PORREY, J.This action' is brought for the recovery of damages for a personal injury alleged to have resulted from the negligence of the defendant. When plaintiff rested -his case, the trial count directed a verdiot for the defendant,’ and, from the judgment entered thereon and an order denying a new trial, plaintiff prosecutes this 'appeal.
The grounds upon which the court directed the verdict agaihst plaintiff, as stated in defendant’s motion, are that there is no proof of actionable negligence on the part of the defendant, and that plaintiff bad assumed1 the risk incident to his employment.
Plaintiff testified that at the time of the accident causing the injury complained of he was working for the defendant as a helper in defendant’s roundhouse at Garretson; that it was his duty to run engines into the roundhouse as they camie in from the road and to coal and fire them up and get them ready to go out again; that on the evening of the accident he was getting a certain engine ready to go out on its run, and, while passing along the left side of said engine in the performance of his said duty, the 'blowout pipe on that side of the engine suddenly and1 without warning, emitted a large volume of hot water and steam *130which scalded plaintiff’s leg, thereby causing, a severe and possibly permanent-injury. He further testified that in the morning before the accident he had -discovered that the flues and blowout pipe of this engine were 'both leaking, -and that he. reported s'uch fact to .his foreman; that the foreman told ¡plaintiff, to- try and draw up the valve so it would not leak away all the water; -that 'he (plaintiff) did try to draw up the valve, but that Ire could not stop the leak, -and left it in the -same -condition that it was before he made the attempt, which fact he reported to the foreman; that the foreman said ¡he was going to have -it .repaired when it went to Sioux City. There was no master mechanic nor any repair facilities at Garretson at that time. Plaintiff further testified that he had,passed the blowout pipe several times while he was getting up steam and working about the engine; that he did not know there -was danger of a blowout, and that the foreman did not tell him there was danger of a blowout; that at the time of the -accident he had on between 80 and ioo pounds o-f steam; and that the more steam there was on the more the blowout pipe-leaked.
[1-3.] Defendant having moved for a directed verdict, the testimony on behalf of plaintiff must be taken -as true. But, admitting the facts to be as claimed by him, no actionable negligence on the part of defendant -is shown. Tihe fact that the valve on the blowout pipe was in a leaky condition in no- manner explains how the valve came to be open for -a single instant just at that particular time. There is nothing in the -evidence that tends to show any cause for the outburst of h-ot water and steam. It is-not a case where tire mere fact of the accident •implies negligence on the part of the employer. The burden is upon plaintiff to show that the defendant had been negligent in some manner and that such negligence was the proximate- cause of the injury. This he has wholly failed to do. The defect -complained of was not of such a nature that injury could- reasonably be anticipated from the -continued use of. the engine, and, if it bad been of such -a nature, the plaintiff, by the continued- use of the engine, assumed the risk incident to the defect. While the foreman may have promised to have the engine repaired, plaintiff knew that it could •not he repaired until it reached Sioux City. Therefore the assumption of the risk of a kno-wn defect did not shift from plain*131tiff to defendant until such time -as the engine could be taken to the place where such repair could be made.
No actionable negligence on the part of the defendant appearing from the testimony, there was nothing for the trial court to do but to direct a verdict for the defendant, and the judgment and order appealed from are affirmed.