Seley v. Tex. & St. Louis R'y Co.
Seley v. Tex. & St. Louis R'y Co.
Opinion of the Court
Opinion by
§ 87. Contract; subscription for construction of railroad; construction of; rules as to conditions in. Appellee sued appellant to recover a balance of $250 alleged to be due upon a subscription list executed by appellant to appellee. Appellant, by the terms of his subscription, bound himself to pay appellee the money whenever the line of appellee’s railroad should be located or established to, or within, the city limits of Wado, said money to be used and expended in constructing said road in McLennan county, and to be paid in such sums as' might be needed as the work progressed. Appellee bound itself to build and operate the line of railroad, and to complete and equip the same, within twelve months from the date of the contract. The contract was dated May 22, 1880. Verdict and judgment for the plaintiff.
At the time this suit was brought, the road had been completed, equipped and was running into the city of Waco, and had been completed nearly two years. It is contended by appellant, that time was of the essence of the contract; that the railroad failed to comply with its obligation in completing and equipping its road, and run-
In Front Street M. & O. R. R. Co. v. Buller, 50 California, 574, it was held: 1. The payment of money cannot be made dependent on the performance of a condition by the party to whom it is to be paid, which condition, by its terms, may not be performed until after the date at which the money is to be paid. 2. Courts are disinclined to construe the stipulations in a contract, to do certain things within a given time, in consideration of the payment of money by the otheF'party, as conditions precedent, unless compelled to do so by the express language of the contract. 3. If property holders along the line of a street contract with a street railroad company to pay it certain sums of money, if, within a certain time, it constructs a railroad along the street, the fact that the road is not built within the time is not an excuse for the
In Davis & Co. v. Cobban, 39 Iowa, 392, it was held that in a written instrument, by the terms of which the obligor became bound to pay a certain sum of money to a railroad company, when the road was completed, and the cars running between designated points, the words ‘ ‘ the road to be finished by the 1st of September’, 1882,” did not imply a condition precedent. The obligor was not released from payment by the fact that the road was not completed at the time fixed in that instrument. To the same effect is Traer v. Stuart, 16 Iowa, 15. We might multiply authorities, but these are deemed sufficient. There is no fact or circumstance of similarity in this case with Henderson v. R. R. 17 Tex. 560. Here the road was not only in process of bona fide construction, but the failure to construct it within the time stipulated is reasonably accounted for. More than that, the road was fully completed, and its trains running into Waco, long before this suit was brought.
§ 88. Verdict; will not be disturbed because it is contrary to an erroneous charge. A proper verdict will not be disturbed by the appellate court for the reason that it was rendered in disregard or contravention of an erroneous charge of the court. [Merriweather v. Dixon, 28 Tex. 16.]
Affirmed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.