Under the second and third assignments, the only matter stated as a proposition is what is stated in the third assignment, which is that the court erred in rendering judgment against defendant H. B. Thompson, because the uncontradicted evidence shows that if a contract was ever made it was with H. B. Thompson Company. The testimony amply supports the fact that the contract was with H. B. Thompson individually.
The fourth assignment is that the uncon-tradicted evidence shows that H. B. Thompson Company held a receipt, dated December 5, 1910, in full payment of account to date, signed by Ora Baird, and that this suit was brought on December 5, 1910, and therefore the judgment was error.
Judgment affirmed.