Bova v. Scorpio
Bova v. Scorpio
Opinion of the Court
Each of the above entitled actions is in assumpsit to recover upon an alleged special promise and undertaking of the defendant, and also to recover for work and labor allegéd to have been performed at the request of the defendant.
The three cases were tried together before a justice of the Superior Court, sitting with a jury, and resulted in a verdict for the plaintiff in each case. In each case the defendant filed his motion, for a new trial which was denied by said justice. Each case is before us upon the defendant’s exception to the decision of said justice upon the motion for new trial, and upon certain exceptions taken by the defendant in the course of the trial.
The claims of the plaintiffs, alleged in their respective declarations and presented in their testimony, are that each was employed by a general contractor as a painter to *99 work upon two houses which were being constructed or repaired for the defendant and were situated upon land of the defendant; that the plaintiffs’ work was in furtherance of a contract which said general contractor had with the defendant for the “construction, erection and reparation” of said houses upon his land; that at some time prior- to December 24, 1911, said general contractor abandoned the further performance of his said contract with the defendant; that the plaintiffs were about to commence legal process to enforce a lien upon said land and buildings for the wages due them from said general contractor for work upon said houses; that thereafter, on December 24, 1911, the defendant agreed with each of the plaintiffs to pay to him the wages due him as aforesaid if he would refrain from enforcing a lien upon said real estate, and each plaintiff, in consideration of this promise of the defendant, agreed that he would not commence lien proceedings as aforesaid and has kept said agreement; and said plaintiffs further claim that the defendant agreed with each of the plaintiffs that if said plaintiff would continue his work until a certain portion of said painting was finished, the defendant would pay him for his work in so doing; that thereupon the respective plaintiffs undertook to finish a certain portion of the painting remaining to be done upon said houses and that they have performed their undertaking but the defendant has failed to perform either of said agreements made by him with the respective plaintiffs and each suit is brought to recover the amount due the plaintiff upon these agreements of. the defendant. The first count of. the plaintiff’s declaration in each case alleges the breach of the defendant’s agreement to pay the plaintiff the wages due.him for labor upon said houses up to December 24, 1911. The second count alleges the failure of the defendant to perform his agreement to pay the plaintiff for labor performed on said houses after December 24, 1911.
The defendant’s first exception is to the refusal of said justice to direct a verdict for the defendant at the conclusion of the evidence. The ground of this motion of the *100 defendant was that the plaintiffs should not be permitted to recover- on the first count of their respective declarations because the plaintiffs’ evidence in support of said count shows that the promise of the defendant to pay the plaintiffs for their work prior to December 24, 1911, if such promise was made, was one to answer for the debt, default or miscarriage of said general contractor, was not in writing and was within the operation of the Rhode Island Statute of Frauds. And further, that the plaintiff should not be permitted to recover upon the second count-of their respective declarations for labor performed after December 24, 1911, because the evidence showed that they failed to perform the alleged agreement on their part, in that they had not completed the painting required to be done on said houses.
The defendant excepted to that portion of the charge of said justice in which he instructed the jury as follows: *101 “They must have substantially performed the contract as it was made between them and the defendant, and they must satisfy your minds by fair preponderance of the evidence of what the contract was, of the fact that they kept and performed that contract substantially in accordance with the agreement between the parties. In addition to that, if the defendant failed to keep his contract, but broke his contract, you would be entitled to give the verdict to the plaintiffs in these cases. If no contract was made, or if one was made, and the plaintiffs themselves broke it, did not complete the contract in accordance with the agreement, substantially, then they are not in a position to recover.” We find no merit in this exception.
The defendant has presented to us his exception to the decision of said justice denying the defendant’s motion for new trial in each case. From an examination of the transcript of evidence with reference to the written memoranda, claimed to be of the plaintiffs’ working time, and in other matters, there appears to us to be some force in the defendant’s criticism of the trustworthiness of the plaintiffs’ testimony. This criticism, however, relates to the credibility of the plaintiffs as witnesses, which was particularly a matter to be passed upon by the jury in the first instance and then by the justice presiding upon a review of the verdicts on the motions for new trial. Both the jury and said justice had the witnesses before them and upon the conflicting evidence have given credit to the statements of the plaintiffs. We do not feel warranted in disturbing the decision of said justice approving the finding of the jury upon the credibility of the witnesses and the weight of the evidence.
All pf the defendant’s exceptions in each case are overruled; and each case is remitted to the Superior Court for the entry of judgment upon the verdict.
Reference
- Full Case Name
- Pasquale Bova vs. Giuseppe Scorpio; Joseph Bova vs. Giuseppe Scorpio; Emilio Achetturo vs. Giuseppe Scorpio
- Status
- Published