Ft. Worth & D. C. Ry. Co. v. Read Bros. & Montgomery
Cases that cite this one
5 later published cases cite this decision.
- San Antonio, U. & G. R. Co. v. Hales (Tex. App. 1917)
- Southwestern Dredging Corp. v. Chicago, R. I. & P. R. Co. (Okla. 1934)
- McLendon Hardware Co. v. Black (Tex. App. 1924)
- Hales v. San Antonio, Uvalde & Gulf Railroad (Tex. 1922)
- Kansas City Southern R. Co. v. Reinman (Okla. 1917)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
The Ft. Worth & Denver •City Railway Company has appealed from a judgment in favor of S. R. Bourgeois foreclosing an alleged lien upon a spur track belonging to appellant, under and by virtue of the provisions of article 5640, Revised Statutes 1911, for work performed with tools and teams upon the spur track.
The railway company let the contract for the construction of said spur track to Read Bros. & Montgomery, who employed Bourgeois to do the work upon which his claim for lien was predicated. The jury made findings in ahswer to 45 interrogatories submitted to them, consisting chiefly of questions -of evidence rather than controlling issues in the case, and many of which are substantial duplicates of others, and these findings were supplemented by several additional findings by the trial judge. The suit was instituted "by Read Bros. & Montgomery against the ■railway company to recover the balance due for the entire work done under the contract, and Bourgeois intervened," praying judgment against the plaintiffs for the balance of $1,-136.83, due him from the contractors, and for a lien to secure the same, upon the spur track, against the railway company for such balance.
At a previous trial judgment was rendered in favor of the intervener against the plaintiffs for $1,276, with a foreclosure of lien against the railway company for $1,179 of that amount. From that judgment, an appeal was prosecuted by the railway company to the Court of Civil Appeals at Texarkana, resulting in a reversal of the foreclosure against the railway company, but leaving the judgment in favor of the intervener against the plaintiffs undisturbed; no appeal having been prosecuted from that part of the judgment. The opinion rendered upon that appeal is reported in 140 S. W. 111.
The trial from which this appeal is perfected was between the intérvener and the railway company alone. The jury found in favor of the intervener for the following items of account against the contractors, which were alleged in his petition:
Moving 6,000 yds. of dirt..$ 720 00
1,000 yds. of rock. 700’ 00
Four teams with men and tools on miles 3 and 4... 120 00
Clearing and grubbing 2.87 acres of land on mile 4 at $30.00 per acre. 86 10
Overhaul of dirt filling washout on mile 4.. 100 00
Hire of 8 teams and tools for 44 days working on mile 9 at $1 per day per team. 352 00
Tickets and freight charges. 25 41
Groceries returned... 62 00
$2,165 51
It was proven beyond controversy that the item of $352 was for the hire of intervener’s teams and tools by the contractors after in-tervener had completed the work undertaken by him and had discharged his employés, and that during the time the contractors used the teams and tools under this contract of hiring plaintiff did. not work with them; nor did he furnish any one to do so.
The jury found that the contractors "paid intervener $1,092.58 for the work done by him on the spur track prior to the time he hired his teams to the contractors, leaving a balance of $1,072.93 owing upon that work, which became due intervener January 1, 1908; that out of the amount paid to inter-vener $714 was paid out to his employés in full for labor performed by them before they were discharged; and the evidence conclusively shows, with no finding of the jury to the contrary, that the items for tickets, freight, and groceries were in fact paid by the contractors and charged to intervener’s account as advancements while the work done by intervener was in progress. The jury further found that the balance owing by the contractors represents only reasonable wages earned by the intervener by the use of his teams and tools, and by his own personal labor in working on the spur track and in superintending the work of his men *1029 while they were working on the spur track; and that intervener realized no profit from the labor of his men in excess of the amount paid them for their services, nor from his own labor and the use of his teams and tools over and above the reasonable value thereof. The jury further found that, while said work was being done by his men and by the use of his teams and tools, intervener superintended the work as foreman and worked with his men, either by laboring thereon himself, or by working in the blacksmith shop and procuring supplies for the use of his men and teams, or by acting as foreman of his men and in superintending the work while they were engaged in constructing the grade; but the jury were unable to determine what portion of the time intervener worked with his men, teams, and tools directly upon the grade and how much of the time he devoted to working in his blacksmith shop, and in and about his camp and procuring necessary supplies for the use of his men and teams and for the repair of his tools. However, they further found that the work which intervener performed in and about the camp and while going after supplies for his men and teams, while they were engaged in working on the grade, was necessary for the proper prosecution of said work.
The trial court held that intervener was not entitled to a lien for the item of $352 for the hire of his teams, but deducted that item from $1,072.93, the balance found to be due, and rendered judgment in favor of the intervener for a lien on the spur track for $720.93, the difference between the two sums last named, with 6 per cent, interest thereon from January 1, 190S
*1030 And for the reasons indicated already there is no merit in the second assignment of error, in which the contention is made that there is no support in the evidence for the finding of the jury that intervener realized no profit from the labor of his hired men; nor in the seventh assignment of error presenting the proposition that there is no support in the evidence for the jury’s finding that the balance due appellee represents only reasonable wages for himself and for the use of his teams and tools.
From the conclusions already stated, it follows that there was no error in overruling the appellant’s motion for a judgment in its favor' upon the findings of the jury, as insisted by the third and fourth assignments of error; nor was such judgment excessive, as insisted by the fifth assignment of error.
In answer to two interrogatories propounded to them, the jury found that the contractors made the payments to appellee without reference to how they were to be applied, and without designating to what part of intervener’s account against them the payments should be applied. But in answer to' other interrogatories they found that the full sum of $1,092.58 paid by the contractors was paid for work done by appellee upon the spur track to the time he discharged his employés and hired his teams to the contractors. No assignment is presented to these apparently conflicting findings.
The judgment is in all things affirmed.