Sjoberg v. P. E. Harding Construction Co.
Sjoberg v. P. E. Harding Construction Co.
Opinion of the Court
This is an action of trespass on the case to recover damages for personal injuries alleged to have been received through the negligence of the defendant.
The case was tried before a justice of the Superior Court sitting with a jury and resulted in a verdict for the plaintiff. At the close of the evidence the defendant moved that said justice direct a verdict in its favor. The justice denied said motion. The case is before us upon the defendant’s exception to said ruling.
*135 It appears from the transcript of evidence that on August 5th, 1912, the day on which said injuries were received, the defendant, as a contractor, was constructing in the city of Providence, a steel-frame building having brick walls, which building was to be about twenty-five feet in height when completed; that the plaintiff, as a carpenter, was an employee of the defendant working upon said building; that the brick walls of the building had been nearly completed, and the interior steel frame, including the framework of the main floor, was in place and bolted together. The framework of the main floor consisted of steel girders and cross girders with open spaces, between the cross girders. In the evidence, these open spaces are called bays and according to the testimony of some witnesses were about ten feet across. The permanent floor was to be of concrete, but had not been laid on said August 5th. The plaintiff had been employed by the defendant for about three weeks previous to said day and had been working in an open lot near said building making wooden frames or forms to be used in the concrete construction about the building. George D. Miller was the defendant’s superintendent having full charge of the work. On the day in question at about half after ten o’clock in the forenoon Mr. Miller directed the plaintiff to go to work upon the roof. To get to the roof the plaintiff was obliged to pass over a so-called run or way, placed upon the steel girders of the main floor, to a platform consisting of three planks laid side to side across two steel floor girders and over one open space or bay. The plaintiff was then obliged to go up a ladder to the roof. The foot of said ladder was placed in the lip of a steel girder, which was not a part of the permanent construction of the floor, but was laid across the steel floor girders. The ladder was further held securely by being tied with a rope to the steel framework at the roof. Before noon the plaintiff left his work on the roof, came down said ladder and across the platform and then returned to the roof in safety. At twelve o’clock noon the plaintiff came down the ladder again; and, when he stepped from the ladder to the platform, the *136 plank on which, he stepped in some manner became displaced from the girders, on which it had rested; the plank and the plaintiff fell into the cellar; and the plaintiff was severely injured.
The defendant based its motion for the direction of a verdict in its favor upon the claim that the evidence showed that the plaintiff had passed over the platform three times before the accident, must have seen the manner in which the platform was constructed and hence the plaintiff in using the platform had assumed the risk of any displacement of the planks; also that according to the testimony the plaintiff was plainly guilty of contributory negligence in stepping from the ladder to the platform without first satisfying himself that the planks were securely placed upon the girders; and further that the evidence failed to disclose any negligence on the part of the defendant.
The negligence of the defendant, which the plaintiff alleges, is that the platform was improperly and carelessly constructed because made of planks which were not long enough to cover two open bays and rest on three floor girders, and also because the platform was not securely fastened to the girders on which it rested. The first of these alleged grounds of negligence may be disregarded. The floor frame was fully disclosed to view, and it was perfectly apparent, upon a superficial glance, that the planks of this platform did not rest upon three floor girders and that they were not long enough to do so. The plaintiff must be held to have assumed the risk arising from using a platform which rested on two girders only.
*139 Although generally the master is not responsible for defects in temporary stagings, for the making of which he had furnished suitable material and competent workmen, yet the fact that a servant is injured through a'defect in such a staging is not conclusive of the master’s freedom from liability. For if the master undertakes to erect the staging himself and it is built under his direction, or if he furnishes it to the workmen for use as a completed structure he is responsible for its safety. Also if the master has actual notice of a defect in a temporary staging, which later causes injury to one of his workmen, who in the exercise of due care is ignorant of it, which defect is due to the negligence of a fellow servant of said workman, or if the circumstances are such that the master should be held to have constructive notice of the danger, .and if the master neglects to remedy the defect and permits the workman to continue to use the staging without warning of the danger, then the master’s negligence, subsequent to that of the fellow workman of the one injured, must be held to be the proximate cause of the accident and the master will not be permitted to escape liability.
It appears from the testimony that the placing of the ladder .and the platform in position was not an incident of any particular work on the building; but that when, in the progress of the work, it became necessary for carpenters and other workmen to go upon the roof and to carry materials there, the ladder was placed and the platform was laid. The only testimony in the case which states how said platform came to be built is that of the defendant’s superintendent, Mr. Miller, as follows: 71 Q. “How did that ladder and planks happen to be put in place there?” A. “I told the men to put it up so to get to the roof; the only way we had to get up,” and again, 74 Q. “And what did you tell the men whom you had do that work?” A. “Told them to put a ladder up there so they could get up on the roof.” 75 Q. “And what about the platform?” A. “Put a plank there for them to land on, step oh when they came down.”
The evidence, therefore, presented fair questions to be submitted to the jury as to whether the platform was reasonably safe for the use to which it was to be put; whether the-plaintiff should be held to have assumed the risk of any defect in its construction; whether he was guilty of contributory negligence in his manner of using it; whether the defendant had undertaken to construct the platform and furnished it to the plaintiff as a completed structure; and whether the defendant had notice of the condition of the platform before-he directed the plaintiff to use it.
The defendant’s motion for the direction of a verdict in its favor was properly denied. The defendant’s exception is overruled. The case is remitted to the Superior Court for the entry of judgment on the verdict.
Reference
- Full Case Name
- Victor D. Sjoberg vs. P. E. Harding Construction Co.
- Status
- Published