Slaughter v. Crisian Nesbit
Slaughter v. Crisian Nesbit
Opinion of the Court
C. C. Slaughter, appellant, made a written contract with Crisman *206 & Nesbit, appellees, by which the latter were to destroy an. old building on a lot belonging to Slaughter and erect a new one in place of it, and to make alterations and extensions to the existing building adjoining. At the conclusion of the work Slaughter held a percentage of the contract price stipulated to be reserved upon current payments and some items of extras done by the contractors were unsettled, and also items of credits owing Slaughter for work omitted by agreement; also Slaughter’s claim for damages for loss suffered because of the contractor’s failure to finish the work within the time stipulated in the contract. These matters, under a written agreement, were submitted to three arbitrators, two of whom were named in the agreement, and the third to be selected by them. An award was made by a majority of the arbitrators.
On April 22, 1910, appellees sued Slaughter on said award, attaching to their petition copies of the original contract, the agreement of arbitration, and the award. Defendant’s amended answer consisted of exceptions, a special plea that the arbitrators did not comply with the terms of the arbitration agreement in that two of them, without having selected the third arbitrator, determined such of the matters in controversy as they could agree upon, and then selected O. A. Gill as ■an umpire to determine such matters only as they had been unable to agree upon; also that the arbitrators did not place any witnesses under oath or affirmation; that said agreement provided that they should determine what amount Slaughter was entitled to by reason of plaintiffs’ failure to complete their contract within the time prescribed, namely, 217 days after getting full possession of No. 253 Main street, Dallas, Tex., which possession they procured March 15, 1909, thus making their time expire on October 18, 1909; that the work, was not completed until March 26, 1910, but arbitrators Gill and Watson permitted plaintiffs to plead and heard statements from them in evidence to the effect that defendant agreed with them orally before the signing of the contract that no damages would be claimed by him for a breach of said contract as to the time within which the work should be completed, and upon said plea and statement said two arbitrators held the written contract not binding upon plaintiffs as to such time limit for completing the work, and that the legal effect of said oral agreement was to abrogate the stipulation in the written contract requiring plaintiffs to complete the work in 217 days; that therefore plaintiffs were not liable for delay in completing the work, and said two arbitrators refused to consider Slaughter’s claim for damages on account of delay or the evidence offered thereon. Defendant further alleged that such construction of the contract was flagrantly erroneous and in contravention of the well-established rules of law that the terms of a written contract cannot be set aside or altered by proof of contemporaneous or antecedent oral agreements between the parties; that such construction of the contract, if enforced, would inflict serious damage to defendant, namely, in the sum of ?12,000, the amount he was entitled to have awarded by said arbitration. Defendant prayed that said award be vacated and set aside and plaintiffs relegated to whatever cause of action they had prior to the submission to arbitration. Defendant further answered with general denial allegation of delay by plaintiffs in completing the work, causing damage to defendant in the sum of 812,000, the value of the use of the building during the time of the delay; also claiming $997.75 for work omitted • by agreement and $80 for work which plaintiffs failed to perform and which defendant had done.
Plaintiffs filed a supplemental petition containing exceptions and setting up numerous claims of obstructions encountered by them in performing their work, and also setting up a claim for extras. A supplemental answer was filed consisting of exceptions which were sustained. Thereupon plaintiffs filed a trial amendment, to which the same exceptions were urged, but overruled. The Texas Glass & Paint Company filed an intervention for work done under contract with Crisman & Nesbit. The case was submitted to the jury upon special issues, together with special instructions, and verdict returned sustaining the award of the arbitrators and also finding on the special issues submitted with reference to the work done under the contract independent of the award. Judgment was entered in accordance with the award of the arbitrators, ignoring the findings of the jury in other respects; also foreclosing mechanics’ lien on the property, and giving interveners judgment for $1,615.68, and foreclosure of mechanics’ lien. Defendant appealed.
The agreement to arbitrate reads as follows: “Whereas, certain differences have arisen between O. C. Slaughter and Crisman & Nesbit, growing out of the written contract of March 6, 1909, between said parties, relating to the building of the Slaughter Annex *207 and alterations to the Slaughter building on Main street, Dallas, Texas; and, whereas, the matters in dispute relate to the following items: (1) The amount of extras, if any, to which Crisman & Nesbit are entitled. (2) The amount of deductions, if any, to which C. C. Slaughter is entitled. (3) The amount of damages, if any, to which C. C. Slaughter is entitled on account of delay in the prosecution and completion of the Work. Now, it is agreed -that the parties hereto will submit' to arbitration the said three matters in controversy between them. There is no dispute as to the amount of the original contract or the payments made thereon, and balance still unpaid upon the contract amounting to $18,-181.27. Erom that amount there is to. be added or deducted the amounts that may be found due by the arbitrators from C. C. Slaughter to Crisman & Nesbit and from Crisman & Nesbit to C. C. Slaughter, on account of the three items in controversy submitted to arbitration. And for the purpose of carrying out the arbitration, the matters in controversy, as aforesaid, are hereby submitted to three arbitrators, two of whom shall be W. Illingworth and A. Watson; these two shall select a third disinterested arbitrator. The three arbitrators shall proceed, in such manner as they may deem most convenient, to determine the said matters in controversy between the parties hereto; and for that purpose they may examine the building, plans, specifications, and other papers, and may hear such testimony, under oath or affirmation, as they may deem relevant. If, upon any matter in controversy, the arbitrators cannot all agree, the majority shall govern. The arbitrators shall make a written award in duplicate, to be signed by at least two of such arbitrators, determining the said three matters in controversy, and fixing the net amount due from C. C. Slaughter to Crisman & Nesbit or from Crisman & Nesbit to C. C. Slaughter, as the.case may be. Such award shall be final, and the parties hereto bind themselves to abide thereby and to comply at once with such award. The expenses of the arbitration shall be paid, one-half by each ■party to this contract. Witness our hands in duplicate this 30th day of March, 1910. Cris-man & Nesbit. J. S. Nesbit. C. C. Slaughter.”
The award reads as follows:
“To C. C. Slaughter, Owner, and Crisman & Nesbit, Contractors. Gentlemen: Your arbitrators, Alex Watson and W. Illingworth, met on the 6th of April and proceeded to investigate the claims for extra work done on the Slaughter building, and also the deductions due the owner for work and material omitted by the contractors. At the third meeting your arbitrators -agreed on the selection of C. A. Gil'l as the third arbitrator. After a thorough investigation of the amount due the contractors for extra work, we find they are entitled to the sum of $2,340.95. This amount included the different' items charged to emergency account, and we are informed that a cheek has been drawn in fa- • vor of Crisman & Nesbit for $357.65, which when accepted by said contractors will leave a net amount due them for extra work the sum of $1,983.30. We also find that C. C: Slaughter is entitled to the sum of $843.00 deductions for work not done by the con-' tractors as provided for by the plans, etc. In regard to the question of demurrage claimed by C. C. Slaughter, we, Alex Watson and C. A: Gill, do not think that his claim is substantiated, therefore we do not allow the. claim of demurrage. [Signed] Alex Watson. C. A. Gill.
“I respectfully dissént from this last finding only, and do not think that said finding is justified either by the contract or the evidence. [Signed] W. Illingworth.”
There is nothing bn the face of the award' to show that all three arbitrators did not. pass on all matters necessary to be decided. It recites that two of them proceeded to in--vestigate the different claims, but shows the selection of the third arbitrator at the third meeting, and then contains the findings of the three. It does not show that the three arbitrators failed to reinvestigate the matters already gone over by the two named in- the-agreement. Therefore there was nothing on the face of the award rendering it invalid. The assignments are overruled.
It is true the testimony of the arbitrators, introduced subsequent to the admission of the award, shows that in fact some of the matters agreed upon by the first two arbitrators were not investigated by the third one, who merely adopted their findings. We are of the opinion that appellant waived any irregularity in the manner of procedure adopted by the arbitrators by submitting to the two arbitrators his version of the conversation had at the time of the making of the contract. Sanders v. Newton, 57 Tex. Civ. App. 319, 124 S. W. 482. He could have declined to do so and insisted that they appoint the third arbitrator, and that every *208 thing be passed on by tbe three. Haying appeared and offered testimony both before and after tbe appointment of tbe third arbitrator, be took tbe chances of a favorable award and waived any irregularity in their method of procedure. Tbe assignment is overruled.
The arbitrators all testified they heard the testimony of Crisman, & Nesbit to the effect that Slaughter had agreed at the time of the signing of the contract to waive all damages for delay, whereupon the clause for liquidated damages of so much per day was crossed out, and also heard the evidence of Slaughter to the effect that he had only agreed to waive the portion calling for a stipulated sum per day for each day of delay, and had said, “Then we will have a contract that won’t specify any demurrage, but we will just simply let it rest upon what we can prove, if you are behind time.” Arbitrators Illingworth and Gill testified that, after hearing the statements of the parties, Watson and Gill construed the contract as not permitting the recovery by Slaughter of any damages for delay, and that .the question was not gone into on its merits, but upon their construction of the contract they refused to consider Slaughter’s claim for delay. Watson contradicted them, testifying in substance that, while he construed the contract as not permitting a recovery by Slaughter of damages for delay, yet that they went into the matter and considered his claim and the claim of the contractors for extra time on account of obstructions, and decided that the claims would about offset each other, and for such reason failed to allow Slaughter anything for delay.
The conflict in the testimony of the arbitrators made an issue of fact proper to submit to the jury to find whether or not they disallowed Slaughter’s claim for delay because they construed the contract, either by virtue of its provisions or when considered in connection with the evidence relating to *209 the discussions taking place prior to and at the time of its signing, to be of such character as not to entitle Slaughter to recover for delay. Bowden v. Grow, 2 Tex. Civ. App. 591, 21 S. W. 612. The court, .therefore, did not err in refusing the special instruction No. 1 asked by defendant, which was a peremptory instruction to disregard the award of the arbitrators. Special charge No. 1, requested by plaintiffs, was erroneous in that it failed to furnish the jury any guide to determine what would constitute such a mistake of law as was mentioned in the charge. The jury were called upon to form an 'opinion as to whether a mistake of law was made, but they were not told what the-law was, and certainly are not presumed to know the law, and therefore were in no position to pass on the matter.
Assignments 4, 5, and 7 are overruled. Assignments 6, 8, and 10 are sustained. Assignment No. 4 is only overruled because the special charge, upon the refusal of which it is based, does not require the jury, in addition to the other matters, to also find that Slaughter suffered damages by reason of delay in completing the building. If no damages were suffered, then no injury was done by any mistake made. It would not be proper to pass upon assignment No. 10, in view of another trial, as it involves the question of sufficiency of the evidence to sustain the award. Assignments 11 and 12 are overruled. Assignment 13 is sustained.
On account of the errors pointed out, the judgment is reversed, and the cause remanded.
Reference
- Full Case Name
- Slaughter v. Crisman & Nesbit
- Cited By
- 7 cases
- Status
- Published