Eastern Texas Traction Co. v. Harrison
Eastern Texas Traction Co. v. Harrison
Opinion of the Court
In July, 1913, the appellants White and Crotty were officially connected with the appellant Eastern Texas Traction Company; one of them as its president, and the other as its vice president and general manager. The Eastern Texas Traction Company was a private corporation organized to construct and operate an interurban railway between Greenville and Dallas. The appel-lees are the owners of property in Greenville; and for the purpose of securing the benefits resulting from the location and the maintenance of the office and terminal buildings of the traction company upon certain lots in the city of Greenville entered into the following contracts:
“In consideration that J. W. Crotty and Forest E. White will buy lot No. 1 in block 202 in Greenville, Hunt county, Texas, known as the J. B. Clayton’s corner on West Lee street, and lot No. 15 in block No. 202, immediately *303 south of said lot, known as the Mrs. Bessie Lit-, tie’s lot, and will construct and maintain on said lots the depot and terminal station buildings of the Eastern Texas Traction Company, the undersigned, as trustee for certain property owners who will be benefited by the location and maintenance of said station and office on said lots, and have subscribed the ¡¡>4,250.00 herein mentioned, agrees to pay to said Crotty and “White the sum of $4,250.00 on the purchase price of said lots, when the purchase of said lots is consummated by said Crotty and White. And the said Crotty and White hereby obligate themselves to buy said lots as aforesaid and .commence to erect thereon the station buildings “aforesaid, within a period of six months from this date, and complete same within twelve months from date hereof, and guarantee that the said Eastern Texas Traction Company will establish and maintain its said depot and terminal station on said premises; and they further guarantee that the said improvements on the said lots shall be at least the fair cost of $10,-000.00.
“This contract shall become effective when ratified by the said traction company by proper resolution entered on its. minutes, and its assent in writing appended hereto, and when a legal and sufficient guaranty for the faithful performance of their agreements by Crotty and White and the traction company is entered into; and upon full compliance by said White and Crotty with their covenant therein, said trustee shall execute to them a full release of this contract.
“Executed in duplicate this the 24th day of July, 1913. [Signed] J. W. Crotty.
“E. E. White.
“[Signed] C. M. Portwood.
“Bond.
“In consideration of the benefits to accrue to it and other good considerations, the Eastern Texas Traction Company hereby assents to and ratifies the foregoing contract on the part of Crotty and White, as to the location and maintenance of its depot and station terminals in the city of Greenville, and the said J. W. Crotty and Forest E. White, as principals, and the said Eastern Texas Traction Company, a corporation, and L. E. Birdsong, hereby jointly and severally acknowledge ourselves to owe and be indebted to C. M. Portwood, trustee, in the full sum of $5,000.00, payable to said trustee, at Greenville, Texas.
“The condition of this obligation is that whereas, if all of the aforesaid covenants and conditions as to the erection and construction and establishment and maintenance of the depot and station terminals on said premises is not fully performed, then the said Crotty and White will repay to said trustee, or his successor', for the benefit of the respective subscribers to said fund, the full sum of money so subscribed, with 8 per cent, interest per annum thereon, and all costs and expenses of collection, if any.
“Witness our hands this 24th day of July, 1913. [Signed] E. E. White. J. W. Crotty. Eastern Texas Traction Co., By E. E. White, President. L. E. Birdsong. Attest: [Signed] I. A. Miller, Secretary.”
At the expiration of the time stipulated no steps had been taken by Crotty and White to perform “their undertaking; and some of those who had contributed to the fund of $4,250 were unwilling to extend further time, and demanded the return of their portion of the contribution. The appellees were those who were willing to give more time, and accepted from Crotty and White the following obligation:
“Supplemental Agreement.
“It is agreed between J. W. Crotty and E. E. White, first parties, and C. M. Portwood, for himself and as trustee for the other subscribers to interurban station site bonus, second parties:
“(1) That Crotty and White will not repay to said trustee et al. the sum of $1,650.00 of the bonus heretofore paid them.
“That they will begin or cause to be begun in good faith the erection of the station and terminal buildings provided for in the original contract, on or before April 15, 1914, and complete the same within six months from that date.
“That they will pay interest on the $4,250.00 from July 24, 1913, to April 14, 1914, at 8% per annum, to be deducted from the $1,650.00 to be repaid by trustee et al.
■ “That the said trustee et al. agree to and hereby extend time for commencement and construction of said buildings to the periods aforesaid, and agree to repay said $1,650.00 to Crotty and White or their assigns, when the foundation of said buildings have been made and material on the ground and construction of walls shall have reached at least six feet in height, but the amount of interest aforesaid shall be deduet-■ed from the sum to be so repaid.
“Said Crotty and White will convey the lots to, and cause a further obligation to be made by the Eastern Texas 'Traction Company, for the construction and maintenance of its depot and terminal station upon said premises in said city of Greenville, as a condition tó being entitled to the said bonus.
“The original contract between the parties as to said matters is continued in force, except as amended hereby.
“Executed in duplicate this 29th day of January, A. D. 1914.
“[Signed] White and Crotty,
“By J. W. Crotty.”
It appears that the $1,650 referred to in this instrument was paid over to those of the original contributors who refused the extension of time. Before the expiration of the time limit last referred to Crotty and White had purchased the lots and had received the bonus of $4,250, but have never constructed the buildings contemplated, nor has the traction company ever established •its offices upon the lots mentioned.
The appellees instituted this suit against Crotty and White and the Eastern Texas Traction Company for the purpose of recovering the sum of their respective contributions to the bonus paid to Crotty and White, and interest thereon at the rate of 8- per cent, per annum as stipulated in the original agreement. They also asked that a resulting trust in the lots purchased by Crotty and White be declared in their favor. In a trial before the court' without a jury a judgment was rendered establishing, the trust as prayed for and awarding in favor of each of the contributors a judgment for that portion which he had contributed, together with interest thereon at the rate of 8 per cent, per annum from the time the contributions were made.
The judgment will accordingly be reformed and affirmed.