Oherbonnier v. Shirley
Oherbonnier v. Shirley
Opinion of the Court
Appellant, as assignee of the contract, sued appellee for damages in the sum of $740 by reason of appellee’s failure to deliver to appellant 60 tons of cotton seed f. o. b. cars at Lorenzo or Cedric. The contract was made between J. A. Bedinfield and appellee October 1, 1914, and the contract price of the seed is $12 per ton. Axipel-lant alleged the execution and assignment of the contract; that he afterwards sold 60 tons for future delivery to the Star Mill & Elevator Company at Amarillo; that appellee wholly failed to deliver the seed to appellant, putting him off from time to time under promise that delivery would he made; that appellant was at all times ready and willing to receive the seed and pay for same, and on or about April 1, 1915, was compelled to purchase 60 tons of seed in the open market at the place of delivery to fulfill his contract with the Star Mill & Elevator Company, for which he was forced to pay at the rate of $23.50 per ton. He also sued for traveling expenses to Lorenzo, Cedric, Amarillo, and to defendant’s home in looking after the matter.
The defendant’s answer, in addition to exceptions and general denial, alleged specially that defendant had made arrangements with one Arthur Kelsey, who was in the ginning business at Lorenzo, to deliver to plaintiff said 60 tons of seed, and that in pursuance of said agreement Kelsey did deliver the same during the month of November, 1914, on account of the defendant, which was a full settlement and discharge of the obligation sued upon. He alleged further in the alternative that plaintiff had never tendered to defendant the price of the cotton seed nor offered to receive the same, and that he was ready and willing to deliver them to appellant in the event delivery had not already been made. He further pleaded in the alternative that he had a special agreement with Bedingfield, as the agent of appellant, to the effect that appellant would furnish ears in which to load the seed at Lorenzo, and that plaintiff at no time procured cars in which said seed could be loaded, nor did plaintiff give defendant notice to have the seed ready for delivery and that cars would be forthcoming to receive them. i
By trial amendment defendant alleged that between November 15 and January 1, 1915. plaintiff was notified, through his agent, Bed-ingfield, that Kelsey would deliver for defendant to plaintiff 60 tons of cotton seed on Monday or Tuesday of the following week, and that Bedingfield agreed to notify plain *642 tiff and have cars ready for loading the seed, and that plaintiff was to notify Kelsey when he would receive the same; that plaintiff never at any time after said conversation notified defendant nor Kelsey that he would receive the seed. Plaintiff filed a reply denying the defendant’s second amended answer and trial amendment.
Por the erfors pointed out, the judgment must be reversed, and the cause remanded.
other oases see same topic and KEY-NUMBER in all Key-Numbered Digests and Indexes
Reference
- Full Case Name
- Oherbonnier v. Shirley.
- Cited By
- 2 cases
- Status
- Published