invoice), lost profits of $120,000.00, plus interest, costs and attorneys' fees. Burman argues that its damages exceed $200,000.00.
Conversely, Bradford argues that the parties never entered into a valid and enforceable contract. According to Bradford, although the parties began negotiating a written agreement, Burman never received authority or approval from Bradford or Commonwealth to enter into contractual relationships with subcontractors or material suppliers. Rather, Bradford alleges that the e-mail that it sent to Burman on September 17, 2007 specifically informed Burman that any work performed by Burman as of that date and until the parties signed a written contract would *Page 6 be at Burman's own risk. Bradford asserts that neither it nor Commonwealth ever told Burman otherwise during the course of the parties' negotiations.
After the commencement of this action, Bradford ceased operations at its facilities. As a result, Burman filed a motion for prejudgment attachment in an effort to secure its ability to satisfy any judgment that it might receive against Bradford for breach of contract, arguing that it has proven a likelihood of success on the merits of its contract claim and a demonstrated need for security.
On April 9, 2010, this Court first heard Burman's motion to attach. At that time, this Court denied the motion without prejudice, not reaching the disputed issues between the parties as to whether, more likely than not, they had a contract and whether Burman could prove a need for security. The Court instead enjoined Bradford from selling, transferring, or encumbering its property without giving Burman notice and an opportunity to be heard on its motion to attach.
Bradford later gave notice to Burman and the Court that it expected to enter into a purchase and sale agreement by which it would sell the majority of its real estate and equipment. At this point, Burman renewed its motion to attach and filed a motion to compel the production of documents for which Bradford had invoked the attorney-client privilege. The Court held the motion to attach in abeyance, with the agreement of the parties, pending the outcome of a hearing on the motion to compel. Pending decision on the motion to compel and the motion to attach, the parties agreed that Bradford would deposit proceeds from the sale of the property into the Court Registry. Bradford subsequently deposited $250,000.00 into the Court Registry pending decision on these motions.
With regard to the motion to compel, this Court conducted anin camera review of the subject documents, reviewed the memoranda submitted by the parties and then ordered Bradford *Page 7 to produce several additional documents. It also gave Burman time to review the additional documents and gave both parties an opportunity to supplement their memoranda with respect to Burman's motion to attach. Both parties subsequently filed supplemental memoranda. After consideration of Burman's motion for prejudgment attachment, affidavit, supplemental affidavit, exhibits, supporting memoranda of law, and Bradford's objection, affidavits, exhibits, and supporting memoranda of law, this Decision follows.
To address Burman's motion to attach, therefore, this Court first must determine whether Burman can establish a probability of success on the merits of its breach of contract claim. For Burman to meet this burden, it must demonstrate a likelihood of success as to the following:
(1). that a valid contract existed between Burman and Bradford;
(2). that Bradford breached that contract; and
(3). that Burman suffered damages as a result of Bradford's breach.
Petrarca v. Fidelity Cas. Ins. Co.,
If Burman establishes a likelihood of success on the merits of its contract claim, this Court then must determine whether it has established a need for security. This Court will address these issues in seriatim.
In response, Bradford argues that the parties never formed a contract. According to Bradford, "[i]t is undisputed that (a) the parties were negotiating a written contract for the Project and (b) the parties never signed the written contract." Bradford asserts that "the parties spent several weeks negotiating and exchanging drafts of a written contract, but never completed those negotiations and never signed the contract." (Def.'s Mem. 1.) Bradford asserts that "[p]arties who are actively negotiating the terms of a written contract have not expressed an objective *Page 9 intent to be bound by anything other than a completed and signed contract." (Def.'s Supp. Mem.3.) Bradford further alleges that Burman admitted in a deposition taken pursuant to R.I. Super. Ct. R. 30(b)(6) that the parties did not enter into a contract at their August 27, 2007 meeting. (Def.'s Supp. Mem. 3.) Bradford contends that Burman's breach of contract claim must fail because no contract was formed between the parties. (Def.'s Mem. 4.)
Bradford further contends that the draft agreement circulated by the parties stated that "[t]he Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreement, either written or oral." Bradford cites Ciaramella v. Reader's Digest Ass'n,
1. Existence of Contract
It is well-settled in Rhode Island law that a valid and enforceable oral agreement can be formed notwithstanding the absence of a signed written contract. See Smith v. Boyd,Additionally, the parties must manifest their objective intent to be bound by the agreement. See McGrath v. Rhode IslandRet. Bd.,
The determination of whether there was an objective intent to be bound by an oral agreement must be made on a case-by-case basis.See Smith v. Boyd,
In Smith v. Boyd, the Rhode Island Supreme Court of Rhode Island outlined various factors to be considered when determining whether a party's objective intent was to be bound before or upon execution of a written contract.
In Desimone, the Rhode Island Superior Court, on different facts, reached the opposite conclusion. C.A. No. PM 01-6077,
In a decision of the United States Court of Appeals for the Second Circuit, relied on by both parties in the instant case, the Court outlined several factors that are instructive in determining whether the parties manifested an objective intent to be bound before execution of a written agreement. Ciaramella, 131 F.2d at 323. These factors include: "(1) whether there has been an express reservation of the right not to be bound in the absence of a signed writing; (2) whether there has been partial performance of the contract; (3) whether all of the terms of the alleged contract have been agreed upon; and (4) whether the agreement at issue is the type of contract committed to writing."Id. at 323 (citing Winston v. Mediafare EntertainmentCorp.,
In considering this dispute in light of these precepts, this Court notes at the outset that the parties have not presented evidence as to all of the factors outlined in these cases.1 The cases are *Page 12 nonetheless instructive, however, on the issue of whether the parties here manifested an objective intent to be bound before execution of a written contract.
Initially, it is important to note in this case that Bradford presented the project to Burman as being on a fast-track schedule. Following the parties' August 27, 2007 meeting, Bradford not only had awarded Burman the contract, but also had determined the contract price, method of payment, and the scope of the work to be performed. While it is true that the parties did not enter into a contract at that meeting, that thereafter they began negotiating a written contract with a merger clause and, on September 17, 2007, Bradford, through its agent Commonwealth, instructed Burman that all work done before and after that date, absent a written contract, would be done at Burman's risk, Bradford's conduct was to the contrary. Before and after that date, Bradford, through its agent Commonwealth, maintained contact with Burman regarding its shop drawing and orders for materials. Indeed, Commonwealth specifically instructed Burman on October 23, 2007, that "the project was okay to go." The following day, Bradford sent to Burman the final version of the written contract. Within a week thereafter and with Bradford's knowledge, Burman visited Bradford to take field dimensions and placed a large fastener order. Thus, before Bradford notified Burman of its desire to change the roof design on November 12, 2007, Burman received the go ahead for the project; began ordering materials; hired an estimator, project manager and carpenter; finished a field shop drawing, submitted it to Bradford for approval, and received feedback on it from Bradford's engineer; completed an on-site visit; and finalized the written contract — all with the knowledge and consent of Bradford.
Although, as of this time, the parties still had not executed a final written contract, and their proposed written contract contained a merger clause, all material terms of the contract had been negotiated and agreed upon, including the price, method of payment, construction schedule, *Page 13 and the scope of the work to be performed. It is uncontroverted that by November 5, 2007, the "mere signing of the contract" was the only task remaining. (Burman Aff. ¶ 28.) Notwithstanding the absence of a final written contract, Burman had partially performed its obligations under the oral contract with Bradford, with Bradford's knowledge and consent.
Based on Smith, Desimone, and Ciaramella, this Court thus finds that Bradford exhibited an objective intent to be bound by its oral agreement with Burman prior to the execution of a written contract. Having reached an oral agreement as to the material terms of the contract, it encouraged and accepted Burman's part performance of that contract to ensure that the renovation work could be finished as quickly as possible.2
In addition, the evidence suggests that the parties not only agreed upon the work to be performed and the price for the work, but that they also agreed upon the method of payment and a construction schedule, outlining a timetable in which the work was to be performed. As in DeSimone, therefore, when the defendant showed the plaintiff the work to be performed and *Page 14
both parties agreed upon a price for the work, the evidence here suggests that the oral agreement between these parties was sufficiently definite to be enforceable.
2. Breach of Contract
The next issue this Court must address is whether Burman is likely to succeed on the merits of its claim that Bradford breached its oral agreement with Burman. See Petrarca,On November 12, 2007, Bradford notified Burman that it had altered the roof design for the project. This alteration caused Burman to cancel and/or modify certain material orders that it had placed with Bradford's knowledge and consent. Burman was unable to return some materials that it already had received and, on December 19, 2007, issued an invoice to Bradford for the cost of those materials. This $99,987.32 invoice represented the cost of the materials received, the labor expended, and Burman's contractual fee of 8%. (Burman Aff. ¶ 30.) Bradford refused to pay this invoice and refused to go forward with the project in November and December 2007. As a result, it is likely that Burman will succeed in establishing that Bradford breached its agreement with Burman for reconstruction of Bradford's fire damaged property.
3. Damages
Finally, in addition to proving the existence of a contract and breach, to succeed on its claim for breach of contract, Burman must prove damages. See Petrarca,With the knowledge and consent of Bradford and Commonwealth, in early September 2007, and in late October 2007, Burman began part performance of the contract, including ordering materials pursuant to the parties' construction schedule. Burman's December 19, 2007 invoice indicates that, up until November 12, 2007, when Bradford notified Burman of its desire to change the roof redesign, Burman had spent $99,987.34. This figure represents Burman's labor costs, including payment for its estimator and project managers ($1,762.00), its carpenter foreman ($1,593.87), as well as its cost for materials that it had ordered that it was unable to return ($89,225.00) and its 8% contractual fee ($7,406.47). (Pl.'s Mem., Ex. J.) Because Burman ordered these materials according to the parties' mutually agreed upon construction schedule and with the knowledge and consent of Bradford and Commonwealth, and could not return them, this Court is satisfied that Burman has proven a likelihood of being awarded damages for the materials and its related labor costs and contractual fee in the amount of $99,987.34.
In addition to its out-of-pocket costs, Burman also argues that due to Bradford's breach of contract, Burman lost its contractual fee of $120,000.00 on the entire contract and should be awarded accrued statutory interest and attorney's fees related to Bradford's breach. As this Court has found that Burman has established a likelihood of success on its claim for breach of its contract with Bradford, it necessarily follows that it has proven a likelihood of success on its claim for damages for its lost contractual fee or lost profits on the entire contract of $120,000.00, plus interest. *Page 16
Accordingly, Burman has proven a likelihood of success as to its claim for breach of contract, namely, that a valid and enforceable oral contract existed between it and Bradford, that Bradford breached that contract by refusing to go forward with the project and pay the materials invoice and that Burman suffered damages in excess of $200,000.00, plus statutory interest, as a result of Bradford's breach. The final question, therefore, is whether Burman has proven that it is inadequately secured with respect to its claim for breach of contract.
As to Burman's claim of inadequate security, Bradford argued at this Court's first hearing on Burman's motion for prejudgment attachment that, despite selling the property, equipment, and other tangible assets associated with the property, it still maintained an interest in two separate parcels of land located adjacent to the property that could provide Burman adequate security. Bradford asserted at the hearing that these two parcels were worth $67,000.00 and $147,000.00, respectively. Moreover, Bradford agreed not to sell or encumber these properties *Page 17 without giving Burman notice and an opportunity to be heard further regarding its need for security. In its response to Burman's supplemental memorandum, Bradford submitted more information regarding the value of these two properties which are located at 3 North Main Street and 5 North Main Street in Westerly, Rhode Island. The assessed values of these properties, according to Bradford, are $67,800.00 and $86,000.00, respectively. The assessed value of the more valuable property is thus substantially less than what Bradford had represented its value to be at the initial hearing.
Additionally, Bradford asserts that it is an operating entity with a fabric inventory valued at approximately $1,000,000.00. Bradford contends that it sold $100,000.00 worth of fabric last month. (Def.'s Supp. Mem. 2.) Bradford further asserts that "[w]hen and if [Bradford] decides to dissolve, its creditors are protected by the procedures for dissolution set forth in the Rhode Island Business Corporation Act." Id.
"Attachment for security reasons is appropriate when it appears likely that the plaintiff will have difficulty enforcing the judgment." Normandin v. Gauthier,
Similar to Long, it is undisputed here that Bradford has sold the property that was the subject of the contract at issue in this litigation. Further, it is uncontested that Bradford has *Page 18 ceased operations at its manufacturing facility and is currently selling off its $1,000,000.00 fabric inventory. There is no evidence that Bradford continues to manufacture or has plans to resume manufacturing operations in the future. Bradford is a current creditor of its successor company and maintains ownership of two unencumbered parcels of land with a combined assessed value of $153,800.00; however, the fair market value of these properties and the ease with which they could be liquidated to satisfy any judgment against Bradford are unknown.
The fact that Bradford's property at issue in this litigation has been sold, its manufacturing business has ceased operations, and its assets are currently being sold, demonstrates that Burman lacks security with respect to its claim against Bradford for breach of contract. This Court is not satisfied that the unrelated properties owned by Bradford provide sufficient security should a judgment ultimately be rendered in Burman's favor. The absence of proof of adequate security thus militates in favor of granting Burman its requested attachment.
Counsel shall confer and submit to this Court forthwith for entry an agreed upon form of order that is consistent with this Decision.
In addition, Burman's part performance, clear agreement with Bradford on all material terms of the contract (which was on the verge of execution), and Bradford's giving the green light, through Commonwealth, for the project — all occurring well after Commonwealth's e-mail warning that all work done by Burman prior to executing a written contract would be at Burman's risk and with no subsequent reiteration of that warning — further distinguish the instant case fromCiaramella (where there were multiple express reservations by a party not intending to be bound absent a written agreement) and Smith v. Boyd (where the Court relied on such an express reservation in the absence of partial performance and together with evidence of ongoing negotiations to find that the parties never progressed beyond negotiations to an agreement). This case, therefore, is more like DeSimone where evidence of part performance led the Court to enforce an oral agreement. Bradford should not be able to hide behind the absence of a written contract with a merger clause and an old e-mail to try to thwart enforcement of an oral agreement with Burman that Burman acted upon, prior to execution of a written agreement, as an accommodation to Bradford to meet its fast track project demands — especially where it appears that Bradford decided belatedly to abandon the project under the guise of a request for a new roof design.